PROJECT TITLE: COMPOSITE WORKS FOR CDWU-II PROJECT AT

IOCL,HALDIA REFINERY
NAME OF Work:- PILING,CIVIL & STRUCTURAL, MECHANICAL PIPING
WORKS,ELECTRICAL, INSTRUMENTATION AND OTHER ASSOCIATED
WORKS.

fOA NO: RHQCC/2021-22/FOA/087 DATED 03.09.2021

Schedule Project start date : 03.09.2021Schedule Project end date :


FOURTEEN MONTHs Form the of DATE OF FOA

Date:- 26.03.2022
1.HSE Performance
Weekly Safety Report for Period Ending Friday – 25.03.2022
Sl.
Description This Week Up to Previous Cumulative
No Week
A Work Hours (Staff + Workers) 25620 173228 198848
Total Work Hours Achieved so far 198848
Avarage Manpower (Staff + Workers) 366
B Safety Performance Indicators
Fatality Nil Nil Nil
Recordable Incidents

Medical Aid Nil Nil Nil


Injuries & Illnesses

Days away from Work Nil Nil Nil

Restricted work day case Nil Nil Nil


First Aid

Case   Nil Nil Nil


Near Miss Nil Nil Nil
Property Damage Nil Nil Nil
Environmental Damage Nil Nil Nil
Motor Vehicle Incident Nil Nil Nil
C HSE Metrics
Safety Induction 38 422 460
Tool Box Talks 54 642 396
Safety Training Conducted 7 48 55
Hazard Identification Report 15 160 175
Site Safety Inspection 8 110 118
1.HSE Performance

D Brief description of incidents for the week (Near Miss)


NIL

E
Salient Achievements / Activities / Milestones for the week / Non Compliances Issues (PPE,
Barricading, Systems, Procedures….etc)
1. Site HSE induction is being conducted for workforce.
2. Daily Tool box talks for workforce.
3. Daily COVID 19 is followed at site - Thermal scanning, oximeter check, mask and social
distancing at site.
4 .Daily Work Clearance is being followed at site and HSE Inspections
5. Medical tie-up with full fledge hospital along with availability of Emergency Vehicle facility
24X7.
6. PPEs compliance is being monitored at site.
7. Weekly HSE walk-through has been done.
8. Monthly HSE inspection with color coding is being followed at site.
9. Medical fitness examination is being conducted for employees.
10. Labour shed & Drinking water facilities provided at site.
11. Toilet facility has been provided for all workmen.
Project S-Curve up to 23.03.2022
Chart Title

14.00% 120.00%

12.33%
12.00% 11.82%
11.31% 100%100.00%
11.03% 97.84% 98.90%
10.25% 10.44%
89.86%
10.00%
79.43% 80.00%

7.98%
8.00% 68.40%
7.37%
6.53% 60.00%
Axis Title

57.09%
6.00%
5.32%
44.76%
4.46% 40.00%
3.93%
4.00% 32.95%
2.57%
22.70%
20.00%
2.00% 1.67%
15.32%
0.90% 0.93% 11.65% 1.06% 1.00%
0.66% 8.79% 7.19%
0.00%
0.00% 0.00% 3.48% 1.59% 3.26%
0.00% 0.00% 0.90%
0.00% 0.66% 0.00%
Sep-21

Oct-21

Dec-21

Jan-22

Feb-22

Mar-22

May-22

Jun-22

Aug-22

Sep-22

Nov-22
Nov-21

Apr-22

Jul-22

Oct-22
Axis Title
Work Front available as on 23.03.2022

Piping Fabrications - 60000 ID released

Concreting Works – 1324M3 Vs 1000 M3 ( Obstacle Free)

Structural Steel Fabrications – 600MT released till date.


Civil works front availability status against issued drawing .
Soft Copy Received
Sl No. Area Drawing No. Area Rev. Transmittal No. Date Start Date Uom Drawing Scope
Date

                     

## RCC                  

20-09-2021
WP-IOCL-PNP-CDWUII-T-001 27-09-2021
1 Foundation layout details for new trestles near DYIP flare stack 44AD2800-121-C.01-1101 Flare 4 WP-IOCL-PNP-CDWUII-T-012 25-10-2021     cum 70.222
WP-IOCL-PNP-CDWUII-T-014
03-11-2021

WP-IOCL-PNP-CDWUII-T-001 20-09-2021
Foundation layout details for new trestles in between road B-2 & Tank 27-09-2021
2
61-T-101/102
44AD2800-121-C.0-1102 Road B2 2 WP-IOCL-PNP-CDWUII-T-030
29-12-2021
    cum 106.345
WP-IOCL-PNP-CDWUII-T-038
18-01-2022

Pipe Bridge foundation layout & details west & south side entry of WP-IOCL-PNP-CDWUII-T-001 20-09-2021
3
CDWU-II Plot
44AD2800-121-C.01-1103 Along Road C 1 WP-IOCL-PNP-CDWUII-T-026
27-09-2021     cum 30.600
22-12-2021

WP-IOCL-PNP-CDWUII-T-012 25-10-2021
Layout & Details of new foundation south of CDWU-II between battery WP-IOCL-PNP-CDWUII-T-016
4
limit of LSTK & street-4
44AD2800-121-C.01-1104 Street-4 3 WP-IOCL-PNP-CDWUII-T-
17-11-2021     cum 174.000
21-03-2022
WP-IOCL-PNP-CDWUII-T-062

