Professional Documents
Culture Documents
Feasibility
Study,
Preliminary
Investigation
M A RYA M K H A L I D
D E PA RT M E N T O F C O M P U T E R S C I E N C E ,
B A H R I A U N I V E R S I T Y, I S L A M A B A D
What is Gantt Chart?
project where the activities are broken down and displayed on a chart
0 1 2 3 4 5 6 7 8 9 10 11 12
Duration(days) Column1
Gantt Chart with Predecessor Finish to
Start relationship
Activity Predecessor Duration
A - 3
B A 4
C B(FS2) 3
Gantt Chart with Predecessor Start-Start
relationship
Activity Predecessor Duration
A - 2
B A(SS) 3
C B 4
D C(SS2) 3
Gantt Chart with Predecessor Finish-Finish
relationship
Activity Predecessor Duration
A - 3
B A(FF) 2
C B(FF2) 3
D C 3
Gantt Chart with Predecessor Start to
Finish relationship
Activity Predecessor Duration
A - 3
B A(SF5) 3
C B 4
Lead Time and Lag time
When you add lead time to a task, work on that task overlaps work on its
predecessor. When you add lag time, you delay the start time of the
successor task.
13
Overview of Feasibility
A systems request must pass several tests, called a feasibility study,
to see whether it is worthwhile to proceed further
Overview of
Feasibility
Evaluating Feasibility
The first step in evaluating feasibility is to identify
and weed out systems requests that are not feasible
Operational feasibility
◦ Is the system a practical and effective approach?
SCHEDULE FEASIBILITY?
Preliminary Investigation P R E L I M I N A RY
I N V E S T I G AT I O N
• Places, Procedures,
Four P’s: Policies, and People
• Surroundings, Suppliers,
Four S’s: Systems, and Skills
Step 2: Define the Project Scope and Constraints
◦ Project scope
◦ Define the range or extent of the project
◦ Set project boundaries
Operational Feasibility
Schedule Feasibility
Feasibility
Matrix
Step 5: Estimate Project Development Time and Cost