Professional Documents
Culture Documents
Train Overview
900km/hr
High Speed
Train
300km/hr
Existing Railway
130km/hr
120km/hr
Project Brief
High Speed Authorities
NATM/ TBM Tunnels
River Crossings
Stations
Stations
Architectural impression
Architectural impression
Depots & Workshop
A total of 3 Heavy Maintenance
Workshops at Thane, Surat and
Sabarmati, 6 Maintenence Depots and
24 Sub-Maintenance Depots will serve
as the maintenance bases for the trains.
Depots
The main functions
are to store materials,
equipment and
engineering trains to
maintain the High
► Speed Rail
subsystem of
permanent way,
traction power,
communications, and
civil infrastructure.
Tracks & Trains
Trackwork
Train in Operation
Tracks & Trains
Tracks and Trains
are divided into 3
separate systems:
■ Trackwork
■ Core Systems
■ Rolling Stock
Tracks & Trains At the time of this
presentation, minor
works for Core Systems
Core Systems were in progress
Core systems
are the essential
■ Driver Training Simulator
components to
make the trains ■ Signaling Systems
Slope2%
Interface
Request from
Station Platforms Stations
Give to Civil
Request from
Substations Equipment Trackwork & Give to Civil
Trains
Coordination
Coordination
Methods
FSLM
Steel Truss
PSM
I-Girders
Site Process Control
Method Statement
Construction Design
Drawings & Works
Specification
Inspection &
Test Plan
Structure Certification
Method Statement
Inspection &
Test Plan
Method Statement
[inspection, testing, etc.] monitors the
activities and
keeps records
as evidence of
Evidence of Record compliance
Keeping
Structure Certification
- Scope of works
- Equipment
- Labor
- Safety plan
The ITPs will detail - Environmental Plan
the sequence of
inspection and - Sequence of works
testing with “hold- - Inspection & Test Plans (ITP)
points” to ensure
- Hazard and risk assessments
the Contractor’s
staff presence upon - Staffing and names
a critical activity
- Drawings
- Materials
- Subcontractors
Method Statement
Inspection &
Test Plan
Implementation - I
[inspection, testing, etc.] monitors the
activities and
keeps records
as evidence of
Evidence of Record compliance
Keeping
Structure Certification
Inspection &
Test Plan
Structure Certification
[inspection, testing, etc.] monitors the
activities and
keeps records
as evidence of
Evidence of Record compliance
Keeping
Monthly Certification:
The Contractor’s Monthly Report will include:
- Design QA Manager certifying that all design activities
during the month comply with Contract requirements.
- Quality Control Manager certifying that the structures
and materials comply with Contract requirements.
- Quality Manager confirming that all works considered
completed are compliant.
Final Certification:
The Quality Control Manager has the final authority at the
end of the Project to certify the completeness and
compliance of the structures. Therefore the Quality
Control Manager must establish a proper certification
system as works progress.
Topics Covers
structures the items
Piles below:
Shape
Quantities
Pile Caps Erection
Drawings
Loads
Piers Programme
Progress
Pier Caps
Girders
Piles
1.9m dia.
GL
caisson
Ground Level
3m long caisson
prevents top loose soil
from collapsing into the
60~70m drilled excavated Pile hole
hole
1.8m dia
PVC Pipes
Sheet piling must be installed prior
to excavation
Pile Caps
GL
Excavation
in progress
exposing
Piles
Pile Caps
GL
Once exposed Piles have
been cleaned off of their
concrete, a concrete
blinding will be placed to
allow the Pile Cap bottom
rebar to be installed
Piers
Pier Caps
GL
Piers
Pier Caps
GL
Pier Caps
and Shear-
Key
concreted
and Piers are
finally
completed
and ready for
Pot Bearings
and
Viaducts...
Girders
FSLM
GL
Girders – MAHSR C4
Rebar portion
FSLM
GL
entering
concreting area
Girders MAHSR C4
FSLM
GL
Girder lifted
and placed on
top of pier caps
Girders
FSLM
GL
Girder
transported
to launcher
Girders
FSLM
GL
Launching sequence:
1. Girder approaching launcher
2. Girder front end lifted
Girders
FSLM
GL
Launching
sequence:
3. Girder front
end lifted and
slowly moved
forward
4. Girder
advancing
towards of
front of
launcher
(only front of
Girder is
lifted)
Girders
FSLM
GL
Launching sequence:
5. Girder back end is lifted when Girder has reach
approx. 2/3 of its path
6. Girder is lowered to its final position
Girders
FSLM
GL
FSLM
GL
Launcher
positioning
front legs
and ready
for next
girder
launching
Girders
FSLM
GL
Looking
behind
launcher
Girders
FSLM
GL
Girders – MAHSR C4
PSC
GL
Girders – MAHSR C6
River Crossings:
GL