JULY 1, 202I
1
Syed Bilal Ghazi

PERSONAL INFORMATION

 Name : Syed Bilal Ghazi

 Profession : Engr. Geologist

 Position in Firm : Principal Materials Specialist

 Specialization : Masters in Engineering Geology 1991

 Years with NESPAK : 2008 till date

 Overall Experience : 30 years

 Countries of Work : Pakistan, Saudi Arabia


2
Syed Bilal
Ghazi

Employment Record
Employer Position From To
NESPAK (Pvt.) Ltd,
Materials Specialist March, 2008 Till Date
Lahore
M/S Osmani and
Materials Specialist February, 2006 Oct, 2007
Company (Pvt.) Ltd.

Al-Omeir Trading &


Contracting Company, Materials Specialist December, 2001 2005
Saudia Arabia

Raashid Associates
Materials Specialist May, 2000 Nov,2001
(Pvt.) Ltd.
Saad Ullah & Brothers
Engineering & Materials Specialist September, 1999 May, 2000
Construction

M/S Republic Engineer


Engineering Corporation Geologist/Material August, 1992 June, 1999
(Pvt.) Ltd. specialist
Engr.
Rockwell Corporation
Geologist/Material September, 1989 August, 1992
(Pvt.) Ltd.
specialist
3
Syed Bilal Ghazi

CAREER PROFILE

Professional Experience: Over 30 Years


NESPAK: Principal Material Specialist , SED , 7 years
2014 to Bridge over River Ravi at Malfatyana, Rathoa_Haryam
date
bridge Mirpur AJK, Lahore Orange line,,

NESPAK – Senior Materials Specialist, SED


2014 - 2011 RATHOA – HARYAM BRIDGE Mirpur AJK: 3Years
Construction of Approach Road and Two Bridges Mirpur

NESPAK - Senior Materials Specialist H&TD : 3 Years


2011 -2008 Shalimar Interchange. Lahore Ring Road, Rehabilitation of Lahore
Multan Road, Widening of Canal Bank Road etc

2008 –1991 PRIVATE FIRMS : REC (PVT)LTD, OSMANI CONSULTANTS,


RASHEED ASSISIATES , SKB, OTC SAUDI ARABIA AS
MATERIAL ENGINEER : 17 Years

4
Syed Bilal Ghazi

SIGNIFICANT PROJECTS)
Bridge Over River Ravi at
Malfatyana Rs 1910 million
:
421 m long bridge
3.6 km approach roads (
1.5 km long Guide banks
1.4 km Cunnett

RESPONSIBILTIES:
Have been performing the
duties as RE on special demand
of the Client. Lead the site and Construction of RCC Lining of Power Channel
lab staff. Ran the project
smoothly with collaboration of
contractor, consultant and the
Client. Processed IPCs and
EPCs. Successfully faced the
Audit team.
Fully performed the duties of
Materials specialist .
5
Syed Bilal Ghazi

RATHOA – HARYAM BRIDGE Mirpur approved cost 6480.159 M


AJK
 2.97 KM Long bridge
 4.2 km approach road
 160 m single span Steel ached bridge (to
be erected)

RESPONSIBILITES:
Worked as Principal Martials Specialist.
Prepared different classes of concrete mix
designs. Supervised all quality control
tastings. Maintained the record upto entire
satisfaction of the Client. Lead the piling
team and trained the inspectors for stressing
of girders and deck slab. Successfully delt
contractual maters with the Client such as
approval of additional staff, clearance of
pending invoices.
6
Syed Bilal Ghazi

SHALIMAR INTERCHANGE PROJECT 5/6/2008 to 31/12/2009 Rs 3380 M

 1.6 KM FLYOVER
 TWO UNDER PASSES

 BRIDGE

 ALLIED ROADS

 Responsibilties
 Worked as Senior Materials Specialist .
Strictly adopted QA/Qc procedures and
carried out the required testing as per
the specifications. Prepared CMDs and
JMFs.
 Contractor clamed the price 15 million
for admixture used in concrete . Which I
rejected. Contractor took the case to
Arbitration, where I successfully
defended it.
7
Syed Bilal Ghazi

Responsibilities

• Reviewing Contractor’s construction schedules


• Selection & approval of borrow areas and other construction
materials in conformance with stipulated standards.
• Ensuring execution of all the site works in accordance with
project specifications and drawings.
• Guiding field staff for Implementation of Quality Control &
Quality Assurance (QC&QA) procedures at site.
• Processing IPCs, reviewing variation orders and rate analysis etc.
• Preparation of Daily, Weekly and Monthly Progress Reports.
• Preparation of concrete mix designs for different classes
• Preparation
l of Job Mix formula for asphalt works

8
Syed Bilal Ghazi

OTHER RESPONSIBILITIES

• Problem solving
Project monitoring reports
• Pre-shipment Inspection of manufacturing units/ sources
• Team Leader
• Training of technicians and inspector and training of
civil Engineering students during their internship

9
Syed Bilal Ghazi

ACHIEVEMENTS

NESPAK acknowledged my services


and awarded me with Honorarium
and letters of appreciation ,that
means to me the most.

10
Syed Bilal Ghazi

Why I believe I should be promoted to Grade-12

 I believe because I have got the required experience, technical


expertise and leadership skills which I want to utilize by being a
key member of Quality assurance team.

I am ready to take more responsibilities.

THANK YOU SIR


11

You might also like