23-8-7 ICP Baching Plant (Draft)
23-8-7 ICP Baching Plant (Draft)
Cooperation Agency
7 August 2023
1. Facility of batching plant
(1) Overview of batching plant
Cement silo
Storage bin
Conveyor belt
weighing
device
Conveyor belt
Additive
Aggregate pull-out gates
tank
Hopper
2
(2) Aggregate stock yards
3
(3) Transfer of aggregate by conveyor belt
Conveyor belt
Aggregate pull-out gates
t
or bel
onvey Mixer
C
Storage bin
Weighing
device
Mixer
Additive
tank
Batching plant
Monitor TV
Operation room
Camera
Measurement of water rate of fine aggregate Adjustment of Job-mix formula at the site
8
3. Compression test
• Judged theTest results shall not be less than 85% of the design strength
• Average of 3 consecutive test results shall be not less than the design strength
test results of the average of one pair test specimens at one time
Using the below graph, the concrete production procedures shall be checked
If the test values become stable enough for secure design strength, it is possible to
change the job-mix formula to decrease cement and water volumes during the
project
9
4. Common mistakes in the field
10
Common mistakes Check sheet
Mixture of different kinds of aggregate in the silo 1 . Reference regulation
2. Activities of PMI
Deferent
type of Periodically go to the batching plant
aggregate Monitor different kinds of aggregate
mix or not
3. Activity of DGH
Deferent
type of Monitor the situation of aggregate
stock yard by the report from PMI
aggregate
11
Common mistakes Check sheet
Mixture of different kind of aggregate in the stock yard 1 . Reference regulation
General Specifications for Freeways and
Toll Roads, August 2020 (Fine and course
aggregate shall be stored separately to
prevent contamination by foreign material)
2. Activities of PMI
Periodically go to the batching plant
Monitor different kinds of aggregate
mix or not
12
5. Good practice in the field
13
(1) Sprinkler in the stock yard General Specifications for Freeways and Toll
Roads, August 2020 (Aggregate shall be
stored so as to protect it from direct rays o the
sun
Photo in Indonesia
Photo in Indonesia
Photo in Indonesia
Photo in Indonesia
Photo in Indonesia
Photo in Indonesia
19
(6) Name plate of the inlet of cement silo
Photo in Indonesia
Photo in Indonesia
Photo in Indonesia
21
(8) Test pieces are stored in separate tanks for each
day of the week
Test pieces are stored in separate water tanks for each day of the week.
The date, place, and kinds of concreting are clearly indicated in the test
pieces 22
(9) Concrete mixer is well cleaned periodically
23