Leak Detection
at JFK Intl Airport, NY
Terminal 4
9 hydrant lines
5 separate test sections
2 concourses + hardstand
Isolation of fuel lines
Four isolation pits
16 surge suppressor pits
Test connections
HPVs and/or LPDs
Jumper hoses
Day/night scheduling
Vault access
Project Phase 3:
Transmission Lines
26 lines transmit fuel from Satellite Fuel
Farm to each terminal’s hydrant lines
3 or 4 transmission lines dedicated to
each of the 8 terminals
HCNA test connections made at Satellite
Fuel Farm
Coordinated with each terminal which
lines would be shutdown for testing
PA assisted HCNA in isolation procedures
Performed at each isolation vault adjacent
to terminals
When possible, multiple sections tested
simultaneously
JFK Transmission Lines
Example: Terminal 1
3 Transmission Lines
At least one line
allocated for fueling
operations during testing
Isolation vault accessed
in busy fueling apron
PA assistance
No contractor needed for
isolation requirements
Project Phase 4:
Fuel Farms
Charlie Fenton
Hansa Consult of North
America, LLC
200 International Drive
Bldg. 120
Portsmouth, NH 03801
T: 603.422.8833
M: 603.828.1670
F: 603.422.8865
cfenton@hcna-llc.com
www.hcna-llc.com
Fill F/S 7,8
Fuel Farm Overviews