REDUCE
WORKING CYCLE
CURING
DETERMINE PROJECT
Project Team & Responsible
Reduction Working Cycle Of Curing Machine
Title Lead the team, define the target,
reporting to sponsor & team member.
Audit of process steps improvement.
The losses working cycle not achieve the target, actual 2,4% Ilham
Description
meanwhile the target is 2%. Have a gap 0,4% from the target Perform analysis and improvement
proposals from cleaning mold activities
Panji
Methods;
Methods ECRS, SMED, PKE, Filming and Recording, Time Measurement
& Tools;
Tools Stopwatch, Handycam, Spagheti Chart, Pareto Chart, Flow Process
Diagram
INTRODUCTION
STEP 1 (Choose one set-up type, define start point and target) STEP 4 (Analyse and solve anomalies)
1.1 Identification of set-up types 4.1 Analysis of priorities and anomalies
1.2 Data Collection – Historical Data 4.2 Determination of countermeasures
1.3 Setup the continuous data collection system 4.3 Implementation of countermeasures
1.4 Priority analysis 4.4. Introduction of monitoring table
1.5 Define the start point and the target 4.5. Cost-benefit analysis
STEP 2 (Define the current best standar and train the oprators) STEP 5 (Further improve the standad)
2.1 Identifying IP code 5.1 Improvement the adjustment methods
2.2 Calculate forklift requirements based on workload
2.3 Filming and formalization of current method
2.4 Proposals For Improvements Of The Ecrs Analysis
Agreement
2.5 Filming and formalization of the best employer
2.6 Operator training
STEP 3 (Introduce a system to record time & anomalies)
3.1 Definition of the time recording system and anomalies
3.2 Definition who, what, when ?
3.3 Provide Operator training
3.4 Daily monitoring of the system and new training if necessary
CHOOSE ONE SETUP TYPE, DEFINE START POINT AND TARGET
STEP 1
Feb
March
Apr
May
Jun
Jul
Aug
Sept
Average
Actual Target
Goal Objective : Setup type Actual time (min) Freqday Total time actual (min) Percentage
Reduce working cycle time Mould cleaning (dry ice) 119,98 26 3119,6 52,3%
Bladder change 66,00 26 1716,1 28,8%
Actual Condition : Mould cleaning (sandblast) 172,83 6 1037,0 17,4%
Average working cycle loss from Jan-Sept 2022 is 2,4%. Vents hole mould cleaning 33,29 1 33,3 0,6%
Coating bladder 21,00 1 21,0 0,4%
Target : Coating mould 8,66 2 17,3 0,3%
Reduce working cycle to 2%
Reassembly bladder 16,27 1 16,3 0,3%
Oring change (PCI) 0,00 0 0,0 0,0%
How to :
Reduce set up time on working cycle activity & remove waiting Total 5960,5 100%
CHOOSE ONE SETUP TYPE, DEFINE START POINT AND TARGET
STEP 1
P ARE T O CHART
3500.0 120.0%
98.8% 99.4% 99.7% 100.0% 100.0%
3000.0 100.0%
2500.0
81.4%
80.0%
2000.0
52.5% 60.0%
1500.0
40.0%
1000.0
500.0 20.0%
3119.6 1716.1 1037.0 33.3 21.0 17.3 0.0
0.0 0.0%
Coating Mould
Bladder Change
STEP 2
DRY ICE
DEFINE THE CURRENT BEST STANDAR AND TRAIN THE OPERATORS
STEP 2 (Filming and formalization of current method) DRY ICE
1 MC Dry Ice Move the Dry Ice Machine tp curing area x 0,18 6 x x
2 MC Dry Ice move the trolley of green tyre x 0,82 8 x x
Time After
No Macro Activity Description Time (Min) NVA VA E C R S Action
Reduction
1 MC Dry Ice Move the Dry Ice Machine tp curing area 0,18 x 0,18
2 MC Dry Ice move the trolley of green tyre 0,82 x x Can be carry out by operator production 0,00
Prepare all equipment to a toolbox before starting cleaning mold (Impact drill) and brint the
3 MC Dry Ice preparation the dry ice machine 6,28 x x 0,5
toolbox closer to curing machine area
4 MC Dry Ice tighten the nut on the mold 0,72 x 0,72
5 MC Dry Ice set the blader 0,33 x 0,33
6 MC Dry Ice entry the molding area 0,72 x 0,72
7 MC Dry Ice set the curing machine 1,35 x 1,35
8 MC Dry Ice tighten the nut on the mold 1,23 x 1,23
9 MC Dry Ice preparation for cleaning 0,73 x x Provide power supply at every location of curing machine 0,20
10 MC Dry Ice install the hose of drying ice machine 0,65 x 0,65
11 MC Dry Ice Wear ear plug 0,13 x 0,13
12 MC Dry Ice filling dry ice machine 0,77 x x Standardize dry ice machine filling (7 spoon in a time) 0,23
