This document outlines the pipe work for the Al Fursan city fire hydrant network. It involves laying HDPE and ductile iron pipes underground ranging from 110mm to 600mm in diameter, totaling over 94,000 linear meters. 24 highly skilled personnel will excavate, lay pipes, install fittings and valves, and backfill trenches in sections of 250 linear meters per day over 182 working days to complete the over 110,000 linear meter project within 7 months. Equipment like excavators, compactors, and vehicles will support the work of the 3 installation teams and 1 testing team.
This document outlines the pipe work for the Al Fursan city fire hydrant network. It involves laying HDPE and ductile iron pipes underground ranging from 110mm to 600mm in diameter, totaling over 94,000 linear meters. 24 highly skilled personnel will excavate, lay pipes, install fittings and valves, and backfill trenches in sections of 250 linear meters per day over 182 working days to complete the over 110,000 linear meter project within 7 months. Equipment like excavators, compactors, and vehicles will support the work of the 3 installation teams and 1 testing team.
This document outlines the pipe work for the Al Fursan city fire hydrant network. It involves laying HDPE and ductile iron pipes underground ranging from 110mm to 600mm in diameter, totaling over 94,000 linear meters. 24 highly skilled personnel will excavate, lay pipes, install fittings and valves, and backfill trenches in sections of 250 linear meters per day over 182 working days to complete the over 110,000 linear meter project within 7 months. Equipment like excavators, compactors, and vehicles will support the work of the 3 installation teams and 1 testing team.
WORKSCOPE : FOR HDPE PIPE & ductile NETWORK laying. • BELOW GROUND 1.4 METER HDPE. • 2 SIZES 110 mm and 160 mm.. HDPE • 18320LM and 76000LM. Total trench (94320LM.) • Below ground 1.4meter iron Ductile pipe. • 300mm,400mm,500mm and 600mm. • 13350LM,1800LM,930LM and 90LM respectively. Total trench excavation(16170 LM) • Total linear meter 18320 linear meter and 76000 linear meter respectively.
• Total trench excavation 110490 linear meter.
STAFF,TOOL & EQUIPEMENT ESTIMATED
• HIGH SKILLED PERSONEL ..------------24 NUMBERS IN 4 GROUPS
• PROJECT LEADER.---------------------------1 NOS • POCLAIN FOR EXCAVATION -------------3 NOS • COMPACTOR MACHINES -------------------3 NOS • JCB MACHINES FOR BACK FILLING---2 NOS • LABOR TO SITE LOGISTIC ------------------3 SITE VEHICLES. • DEISEL FUEL DUMPER TANK-------------1 FOR DAILY FUEL SUPPLY. • MOVEABLE GENSET -----------------1 NOS WORK STRATIGY/PLAN. TIME 7 MONTHS 182 WORKING DAYS (28 FRIDAYS) • Client Serveyer Will Mark The Excavation Area 250 Lm Each Day. • At The Same Time every 100 Meter The area bed As Per boq will Be Compacted And Pipe will Be Laid. • After Fusing /Joints valves And Acessories Will be Firred And Tested.Every 100 Meters or Upto The next Fitting Acessory. • After Positive report The Line Will Be Buried And Compacted. • This process Will Be Repeated As Per The Drawing fittings & accessories and for testing commissioning. Calculation based on : • Three teams each will Excavation 250 lm deliver 250 meter excavation / pipe laying /joints and accessories Pipe Bed Compaction 250 lm fitting as per these steps per day Pipe laying 250 lm. • Forth team will test the pipe and finalize burring and compaction. Acessories fitting and testing. PROGRESS CHART WILL BE AS BELOW: 1ST MONTH 2ND MONTH 3RD MONTH 4TH MONTH EXCAVATION 750X3 EXCAVATION 750X3 EXCAVATION 750X3 EXCAVATION 750X3 TEAM IN 26 DAYS TEAM IN 26 DAYS TEAM IN 26 DAYS TEAM IN 26 DAYS =15790LM =15790LM =15790LM =15790LM
5TH MONTH 6TH MONTH 7TH MONTH
EXCAVATION 750X3 EXCAVATION 750X3 EXCAVATION 750X3 Final testing and TEAM IN 26 DAYS TEAM IN 26 DAYS TEAM IN 26 DAYS commissioning =15790LM =15790LM =15790LM
TOTAL IN 182 DAYS =15790 lmX7=110490