Professional Documents
Culture Documents
Project Planning
1. Determining the sequential logic, i.e. creating the most likely order in which the
2. Creating a project plan from start to finish, i.e. constructing a network diagram
• Construction of WBS
– Represents the conversion of project goals into an achievable methodology for the completion
– Creates a timetable and reveals the network logic that relates project activities to each other in
coherent fashion
– Defines network logic for all activities; i.e. tasks must either precede or follow other tasks from the
Project planning process descriptions vary from industry to industry, from organization to
organization. In IT sector the project planning process has the following phases
1. Concept evaluation
2. Requirements identification
3. Design
4. Implementation
5. Test
6. Integration
7. Validation
8. Customer test and evaluation
9. Operations and maintenance
The action plan
The project’s action plan is a detailed, scheduled plan of the required steps in the
implementation process needs to be developed, including all resource
requirements (money, raw materials, staff, etc.)
In project planning,
• We need to know exactly what is to be done, by whom, and when
• We need to identify and coordinate all activities required to complete the project
• The necessary resources must be available when and where they are needed,
and in the correct amount
• Some activities must be done sequentially, but some may be done simultaneously
If a large project is to come in on time and within cost, a great many things must
happen when and how they are supposed to happen. Yet each of these details is
uncertain and thus each must be subject to risk management
The method of constructing an action plan, therefore, has to be systematic. One
such method ‘a hierarchical planning system’.
hierarchical planning system
A network diagram is a schematic display of the project’s sequential activities and the
logical relationships between them
A B C D E
B D
F
A
C E
Option B: Nonserial sequential logic
Many of actual projects are large and complex. Since WWII two techniques have been
developed and used to deal with such large or complex projects: PERT/CPM.
The distinction between the two techniques has gradually diminished through time and
we can use CPM representing the integrated logic that each has introduced to the
methodology
CPM can be used to plan, schedule, and control a wide variety of projects:
Activity
float ACTIVITY DESCRIPTOR
C
H I
START I
FINISH
A. Find the earliest start time and a latest start time for all activities in the network
EF = ES + T
B. Find the latest start and latest finish time for all activities in the
network
LS: latest start time for an activity
LF: latest finish time for an activity, and
TO calculate LF, begin with EF time of the project, i.e., the last activity’s early finish and calculate
backward.
LS = LF – t
In calculating earliest start for merge activity, take the largest late finish time of those activities which flow
into it
In calculating latest finish time for burst activity, take the smallest late start time of those activities which
flow out from it
Float or slack activity time : The amount of time an activity may be delayed from its early start without delaying
the finish of the project
SLACK TIME = LF - EF = LS – ES
A critical path is that path consisting of activities with zero slack time. Observe that such
path determines the longest duration time for the project. Therefore, it is the path
through the project network with longest duration
The work we did so far is what it takes to do the critical path analysis of the project, and
by doing so we answer the following questions:
B - 6 0 6 6 12 6
C A 4 5 9 8 12 3
D A 3 5 8 7 10 2
E A 1 5 6 5 6 0
F E 4 6 10 6 10 0
G D,F 14 10 24 10 24 0
H B,C 12 9 21 12 24 3
I G,H 2 24 26 24 26 0
51
A
D G J
FINISH
E H
I
START I
a) M = Time estimate under most likely condition (most probable time estimate)
b) B = Time estimate under worst condition (pessimist time estimate)
c) A = Time estimate under best condition ( optimist time estimate)
Using these three time estimates, we develop expected time using beta distribution ( a
probability distribution having
Activities optimistic time (a) Most probable (m) Pessimistic time (b) Expected time
A 4 5 12 6 1.777778
B 1 1.5 5 2 0.444444
C 2 3 4 3 0.111111
D 3 4 11 5 1.777778
E 2 3 4 3 0.111111
F 1.5 2 2.5 2 0.027778
G 1.5 3 4.5 3 0.25
H 2.5 3.5 7.5 4 0.694444
I 1.5 2 2.5 2 0.027778
J 1 2 3 2 0.111111
0 A 6
6 D 11 11 G 14 15 J 17
0
1 1 0
0 6 6
7 5 12 12 3 15 15 2 17
FINISH
6 E 9 9 H 13
13 I 15
START 0 0
0
6 3 9 9 4 13
13 2 15
0 B 2
7
7 2 9
6 C 9 9 F 11
4 4
10 3 13 13 2 15
0 A 6
6 D 11 11 G 14 15 J 17
0
1 1 0
0 6 6
7 5 12 12 3 15 15 2 17
FINISH
6 E 9 9 H 13
13 I 15
START 0 0
0
6 3 9 9 4 13
13 2 15
0 B 2
7
7 2 9
B - 2 0 2 7 9 7
C A 3 6 9 10 13 4
D A 5 6 11 7 12 1
E A 3 6 9 6 9 0
F C 2 9 11 13 15 4
G D 3 11 14 12 15 1
H B,E 4 9 13 9 13 0
I H 2 13 15 13 15 0
J F,G,I 2 15 17 15 17 0
i.e., z – 1.28
In Z = [(X-17)/1.65], X is unknown
1.28 = [(X-17)/1.65],
[1.28x1.65] + 17 = X = 19.112 weeks
A [contract signing] - 5
B [questionnaire design] A 5
6 5 11
26.9 H 29.1
0 A 5 11 D 22.7 22.7 F 26.9
0 Presentation
START 0 CONTRACT 0 Survey sample 0 Analyze to client FINISH
SIGNING results
11 12.7 22.7 26.9 2.2 29.1
0 5 5 22.7 4.2 26.9
5 C 11
0 Target
market ID
5 6 11
11 G 20.3
6.6 Demographi
c analysis
17.6 9.3 26.9
Laddering activities
Hammock activities
A - 7
B A 3
C - 6
D C 3
E B,D 2
0
0
10 E 12
7 3 10
0 7 7
0
FINISH
START 10 2 12
6 D 9
0 C 6
1
1
7 3 10
1 6 7