20-09-2021
5 Details of box culvert near CDWU-II ISBL area south side battery limit 44AD2800-121-C.01-1105 Steeet-4 0 WP-IOCL-PNP-CDWUII-T-001
27-09-2021
    cum 38.800

WP-IOCL-PNP-CDWUII-T-001 20-09-2021
New pipe bridge foundation layout & details south of CDWU-II between 27-09-2021
6
battery limit of LSTK & street-4
44AD2800-121-C.01-1106 C1 & ST-4 2 WP-IOCL-PNP-CDWUII-T-017
23-11-2021
    cum 29.244
WP-IOCL-PNP-CDWUII-T-026 22-12-2021

WP-IOCL-PNP-CDWUII-T-016 17-11-2021
7 Layout & details of new foundations for new dispatch facility area 44AD2800-121-C.01-1307 Bitumen 2 WP-IOCL-PNP-CDWUII-T-026 22-12-2021     cum 50.936
WP-IOCL-PNP-CDWUII-T-038 18-01-2022

Layout & Details of new foundations for new dispatch facility area near
8
tank truck loding area
44AD2800-121-C.01-1308 Tank-908/909 & Bitumen 0 WP-IOCL-PNP-CDWUII-T-015 11-11-2021     cum 92.028

Layout and details of new foundations for feed Tank Farm Area (sheet
9
1)
44AD2800-121-C.01-1302 800 tank farm South of Steet-4 0 WP-IOCL-PNP-CDWUII-T-031 31-12-2021     cum 81.000

10 Layout & details for new foundationsfor tank farm area (sheet 2) 44AD2800-121-C.01-1302 800 tank farm South of Steet-4 0     07-01-2022   cum 70.000

WP-IOCL-PNP-CDWUII-T-039 27-01-2022 19-01-2022


11 Layout & details for new foundations for tank farm area (sheet 3) 44AD2800-121-C.01-1302 800 tank farm South of Steet-4 0 WP-IOCL-PNP-CDWUII-T-062 21-03-2022 17-03-2022
19-03-2022 cum 280.000

Layout and Details of Foundations along ROAD-C West Side & South
12
Side Entry of CDWU-II Plot
44AD2800-121-C.01-1301 Along Road C 0 WP-IOCL-PNP-CDWUII-T-039 27-01-2022 11-12-2022   cum 192.000

13 Layout and details of New foundations for new dispatch facility area 44AD2800-121-C.01-1303 Bitumen Area 0 WP-IOCL-PNP-CDWUII-T-062 21-03-2022 15-03-2022   cum 25.000

14 Schedule and details of miscellaneous piping supports 44AD2800-121-S.01-1352 MPS 1         cum 45.000

13 Precast Culvert 44AD2800-121-C.01-000 Street-5A 0         cum 38.800


                     
1323.975
TOTAL             cum
Drawing Received Status.
Sl. No Discipline No of Drawing Remarks

1. Civil 15 No's

2. Structural 18 No's

3. Piping ISO 1282No’s

4. Electrical 18 No's

5. Instrumentation. 1 No

6. IBR Package Lot-2

7. Demolition Package 1
Tie Point Status

Nos of TP
No's Of TP Scope TP
Sl. No. Category C Scope Drawing Completed Balance Remarks
Release

TANK WAGON AREA 40


Nos Tie Point materials
Partly received, 40 Nos
1 Category A 157 63 34 123
Fabrication Completed,
121-TP-132,134
Fabrication Completed

2 Category B 8 8 8 0  

3 Category C 4 3 0 4 Waiting Hot Tapping


Permit

4 Category D 259 11 6 253  

Sub-Total 428 85 48 380  


Piping Materials Received Status
 Matching Piping Materials Received Status – 60000
ID.
40 No's TP materials received from IOCL Store.
Procurement Status

1. 166 MT TMT Bar received at site & PO placed


another 56 MT Bar Materials.
2. 10000 Bags cement received at site
1000 No's foundation bolt received at site
465 MT Structural Materials received
1530Mtr Cable tray received at site.
7200Mtr Earth strip received at site.
Highlights
 Piling works completed.
 Foundations completed at New Flare area & Along Road C1.
 Load test of working & test pile along with Integrity test has been
completed and Vertical, Lateral & Pull-out test have been completed..
 PPC Cement has been approved along with OPC Cement.
 All Tie-In JSA has been approved.
 TP-Eleven (21) number has been completed out of 23.
 Piping Erection & Fabrications under process.
 Structural Fabrication done 200Aprx. MT & Painting works under
process.
 465 MT Structural Materials received at site & Fabrications works
commence.
 1530mtr Cable tray & 7200mtr earth strip received at site.
 50 Nos another USK labours gate pass & 50Nos Mechanicals technician
Gate pass related doc. Submitted to Pass departments.
Areas Needing Attention

 Balance Electrical Items other than Cable Tray and Earth Strip to be furnished
expeditiously . Similar for Instrument Balance items
 QAP Issue for Instrument Supply items needs to be resolved expeditiously.
 Drawing Control index ( DCI) needs to be provided on immediate basis.
 Architectural drawing to be provide on priority basis.
 Providing Round the clock Hot work permit( Welding only) at Fab. Yard to
boost up progress of Structural & Piping.
 Request for work permit at Tank 908/909 & Near Railway track all tank farm
areas.
 Request for issue work permit on priority basis.
THANKING YOU COURTESEY- IOCL-Worley-PNP