IOCL,HALDIA REFINERY
NAME OF Work:- PILING,CIVIL & STRUCTURAL, MECHANICAL PIPING
WORKS,ELECTRICAL, INSTRUMENTATION AND OTHER ASSOCIATED
WORKS.
Date:- 26.03.2022
1.HSE Performance
Weekly Safety Report for Period Ending Friday – 25.03.2022
Sl.
Description This Week Up to Previous Cumulative
No Week
A Work Hours (Staff + Workers) 25620 173228 198848
Total Work Hours Achieved so far 198848
Avarage Manpower (Staff + Workers) 366
B Safety Performance Indicators
Fatality Nil Nil Nil
Recordable Incidents
E
Salient Achievements / Activities / Milestones for the week / Non Compliances Issues (PPE,
Barricading, Systems, Procedures….etc)
1. Site HSE induction is being conducted for workforce.
2. Daily Tool box talks for workforce.
3. Daily COVID 19 is followed at site - Thermal scanning, oximeter check, mask and social
distancing at site.
4 .Daily Work Clearance is being followed at site and HSE Inspections
5. Medical tie-up with full fledge hospital along with availability of Emergency Vehicle facility
24X7.
6. PPEs compliance is being monitored at site.
7. Weekly HSE walk-through has been done.
8. Monthly HSE inspection with color coding is being followed at site.
9. Medical fitness examination is being conducted for employees.
10. Labour shed & Drinking water facilities provided at site.
11. Toilet facility has been provided for all workmen.
Project S-Curve up to 23.03.2022
Chart Title
14.00% 120.00%
12.33%
12.00% 11.82%
11.31% 100%100.00%
11.03% 97.84% 98.90%
10.25% 10.44%
89.86%
10.00%
79.43% 80.00%
7.98%
8.00% 68.40%
7.37%
6.53% 60.00%
Axis Title
57.09%
6.00%
5.32%
44.76%
4.46% 40.00%
3.93%
4.00% 32.95%
2.57%
22.70%
20.00%
2.00% 1.67%
15.32%
0.90% 0.93% 11.65% 1.06% 1.00%
0.66% 8.79% 7.19%
0.00%
0.00% 0.00% 3.48% 1.59% 3.26%
0.00% 0.00% 0.90%
0.00% 0.66% 0.00%
Sep-21
Oct-21
Dec-21
Jan-22
Feb-22
Mar-22
May-22
Jun-22
Aug-22
Sep-22
Nov-22
Nov-21
Apr-22
Jul-22
Oct-22
Axis Title
Work Front available as on 23.03.2022
## RCC
20-09-2021
WP-IOCL-PNP-CDWUII-T-001 27-09-2021
1 Foundation layout details for new trestles near DYIP flare stack 44AD2800-121-C.01-1101 Flare 4 WP-IOCL-PNP-CDWUII-T-012 25-10-2021 cum 70.222
WP-IOCL-PNP-CDWUII-T-014
03-11-2021
WP-IOCL-PNP-CDWUII-T-001 20-09-2021
Foundation layout details for new trestles in between road B-2 & Tank 27-09-2021
2
61-T-101/102
44AD2800-121-C.0-1102 Road B2 2 WP-IOCL-PNP-CDWUII-T-030
29-12-2021
cum 106.345
WP-IOCL-PNP-CDWUII-T-038
18-01-2022
Pipe Bridge foundation layout & details west & south side entry of WP-IOCL-PNP-CDWUII-T-001 20-09-2021
3
CDWU-II Plot
44AD2800-121-C.01-1103 Along Road C 1 WP-IOCL-PNP-CDWUII-T-026
27-09-2021 cum 30.600
22-12-2021
WP-IOCL-PNP-CDWUII-T-012 25-10-2021
Layout & Details of new foundation south of CDWU-II between battery WP-IOCL-PNP-CDWUII-T-016
4
limit of LSTK & street-4
44AD2800-121-C.01-1104 Street-4 3 WP-IOCL-PNP-CDWUII-T-
17-11-2021 cum 174.000
21-03-2022
WP-IOCL-PNP-CDWUII-T-062
20-09-2021
5 Details of box culvert near CDWU-II ISBL area south side battery limit 44AD2800-121-C.01-1105 Steeet-4 0 WP-IOCL-PNP-CDWUII-T-001
27-09-2021
cum 38.800
WP-IOCL-PNP-CDWUII-T-001 20-09-2021
New pipe bridge foundation layout & details south of CDWU-II between 27-09-2021
6
battery limit of LSTK & street-4
44AD2800-121-C.01-1106 C1 & ST-4 2 WP-IOCL-PNP-CDWUII-T-017
23-11-2021
cum 29.244
WP-IOCL-PNP-CDWUII-T-026 22-12-2021
WP-IOCL-PNP-CDWUII-T-016 17-11-2021
7 Layout & details of new foundations for new dispatch facility area 44AD2800-121-C.01-1307 Bitumen 2 WP-IOCL-PNP-CDWUII-T-026 22-12-2021 cum 50.936
WP-IOCL-PNP-CDWUII-T-038 18-01-2022
Layout & Details of new foundations for new dispatch facility area near
8
tank truck loding area
44AD2800-121-C.01-1308 Tank-908/909 & Bitumen 0 WP-IOCL-PNP-CDWUII-T-015 11-11-2021 cum 92.028
Layout and details of new foundations for feed Tank Farm Area (sheet
9
1)
44AD2800-121-C.01-1302 800 tank farm South of Steet-4 0 WP-IOCL-PNP-CDWUII-T-031 31-12-2021 cum 81.000
10 Layout & details for new foundationsfor tank farm area (sheet 2) 44AD2800-121-C.01-1302 800 tank farm South of Steet-4 0 07-01-2022 cum 70.000
Layout and Details of Foundations along ROAD-C West Side & South
12
Side Entry of CDWU-II Plot
44AD2800-121-C.01-1301 Along Road C 0 WP-IOCL-PNP-CDWUII-T-039 27-01-2022 11-12-2022 cum 192.000
13 Layout and details of New foundations for new dispatch facility area 44AD2800-121-C.01-1303 Bitumen Area 0 WP-IOCL-PNP-CDWUII-T-062 21-03-2022 15-03-2022 cum 25.000
14 Schedule and details of miscellaneous piping supports 44AD2800-121-S.01-1352 MPS 1 cum 45.000
1. Civil 15 No's
2. Structural 18 No's
4. Electrical 18 No's
5. Instrumentation. 1 No
7. Demolition Package 1
Tie Point Status
Nos of TP
No's Of TP Scope TP
Sl. No. Category C Scope Drawing Completed Balance Remarks
Release
2 Category B 8 8 8 0
Balance Electrical Items other than Cable Tray and Earth Strip to be furnished
expeditiously . Similar for Instrument Balance items
QAP Issue for Instrument Supply items needs to be resolved expeditiously.
Drawing Control index ( DCI) needs to be provided on immediate basis.
Architectural drawing to be provide on priority basis.
Providing Round the clock Hot work permit( Welding only) at Fab. Yard to
boost up progress of Structural & Piping.
Request for work permit at Tank 908/909 & Near Railway track all tank farm
areas.
Request for issue work permit on priority basis.
THANKING YOU COURTESEY- IOCL-Worley-PNP