Professional Documents
Culture Documents
PROCUREMENT
OF GOODS AND SERVICES
1
GENERAL MODE OF PROCUREMENT
2
COMPETITIVE BIDDING
3
COMPETITIVE BIDDING
Garcia vs. Burgos (291 SCRA 546)
4
COMPETITIVE BIDDING
5
STANDARDIZED BIDDING PROCEDURE FOR
GOODS AND SERVICES
Pre-Procurement Pre-Bid
Advertisement
Conf. Conference
Opening of
Submission of Opening of 2nd
1st Env. - Eligibility
Bids Envelope – Financial
Docs & Technical
Proposal
Proposal
6
I. PRE-PROCUREMENT
CONFERENCE
Purpose: Determine readiness of procurement
Conducted prior to advertisement/posting of the Invitation to
Bid
Mandatory for projects with ABC above PhP 2M
Attended by the following:
a)BAC
b)BAC Secretariat
c)TWG
d)Consultants
e)End-user unit/Other officials
7
REFERENCE TO BRAND NAMES
Section 18 of RA 9184 and its IRR
Applicable only to procurement of goods
8
II. ADVERTISEMENT/POSTING OF THE
INVITATION TO BID
Importance:
Signals the start of the bidding process. Procurement process
should be made within 3 months starting from posting and
advertisement until awarding of contract. (Sec. 38.1 IRR)
9
II. ADVERTISEMENT/POSTING OF THE
INVITATION TO BID
At least once in one (1) newspaper of general nationwide circulation,
which has been regularly published for at least two (2) years before
advertisement date.
10
II. ADVERTISEMENT/POSTING OF THE
INVITATION TO BID
Medium Above 2M 2M and below
12
III. PRE-BID CONFERENCE
13
III. PRE-BID CONFERENCE
• Section 22.1 of the IRR of RA 9184 provides that at least one (1) pre-bid
conference should be conducted by the procuring entity for projects
costing at least PhP1 Million, in order to afford prospective bidders the
opportunity to inquire on or clarify any of the requirements, terms,
conditions, and specifications stipulated in the Bidding Documents.
14
CLARIFICATION OF BIDDING
DOCUMENTS
Supplemental/Bid Bulletins– issued by BAC to answer
requests for clarification (query submitted 10 c.d. before
deadline) or interpretation, and upon BAC’s initiative to
clarify or modify any provision of Bidding Docs. (at least 7
c.d. before deadline for bids).
15
CLARIFICATION OF BIDDING
DOCUMENTS
§22.5.2 RA 9184 IRR allows PEs to issue Supplemental/Bid Bulletins
upon their initiative for the purpose of clarifying or modifying any
provision in the Bidding Documents, including the IB.
16
ADDITIONAL REQUIREMENTS
17
IV. SUBMISSION AND RECEIPT OF
BIDS
Two-Envelope System
1st Envelope – Eligibility Requirements and Technical Component
2nd Envelope – Financial Component
Submitted to the BAC on the date, time, and place specified in the Invitation to
Bid. Bids submitted after the deadline should not be accepted.
Date of submission should not be later than the following period from the last
day of posting of the Invitation to Bid.
18
IV. SUBMISSION AND RECEIPT OF
BIDS
Bidders are no longer required to submit a written LOI
together with their application for eligibility as
previously required in IRR Part A of RA 9184.
19
IV. SUBMISSION AND RECEIPT OF
BIDS
The practice of pre-qualification has been abandoned in RA
9184 and its IRR. the results of a pre-qualification have no
legal force and effect, bearing or weight, and cannot preempt
the findings of the BAC during the preliminary examination
of bids conducted during the opening of bids. Hence, a bidder
may still be declared ineligible during the opening of bids
despite a finding of qualification during the purported pre-
qualification exercise. (NPM 54-2013)
20
IV. SUBMISSION AND RECEIPT OF
BIDS
Procuring entity cannot validly and legally refuse to accept a
bid submitted before the deadline for the submission
indicated the Invitation to Bid or Request for Quotation.
21
V. OPENING AND EVALUATION OF 1ST
ENVELOPE
CONTENTS:
1. Eligibility requirements
2. Bid Security
3. Technical specifications
4. Omnibus sworn statement
Non-inclusion in blacklist
Authenticity of documents
Verification authority
22
V. OPENING AND EVALUATION OF 1ST
ENVELOPE
CONTENTS (continuation):
4. Omnibus Sworn Statement
Signatory’s authority
Disclosure of relations
Responsibilities of bidders
Labor laws and standards
Non-payment (directly or indirectly) any
commission, amount, fee, or any form of
consideration in relation to any procurement
project or activity
23
V. OPENING AND EVALUATION OF 1ST
ENVELOPE
Section 30 requires that the preliminary examination of bids
be conducted by merely checking for the presence or absence
of documentary requirements using a non-discretionary
“ pass/fail” criterion.
24
V. OPENING AND EVALUATION OF 1ST
ENVELOPE
25
ELIGIBILITY REQUIREMENTS
Class A Documents
1.DTI/SEC/CDA Registration
2.Mayor’s permit
3.Tax clearance per Executive Order 398, series of 2005,
as finally reviewed and approved by the BIR.
4.Statement of ongoing contracts.
5.Statement of SLCC
6.Audited financial statement
7.NFCC
26
ELIGIBILITY REQUIREMENTS
Class B Document
•JVA or notarized statement from the partners that they
will enter into joint venture if awarded the contract.
27
MAYOR’S PERMIT
28
TAX CLEARANCE
29
TAX CLEARANCE
EO 398 specifically requires the submission of Tax Clearance
issued by the BIR. It refers to the clearance issued by the
Collection Enforcement Division of BIR attesting that the
bidder has no outstanding Final Assessment Notice and/or
delinquent account.
30
TAX CLEARANCE
31
TAX CLEARANCE
32
CREDIT LINE COMMITMENT
33
STATEMENT OF ON GOING AND
COMPLETED CONTRACTS
The submission of a Statement of Ongoing Contracts should
only be required if the bidder opts to submit an NFCC
computation. If the bidder opts to submit a CLC, it need not
submit said statement.
The Statement of Completed Contract(s) should always be
required for the purpose of showing the bidder’s Single Largest
Completed Contract that is similar to the contract to be bid.
(Resolution 29-2012)
34
ELIGIBILITY REQUIREMENTS FOR
FOREIGN BIDDERS
35
ELIGIBILITY REQUIREMENTS FOR
FOREIGN BIDDERS
Foreign bidders may substitute eligibility documentary
requirements with the appropriate equivalent documents in their
country.
Only upon actual determination and confirmation of this
equivalence through post qualification by the BAC may it be
categorically resolved that the foreign documents submitted are
acceptable substitutes of the required eligibility documents
pursuant to §23.2 of the IRR. (NPM 42-2013)
36
ELIGIBILITY REQUIREMENTS FOR
FOREIGN BIDDERS
TAX CLEARANCE FOR FOREIGN BIDDERS
37
ELIGIBILITY REQUIREMENTS FOR GOVT.
CORPORATE ENTITIES
38
ELIGIBILITY REQUIREMENTS FOR
JOINT VENTURES
39
ELIGIBILITY REQUIREMENTS FOR
JOINT VENTURES
40
LEGAL ELIGIBILITY CRITERIA
41
TECHNICAL ELIGIBILITY CRITERIA
Previous contract
Similar to the contract to be bid out (as defined by the Bidding Documents)
42
TECHNICAL ELIGIBILITY CRITERIA
43
TECHNICAL ELIGIBILITY CRITERIA
GOODS – SINGLE LARGEST CONTRACT (Illustration)
Expendable Goods Non-expendable Goods
THUS: Previous contract should be at least THUS: Previous contract should be at least
P250,000 P500,000
44
FINANCIAL ELIGIBILITY CRITERIA
45
NFCC COMPUTATION
47
BID SECURITY
Procuring entity shall indicate in the Bidding Documents at least 2
acceptable forms of bid security, one of which should be the Bid
Securing Declaration.
48
BID SECURITY
Amount
Form of Bid Security Bid Security
(% = ABC)
a) Cash or cashier’s/manager’s
check
2%
b) Bank guarantee/draft or
Irrevocable LC
49
BID SECURING DECLARATION
50
BID SECURING DECLARATION
Penalties
- Automatic blacklisting for 2 years in ALL government
procurement activities, and
- Payment of fine
• For multiple bidders: difference between the evaluated
bid prices of LCRB/HRB with the next LCRB/HRB.
In case bidder is the LCRB/HRB, the amount shall be
based on the difference between the evaluated bid price
and ABC.
• For a single bidder: difference between the evaluated
bid price and ABC.
51
BID VALIDITY PERIOD
52
DISCLOSURE OF RELATIONS
53
CONFLICT OF INTEREST
54
VI. OPENING AND EVALUATION OF 2ND
ENVELOPE
CONTENTS:
55
VII. DETAILED EVALUATION
OF BIDS
Purpose is to determine the Lowest Calculated Bid (LCB),
by:
1. Establishing correct calculated prices of bids; and
2. Ranking calculated total bid prices from lowest to highest
56
VII. DETAILED EVALUATION
OF BIDS
No Contact Rule - prohibition on communication w/ bidders from bid
evaluation until award of contract.