13 MC Dry Ice Wear safety helmet 0,08 x 0,08
14 MC Dry Ice cleaning the top mold with a dry ice machine 4,28 x 4,28
15 MC Dry Ice filling dry ice machine 0,50 x x Standardize dry ice machine filling (7 spoon in a time) 0,23
16 MC Dry Ice cleaning the top mold with a dry ice machine 3,58 x 3,58
17 MC Dry Ice filling dry ice machine 0,47 x x Standardize dry ice machine filling (7 spoon in a time) 0,23
18 MC Dry Ice clean the bottom mold with a dry ice machine 3,50 x 3,50
19 MC Dry Ice filling dry ice machine 0,23 x x Standardize dry ice machine filling (7 spoon in a time) 0,23
20 MC Dry Ice clean the bottom mold with a dry ice machine 1,52 x 1,52
21 MC Dry Ice tidy up the dry ice machine tools and remove the hose 1,73 x 1,73
22 MC Dry Ice clean the mold with high pressure air 0,32 x 0,32
23 MC Dry Ice set up curing machine 2,53 x 2,53
24 MC Dry Ice tidy up dry ice machine tools 4,08 x x Bring a tool box to arrange all equipment neat and fast 3,00
25 MC Dry Ice moving dry ice machine from curing mc to eff area 0,18 x 0,18
Total 36,93 27,67
Give directions to the curing machine operator to move the trolley in front of the machine
2 move the trolley of green tyre
where the mold cleaning will be done
Provide toolboxes according to work needs closer the curing machine, for mold cleaning
activities with the dry ice method the tools needed are as follows;
3 preparation the dry ice machine
- Impact drill
9 preparation for cleaning Provide power supply at every location of curing machine
12
15
filling dry ice machine Standardize dry ice machine filling (7 spoon in a time)
17
19
24 tidy up dry ice machine tools Bring a tool box to arrange all equipment neat and fast
STEP 2
SANDBLAST
DEFINE THE CURRENT BEST STANDAR AND TRAIN THE OPERATORS
STEP 2 (Filming and formalization of current method) SANDBLAST
50.0 20%
0.0 0%
A-B B-A A-C C-A
1 searching the equipment x x Prepare all equipment before start uninstalling bladder
3 push down green tyre from curing machine x x Can be carry out by operator production
6 move trolley and equipment x x the activity can be carry out after move trolley
7 searching the equipment x x Prepare all equipment before start uninstalling bladder
12 move the blader from curing machine x x Place the bladder around the curing machine in a bladder pallet which is sufficient for 2 bladders
14 move the blader from curing machine x x Place the bladder around the curing machine in a bladder pallet which is sufficient for 2 bladders
17 move the equipment and klem ring x x operator can bring a pallete to bring more equipment
21 release the eyebolt mould from mould x x this activity can be carry out at the same time before move the mold to mold pallete
29 setup the sandblasting machine x x This Activity should be carry out by operator 2 when the sandblast machine is delay
56 take the bladder from the bladder area x x Place the bladder around the curing machine in a bladder pallet which is sufficient for 2 bladders
57 move the bladder into the curing machine x x Place the bladder around the curing machine in a bladder pallet which is sufficient for 2 bladders
60 install the bladder x x Prepare and bring all equipment near arround the curing machine
63 cleaning mould with high pressure air x x liquid cleaning should be available before instalation
TIME AFTER
61,8
ESTIMATE REDUCTION TIME
85,2-61,8 = 23,4 Minutes
REDUCTION
PROPOSALS FOR IMPROVEMENTS OF THE ECRS ANALYSIS AGREEMENT
(SANDBLAST)
STEP 2 (Proposals For Improvements Of The Ecrs Analysis Agreement) SANDBLAST
12
11
14
Place the bladder around the curing machine in a bladder pallet which is
sufficient for 2 bladders hook the blader with eyebolt
56
57 13
- Hammer
17
- Pahat
- Impact drill
60
- L key 61 Install Mold
63 - Cleaning Liquid
DATE Project Manager
Sponsor
STEP 2 CHANGE
BLADDER
DEFINE THE CURRENT BEST STANDAR AND TRAIN THE OPERATORS
STEP 2 (Filming and formalization of current method) CHANGE BLADDER
WITH FORKLIFT
FILMING AND FORMALIZATION OF CURRENT METHOD (CHANGE BLADDER)
