Professional Documents
Culture Documents
TANDI GHYANPHEDI
HYDROPOWER PROJECT
1
HYDROLOGICAL ANALYSIS
• As hydropower is the generation of electricity from water, hydrological study
should be done. In prefeasibility study of any hydropower project, it is
necessary to have long term historical data. The longer the hydrological
records, the more will be the reliable estimation of design parameters for the
project.
Objectives
• Following are the objectives for hydrological analysis of run-of-river
hydropower project in prefeasibility study:-
• To preform long term stream flow analysis and obtain average flow & and
analyze for design discharge through flow duration curve.
• To perform flood flow analysis and find out design flood discharge for different
return period.
• To calculate lowest flow discharge of proposed river.
Scope
• Following are the activities that were performed in order to achieve the above
objectives:-
• Collection of Hydro-meteorological for the catchment of proposed site.
• Analysis of collected data using different methods for alternatives and
adoption of one result for different hydrological analysis.
Drainage area characteristics
3
Long-term Stream Flow Analysis
• Studying the long-term changes of stream flow is an important tool for enhancing
water resource and planning, design, and management of hydropower system.
The aim of this work is to identify the long-term variations in annual stream flow.
This analysis will provide us with the average monthly discharge and then these
values can be used to obtain the design discharge of the project.
Importance of long-term flow
5
Long term stream flow (m3/s)
Month
Return Period
(yrs) Modified
Fuller's Gumbel's Log Pearson
Dickens WECS/DHM MHSP
Method method type III
Method
87 42.21 37
2 185 - -
83.359 57 169.579
5 - - -
101.097 77.732 71
10 153 269 -
118.111 86 262.891
20 - -
99.476
25 - - - - -
127.899 -
30 - - - -
33 202 331 - - - -
140.135 117.515 106 333.208
50 218.57 352
156.638 137.108 122 391.518
100 247 387
• 1.9 Low flow analysis
7
Comparison of low flows
• To compute the low flow discharges WECS/DHM and GUMBEL methods were
performed. In WECS/DHM method, the total catchment area, areas below 5000
m is required as input to calculate low flow of 2yr, 10yr and 20yr return period.
And for Gumbel’s method, data of minimum discharges for different return
period for Tadi river were obtained using gauging station number 448 (provided
in hydrological estimations in Nepal by DHM) and then applying CAR method.
As gauging station number 448 is on Tadipul Belkot and the project area is at
upper part of Tadi river so CAR method seems not much appropriate and hence
low flow obtained from WECS/DHM method can be taken for further design
purpose.
8
WORK REMAINING
• 1.Design of Hydraulic structures
• 1.1 Weir and under sluice
• 1.1.1 Selection of weir type
• 1.2 Energy Dissipating Structures
• 2. Design of intake structures
• 3. Design of Gravel trap
• 4. Design of settling basin
• 5. Design of Headrace pipe and Design of Anchor Block
• 6. Design of surge Tank
• 7. Design of penstock and Optimization
• 8. Design of power House and tailrace canal and Selection of turbine
• 9. Economic analysis
• 10. Final report
9
SCHEDULE FOR REMAINING
WORK
Task Start Date Days to Complete
2 10
Design of Intake Structures 15-Nov-22
2
3 Design of Gravel Trap 25-Nov-22
2
4 Design of Settling Basin 27-Nov-22
2
5 Design of Headrace pipe 29-Nov-22
6 Design of surge tank 1-Dec-22 2
7 Design of Penstock 3-Dec-22 2
8 Design of powerhouse 5-Dec-22 5
10
9 Economic Anaysis 10-Dec-22
45
10 Final report 20-Dec-22
Gantt Chart
31-Oct-22 10-Nov-22 20-Nov-22 30-Nov-22 10-Dec-22 20-Dec-22 30-Dec-22 9-Jan-23 19-Jan-23 29-Jan-23 8-Feb-23
Design of Penstock
Design of powerhouse
Economic Anaysis
Final report
12