The “ no contact” rule applies only to those whose bids are being
evaluated by the BAC after passing the preliminary examination.
Bidders who waived their right to utilize the protest mechanism or those
whose request for reconsideration and/or protest were subsequently denied
are not covered by the prohibition under §32.1 of RA 9184 IRR. (NPM 07-
2013)
57
VII. DETAILED EVALUATION
OF BIDS
Bid Evaluation shall not be more than 7 cd.
58
VII. DETAILED EVALUATION
OF BIDS
59
DOMESTIC PREFERENCE
60
DOMESTIC PREFERENCE
SAMPLE COMPUTATION
61
VIII. POST-QUALIFICATION
62
VIII. POST-QUALIFICATION
BAC will notify the Bidder with the Lowest Calculated Bid
that it was determined as such.
63
VIII. POST-QUALIFICATION
64
VIII. POST-QUALIFICATION
The three (3) calendar day period under §34.2 of the IRR is
mandatory and should not be extended.
In case PE accepts the post-qualification documentary
requirements beyond the reglementary period, it must show
that there is a compelling, sufficient, valid, reasonable, and
justifiable cause for such extension, so that penal sanction or
liability will not set in. Applicable administrative and civil
sanctions or liabilities may also be imposed against the
concerned officials. (NPM 27-2013)
65
VIII. POST-QUALIFICATION
66
VIII. POST-QUALIFICATION
67
FAILURE OF BIDDING
GROUNDS:
68
FAILURE OF BIDDING
EFFECTS:
3)Re-bidding
4)Re-advertisement
69
IX. AWARD OF CONTRACT
70
IX. AWARD OF CONTRACT
PROCUREMENT PROCESS
From Opening of Bids to Award of Contract shall
NOT EXCEED 3 MONTHS
71
PERFORMANCE SECURITY
Posted by winning bidder upon signing of contract to
guarantee performance of obligation, in such form and amount
specified in the Bidding Documents.
72
PERFORMANCE SECURITY
73
PERFORMANCE SECURITY
Amount
Form of Performance Security Performance Security
(% equal to the Contract Price)
a) Cash or cashier’s/manager’s
check
5% (Goods ) & 10% (Infra)
b) Bank guarantee/draft or
Irrevocable LC
c) Surety bond callable upon
demand 30%
74
RESERVATION CLAUSE
HOPE reserves the right to:
◦ Reject any and all bids;
◦ Declare a failure of bidding;
◦ Not award the contract.
GROUNDS:
1. Prima facie evidence of collusion;
2. BAC is found to have failed in following the prescribed bidding procedures;
3. For justifiable reasons, the award of contract will not redound to the benefit of
the Government:
Physical and economic conditions have significantly changed;
Project is no longer necessary
Source of funds for the project has been withdrawn/reduced.
75
NOTICE TO PROCEED
Issued to the successful bidder together with the copy of the
approved contract within 3 cd from date of approval
Contract effectivity date should be provided in the NTP,
which should not be later than 7 cd from its issuance
BAC Secretariat should post a copy of the NTP and the
approved contract in the PhilGEPS or PE’s website within 15
cd from issuance of NTP
76
CONTRACT IMPLEMENTATION
GUIDELINES FOR THE
PROCUREMENT OF GOODS,
SUPPLIES AND MATERIALS
77
AMENDMENT TO ORDER
Issued at any time by the procuring entity in cases of:
1. Emergency
2. Fortuitous event
REASONS FOR ISSUING:
1. Necessary adjustments within the general scope of the contract in any one
or more of the following:
a) drawings, design or specifications (if specifically manufactured for Government)
b) method of shipment or packing; or
c) place of delivery.
2. Additional items needed and necessary for the protection of the goods,
which were not included in the original contract.
78
SUSPENSION OF WORK
79
LIQUIDATED DAMAGES
Bidder shall pay an amount equal to 1/10 of 1% of the cost of the cost of
delayed goods scheduled for delivery for every day of delay until such
goods are finally delivered and accepted by the procuring entity.
80
LIQUIDATED DAMAGES
81
ADVANCE PAYMENT
Made only after prior approval of the President.
Single advance payment not to exceed 50% of the contract for
the following services:
◦ Hotel and restaurant services
◦ Use of conference/seminar and exhibit areas
◦ Lease of office space
Advance payment not to exceed 15% allowed to address
contingencies arising from natural or man-made calamities in
areas where “state of calamity” has been declared
82
ADVANCE PAYMENT
For goods, 15% of the contract price shall be paid within 60
days from signing of contract and upon submission of a claim
and a bank guarantee. (Amended by M.O. 15, series of 2011)
83
THANK YOU!!
Contact us:
TeleFax: (632)900-6741 to 44
84