STEP 2 (Filming and formalization of current method) CHANGE BLADDER
Macro Activity
No Description Time (Minutes) Distance (m)
Activity
Uninstall Bladder
3 Open Bladder X 0,15
4 Installation eye bolt and link to hook in lifter X 0,90
5 Move bladder with forklift x 0,73 1
6 Close press mould X 1,23
7 Move bladder to prep. Table X 2,00 51
8 Release clamp ring top from bladder X 0,80
9 Release blader X 1,17
Assembly Blader
Separate internal and external steps Convert internal to external Streamline all aspects of setup operations
Description Time Ext Int Description Time Ext Int Eliminate Description Time Ext Int
Uninstall Bladder Release Klem Centerpost 1,47 X Uninstall Bladder Release Klem Centerpost 1,47 X Assembly Blader Release clamp ring top from bladder 0,80 X
Uninstall Bladder Down Centerpost 0,35 X Uninstall Bladder Down Centerpost 0,35 X Assembly Blader Release blader 1,17 X
Uninstall Bladder Open Bladder 0,15 X Uninstall Bladder Open Bladder 0,15 X Assembly Blader Clean klem ring blader 0,28 X
Uninstall Bladder Installation eye bolt and link to hook in lifter 0,90 X Uninstall Bladder Installation eye bolt and link to hook in lifter 0,90 X Assembly Blader Searching the new blader 2,18 X
Uninstall Bladder Move bladder with forklift 0,73 X Uninstall Bladder Move bladder with forklift 0,73 X Assembly Blader assembly the new blader 4,35 X
Uninstall Bladder Close press mould 1,23 X Uninstall Bladder Close press mould 1,23 X Assembly Blader Installation eye bolt and link to hook in lifter 0,87 X
Uninstall Bladder Move bladder to prep. Table 2,00 X Uninstall Bladder Move bladder to prep. Table 2,00 X Assembly Blader move blader to curing area 1,57 X
Assembly Blader Release clamp ring top from bladder 0,80 X Assembly Blader Release clamp ring top from bladder 0,80 X Uninstall Bladder Release Klem Centerpost 1,47 X
Assembly Blader Release blader 1,17 X Assembly Blader Release blader 1,17 X Uninstall Bladder Down Centerpost 0,35 X
Assembly Blader Clean klem ring blader 0,28 X Assembly Blader Clean klem ring blader 0,28 X Uninstall Bladder Open Bladder 0,15 X
Assembly Blader Searching the new blader 2,18 X Assembly Blader Searching the new blader 2,18 X Uninstall Bladder Installation eye bolt and link to hook in lifter 0,90 X
Assembly Blader assembly the new blader 4,35 X Assembly Blader assembly the new blader 4,35 X Uninstall Bladder Move bladder with forklift 0,73 X
Assembly Blader Installation eye bolt and link to hook in lifter 0,87 X Assembly Blader Installation eye bolt and link to hook in lifter 0,87 X Uninstall Bladder Close press mould 1,23 X
Assembly Blader move blader to curing area 1,57 X Assembly Blader move blader to curing area 1,57 X install bladder up the press mould 1,00 X
Install Blader up the press mould 1,00 X Install Blader up the press mould 1,00 X install bladder entry to mould area 0,40 X
Install Blader entry to mould area 0,40 X Install Blader entry to mould area 0,40 X install bladder set the left one blader 0,18 X
Install Blader set the left one blader 0,18 X Install Blader set the left one blader 0,18 X install bladder check the left one blader 0,83 X
Install Blader check the left one blader 0,83 X Install Blader check the left one blader 0,83 X install bladder change oring 1,32 X
Install Blader change oring 1,32 X Install Blader change oring 1,32 X install bladder move the new blader to curing machine 1,63 X
Install Blader move the new blader to curing machine 1,63 X Install Blader move the new blader to curing machine 1,63 X install bladder installation the new blader 2,82 X
Install Blader installation the new blader 2,82 X Install Blader installation the new blader 2,82 X install bladder up the center post 0,25 X
Install Blader up the center post 0,25 X Install Blader up the center post 0,25 X install bladder set the bladder 0,18 X
Install Blader set the bladder 0,18 X Install Blader set the bladder 0,18 X install bladder up the center post 0,58 X
Install Blader up the center post 0,58 X Install Blader up the center post 0,58 X install bladder clean the blader 1,15 X
