INTRODUCTION
• In Kota Super Thermal Power Station electricity is generated.
• The project was proposed by Central Electric Authority of India
in April, 1973.
• The project was revised in 1975 and approved in Sep., 1976.
• At first two units were installed each producing 110 MW of
power.
• The first estimated cost was Rs. 143 Crores.
STAGE I STAGE V

2x110 MW STAGE Il STAGE IV 1x195 MW


STAGE Ill
2x210 MW 1x195 MW
1x210 MW
Coal
Coal Chim
Storage Air ney
Pre-heater
Coal Handling
Plant Air
Economizer

Ash Handling Alter-


Turbine Exciter
Plant Boiler Super nator
Heater
Ash
Storage
Feed Water
Heater
Ash Make up
Water Condenser
STEAM
Deaerator
COAL WATER
Cooling
ASH FLUE GASES Tower
COAL HANDLING PLANT
WAGON TRIPLER
 Wagons From the
coal yard come to the
tippler and are emptied
here.

 The process is per-


formed by a Slip ring mo-
tor of rating 55KW, 415V,
1480 RPM.

 This motor turns the


wagon by 150 degree
and coal falls directly on
the conveyor through vi-
brators
WATER TREATMENT PLANT
BOILER
Temperature of Super
Heated Steam – 540’c
Pressure-144 kg/cm*cm

• Boilers are used for elec-


trical power generation,
heat energy is released
from the combustion of
fuels.

• BHEL make direct fired


natural circulation bal-
anced draft tube boilers
are used here, having ca-
pacity of 375 tones/hour
and efficiency of 86.6%.
STEAM TURBINE
 It convert heat en-
ergy of steam into Steam Flow
mechanical energy
and drive generator. HP Turbine

 It uses the principle


the steam when issu- IP Turbine
ing from a small
opening attains a LP Turbine
high velocity.
TRANSFORMER
 Transformer is a static device which
is used to change the voltage level
keeping the power and frequency
same.

 In the whole plant there are about 83


transformer installed at various
places to operate the auxiliaries.

 Main transformers, which are neces-


sary:
1. To step up the generated voltage.
2. To supply power to the auxiliar-
ies from the generator.
3. To start the plant by taking the
supply from the grid
BOILER –FLY ASH PRODUCESD
E.S.P. – BOTTOM ASH
(in small amount)

Fly ash (80%).


Used for making bricks.
Cement.
Bottom ash (20%)
Used to improve fertility.
Roads.
 Two 220 KV bus
bars have been
provided in switch
yard and are inter-
connected through
a bus coupler

 Two step down


transformer each
feeding 6.6 KV sys-
tem

 12 Feeders