Activity Introduction
The process produces one black ABC in capitals each cycle, on the
flipchart.
Fig. 1
ABC 25 mm
80 mm
3
Activity Introduction
Write down exactly what you see in one cycle of the process.
I will say "start" at the beginning of the first cycle and "finish" at the
end of each cycle.
4
ABC Process: Job Detail Sheet
No. Work Element Key Point Ke y Po int Re as o n: S a fe ty Qua lity Ea s e Photo/Sketch
Pretend to trip over hazard on floor But avoid injury Ea s e
Put in configured place. To make it quick and simple to select next time.
4 Walk to table and put pen in box
5
ABC Process: Standard Work Chart
Chair
1 Table Team
2
5
Configured box
4
of assorted
3
pens
Flip
Chart
6
Team Activity: Identify process content
If the team need it, run through the cycle a third time.
Give the team time to write down what they have seen.
Ask each person how many steps they saw in one cycle.
Choose a team member who had about 11 steps and write their steps
up on the flipchart.
7
Example list of process content
• Stand up
• Walk to the pens
• Select black flipchart pen
• Carry pen to flipchart
• Take the lid off
• Write ABC on the board
• Put pen lid back on
• Carry pen back to the table
• Place pen back in box
• Walk to the chair
• Sit down
8
Activity: Define work elements
9
Example elements
10
Team Activity: Time the elements
Explain that we need to time each element and also the walking elements.
Commentate to assist the team with the timings by saying start, split
(between each element and to separate out the walk times) and finally end.
11
Example element times
12
Team Activity: Create Standardized Work
Chart
Fill in the chart heading boxes.
13
Example Standardized Work Chart
Organisation ACME
Created By C Brown
Area Training Room
Part Name/Number ABC Standardised Work Chart Issue Date 23/10/2007
Job From: Stand up and walk to table Issue Number 1
Content To: Walk to chair and sit down Takt Time -
No. Working Sequence Steps
2
5
Configured box
4
of assorted
3
pens
Flip
Chart
- 29 seconds
14
Team Activity: Create Job Detail Sheet
Indicate what PPE is required and fill in the key preparation activities box.
15
Example Job Detail Sheet
Organisation ACME
Area Training Room Created By C Brown
Part Name/ Number ABC
Job Detail Sheet
Working Sequence Step Steps 1 to 5 Issue Date 23/10/2007
Operation / Process No. - Issue Number 1
Initial Creation Date 23/10/2007 Takt time -
No. Work Element Key Point Key Point Reason S a fe ty Qua lity Ea se Photo/Sketch
16
Team Activity: Create Standardized Work
Combination Table
Fill in the chart heading boxes.
17
Example Standardized Work
Combination Table
Organisation ACME
Created By C Brown
Area Training Room
Standardised Work
Part Name/ Number ABC Issue Date 23/10/2007
Combination Table Issue Number
From: Stand up and walk to table 1
Job Content
To: Walk to chair and sit down Takt Time -
Time Element Time Unit: seconds
No. Work Element
5 10 15 20 25 30
Manual Auto Wait Walk
Key:
Totals 15 14 Manual Walk
Auto Waiting
Cycle Time 29
18
Activity Review
19