Install Blader clean the blader 1,15 X Install Blader clean the blader 1,15 X install bladder Check baut/mur at unloader dan turn on mesin 0,57 X
Install Blader Check baut/mur at unloader dan turn on mesin 0,57 X Install Blader Check baut/mur at unloader dan turn on mesin 0,57 X install bladder Filling checksheet 1,87 X
Install Blader Filling checksheet 1,87 X Install Blader Filling checksheet 1,87 X install bladder Reset counter bladder ke o 3,07 X
Install Blader Reset counter bladder ke o 3,07 X Install Blader Reset counter bladder ke o 3,07 X install bladder Move bladder to prep. Table 2,00 X
Total 33,9 Total 33,9 Total 33,9
PROPOSALS FOR IMPROVEMENTS OF THE ECRS ANALYSIS AGREEMENT
(CHANGE BLADDER)
STEP 2 (Proposals For Improvements Of The Ecrs Analysis Agreement) CHANGE BLADDER
Time After
No Macro Activity Description Time Ext Int NVA VA Eliminate Combine Rearrange Simplify Action Status
Reduction
1 Assembly Blader Release clamp ring top from bladder 0,80 X X 0,80
2 Assembly Blader Uninstall bladder 1,17 X X 1,17
3 Assembly Blader Clean klem ring bladder 0,28 X X 0,28
4 Assembly Blader Searching the new blader 2,18 X X x Prepare the bladder to be replaced 2,18
5 Assembly Blader assembly the new blader 4,35 X X 4,35
6 Assembly Blader Installation eye bolt and link to hook in lifter 0,87 X X 0,87
7 Assembly Blader move blader to curing area 1,57 X X x Bring the new blader with bladder pallet in one time transport 1,57
8 Uninstall Bladder Release Klem Centerpost 1,47 X X 1,47
9 Uninstall Bladder Down Centerpost 0,35 X X 0,35
10 Uninstall Bladder Open Bladder 0,15 X X 0,15
11 Uninstall Bladder Installation eye bolt and link to hook in lifter 0,90 X X x Use threaded lifting pins 0,10
12 Uninstall Bladder Move bladder with forklift 0,73 X X x Carry out activities in accordance with work instructions and train the operator 0,50
13 Uninstall Bladder Close press mould 1,23 X X 1,23
14 Install Blader up the press mould 1,00 X X 1,00
15 Install Blader entry to mould area 0,40 X X X Carry out activities in accordance with work instructions and train the operator 0,00
16 Install Blader set the left one blader 0,18 X X X Carry out activities in accordance with work instructions and train the operator 0,00
17 Install Blader check the left one blader 0,83 X X X Carry out activities in accordance with work instructions and train the operator 0,83
18 Install Blader change oring 1,32 X X x Provide a place for equipment as needed 0,00
19 Install Blader move the new blader to curing machine 1,63 X X 1,63
20 Install Blader installation the new blader 2,82 X X 2,82
21 Install Blader up the center post 0,25 X X 0,25
22 Install Blader set the bladder 0,18 X X 0,18
23 Install Blader up the center post 0,58 X X 0,58
24 Install Blader clean the blader 1,15 X X 1,15
25 Install Blader Check sensor at unloader dan turn on mesin 0,57 X X X Carry out activities in accordance with work instructions and train the operator 0,00
26 Install Blader Filling checksheet 1,87 X X 1,87
27 Install Blader Reset counter bladder ke o 3,07 X X 3,07
28 Install Blader Move bladder to prep. Table 2,00 x X x put the old one blader to blader pallet 0,00
Total 33,9 17,2
2 Uninstall bladder
28
DEFINE THE CURRENT BEST STANDAR AND TRAIN THE OPRATORS
STEP 2 (Workload forklift)
Description Duration Regulation Standard
(Minute) (according to standard) Minutes
Available time/shift 100% 1.440
Break 135 135
Briefing 10 10
Allowance 7 7
Available time/shift (maximum) 1.288
Reduce duration and frequency per day
Total Usage Time Duration Regulation Frequency Total
(Minute) (according to standard) Per Day minutes
Mould Cleaning-Sandblast 90,0 6,0 540,0
Change blader 30,7 26,0 798,0
Change Mould 61,8 10,0 618,0
Pembuangan scrap blader 17,3 1,0 17,3
Pengisian dry ice 27,2 1,0 27,2
Tidy up rack scrap mould 63,0 3,0 189,0
Tidy up rack mould before after
164,0 3,0 492,0
cleaning
Loading/unload mold in warehouse 63,6 0,6 36,2
change the battery 16,0 1,0 16,0
Saturation 106,14%