1.

Work Scope

Main P/R Restoration : Steel Structure (All), Piping (67k DI/ 117k DI)

(1) Direct Operation Plan (3) RRW Direct Construction Work Scope
Area 2
Area 1 Area 2-2 Area 3
Discipline
1220
1600,1610
1040 1630  Work Volume
1620
-. S/S 470 TN, Piping 67,278 DI (1st&2nd Level, All Bypass Line)
Temporary TF-1
Civil
CB-1 Cat. Discipline Unit Volume Action by Remark
Building S/S P/R TN 246 Dae-Ah E&C  
Demo-
Steel Structure Cat.1,2,3
lition Piping TN 2,391 Dae-Ah E&C  
SMP2-2 Cat.4,5,6
Mechanical SMP-1 SMP-2 SMP-3
GS Direct P/R 246 Direct Const  
Piping S/S TN
Bypass 224 Direct Const  
Electrical E-1 Cat.1,2,3 1st,2nd
Restora- 50,100 Direct Const
Instrument I-1 Cat.5,6 Level
tion
Insulation Piping DI 3rd, 4th
Cat.4,5,6 50,767 (TBA)
Level
Painting SPIF-1 SPIF-2 SPIF-3
Bypass 17,278 Direct Const  
Fire Proofing
NDE NDE-1 NDE-2 NDE-3
Heavy Lifting HL-1  Early Work Execution Plan
-. FGS Filipino MP (Key Persons) Mob Date : End of December 2017
(2) Direct Construction Area -. Early works to done by other manpower immediately
Early work Manpower (supplied locally) Work Period
GS Direct Operation
MS support 20 workers (Inc. 5 scaffolder) 1 Month
(U1040)
By pass 26 workers (Inc. 10 scaffolder) 10 days

직영 Shop 세팅 17 workers (Inc. 10 scaffolder) 1 Month

 Construction Period (Restoration).


-. S/S : ’17. 12 ~ ’18. 9 (Total 10M)
 MS Support : End of Dec ’17 ~ Mid of Jan ‘18 (0.5M)
 By Pass : Mid of Jan 18 ~ End of Mar ‘18 (2.5M) /Except Platform
 P/R : Mid of Feb ‘18 ~ End of Sep ‘18 (7.5M)

-. Piping : ’18. 1 ~ ’19. 1 (Total 12M) / Welding Completion by ’18. 12


 Shop Welding : Start at ’18. 1 / Category No.1
 Field Welding : Start at ’18. 2
 By Pass : ’18. 1 ~ ’18. 4 (4.5M) / Including Test
U1040