You are on page 1of 7

Al Fursan city pipe work.

HDPE AND IRON DUCTILE FOR FIRE HYDRANT.


WORKSCOPE : FOR HDPE PIPE & ductile NETWORK
laying.
• BELOW GROUND 1.4 METER HDPE.
• 2 SIZES 110 mm and 160 mm.. HDPE
• 18320LM and 76000LM. Total trench (94320LM.)
• Below ground 1.4meter iron Ductile pipe.
• 300mm,400mm,500mm and 600mm.
• 13350LM,1800LM,930LM and 90LM respectively. Total trench excavation(16170 LM)
• Total linear meter 18320 linear meter and 76000 linear meter respectively.

• Total trench excavation 110490 linear meter.


STAFF,TOOL & EQUIPEMENT ESTIMATED

• HIGH SKILLED PERSONEL ..------------24 NUMBERS IN 4 GROUPS


• PROJECT LEADER.---------------------------1 NOS
• POCLAIN FOR EXCAVATION -------------3 NOS
• COMPACTOR MACHINES -------------------3 NOS
• JCB MACHINES FOR BACK FILLING---2 NOS
• LABOR TO SITE LOGISTIC ------------------3 SITE VEHICLES.
• DEISEL FUEL DUMPER TANK-------------1 FOR DAILY FUEL SUPPLY.
• MOVEABLE GENSET -----------------1 NOS
WORK STRATIGY/PLAN.
TIME 7 MONTHS 182 WORKING DAYS (28 FRIDAYS)
• Client Serveyer Will Mark The Excavation Area 250 Lm Each Day.
• At The Same Time every 100 Meter The area bed As Per boq will Be
Compacted And Pipe will Be Laid.
• After Fusing /Joints valves And Acessories Will be Firred And Tested.Every
100 Meters or Upto The next Fitting Acessory.
• After Positive report The Line Will Be Buried And Compacted.
• This process Will Be Repeated As Per The Drawing fittings & accessories
and for testing commissioning.
Calculation based on :
• Three teams each will Excavation 250 lm
deliver 250 meter
excavation / pipe laying
/joints and accessories Pipe Bed Compaction 250 lm
fitting as per these steps per
day
Pipe laying 250 lm.
• Forth team will test the
pipe and finalize burring
and compaction. Acessories fitting and testing.
PROGRESS CHART WILL BE AS
BELOW:
1ST MONTH 2ND MONTH 3RD MONTH 4TH MONTH
EXCAVATION 750X3 EXCAVATION 750X3 EXCAVATION 750X3 EXCAVATION 750X3
TEAM IN 26 DAYS TEAM IN 26 DAYS TEAM IN 26 DAYS TEAM IN 26 DAYS
=15790LM =15790LM =15790LM =15790LM

5TH MONTH 6TH MONTH 7TH MONTH


EXCAVATION 750X3 EXCAVATION 750X3 EXCAVATION 750X3 Final testing and
TEAM IN 26 DAYS TEAM IN 26 DAYS TEAM IN 26 DAYS commissioning
=15790LM =15790LM =15790LM

TOTAL IN 182 DAYS =15790 lmX7=110490


APPROX
Naseem Kareem Baksh Est
Jeddah old Makkah road kilo 14.KSA contact 0594391285 Engr..Ihtesham

You might also like