LINE CROSSING
Introduction
Work Scope
Required Tools & Equipment
Manpower
Pre-Stringing Activity For Crossing
Stringing Methodology
Job Safety Procedure/Safety Precautions
Risk Assessment
Work At Height Rescue Plan
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING
INTRODUCTION/PURPOSE
• To provides the requirements for stringing activity on
live 33kv line crossing.
• To includes the requirement for safety and quality
control.
• Layout all necessary requirements to achieve safety
and standard quality of said OHTL project.
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING
WORK SCOPE
Crossing of Live Existing 33KV OHTL
Distribution Line
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING
REQUIRED TOOLS & EQUIPMENT
Tensioner
Puller
Cable Drum Trailer
Boom Truck
Full body harness safety belts
5 No. Hydraulic Cranes of Different Capacity
Bull Wire
Pilot Wire
4 No. Nylon Ropes(350m each)
Stand for conductor reel
Work Bridge
Traveler/Pulley
Tool Box
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING
Manpower
Construction Manager 1 No.
Site Engineer 1 No.
HSE Engineer 1 No.
Gang Leader 1 No.
Forman 1 No.
Lineman 4 No.
Fitter 6 No.
Labor Person 4 No.
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING
STRINGING METHODOLOGY
Conductor pulling will be done by utilizing 4 cranes and wooden spreader
Positioning of cranes on both sides of 33kv live line two at each side with wooden
spreader beem
Both cranes will hold the wooden spreader beem at the required level and
position
5th crane will hold the conductor traveler for nylon rope/pilot wire passing
Fiber wire rope shall be passed from conductor traveler
Conductor shall be pulled under controlled tension method
Above same method is repeated for stringing of all phases of circuit I&II.
After completion of pulling conductor shall be removed from traveler while doing
rough sag.
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING