You are on page 1of 15

logistic Route Survey Report

From: Eppothumvendran Bypass To: O.Saravanapuram PSS


Length: 17.6 Km Approx
Survey Conducted by:

Vestas Team: Engie Team:


Major Balasubramaniyan R Vasanth Kumar
Balaganesan Sangiah
Venkatesan Arumugam
Sridhar A
Sundar
Manikandan A
EAGLE VIEW..
In Pauvanthanai to eppothumvendran

LC required for 2 no of 11Kv line


In kailasanathapuram
Gamesa bypass

House present near to road and it


hindrance the material movement
Service line should be removed
Road undulated needs filling work.
All these lines existing in
pasuvanthanai to kailasanathapuram
Gamesa bypass
LC Required 33Kv Gamesa line F4/345/P9 to P8
for the 33Kv Gamesa line F4/345/P5 to P4
mentioned 33Kv Gamesa line F4/484/p20 to
lines p21
33Kv Gamesa line F4/484/p18 to
p17
In Kuthiraikulam,
Heightening required during
material movement for Scada cable
stringed under power conductor in
33Kv Gamesa line of F4/P61 near
chillankulam
 Heightening or LC required during
material movement for 4 No of service
line in front of muthukarupan school
 Heightening or LC required during
In material movement for service line
chillankulam, present ahead of culvert
 Development required from tar road to
O.Saravanapuram junction
 Cause way development required at
O.saravanapuram road
 LC required for LT line in chillankulam to
O.Saravanapuram road
In chillankulam to
O.Saravanapuram road

Bypass required- to overcome the


bottle neck near culvert, Not suitable
for material movement.
In O.Saravanapuram
Guarding clearance to be provided for 33Kv Gamesa line of F4/P30 to P29
Scada cable heightening to be provided for 33Kv Gamesa line of F5/207/p31
Development required in turning at nearby temple
Tree (Tamarind)cutting required in front of temple
Tree (Babool)cutting required in road to pss at a house in O.saravanapuram
Clearance required for TV cable
House situated nearby road, horizontal clearance not available
Development required in left side turning at O.saravanapuram
In O.saravanapuram to PSS road
Guarding clearance required in 33Kv Gamesa panther line

Bund clearing required in PSS boundary


12 No of 11Kv line
28 No of LT line
Total 13 No of service wire
crossings in 5 No of Scada and cable crossing

entire route
The fore mentioned crossing requires heightening
or LC during material movement.
Final suggestion,
On considering the obstacles present in O.Saravanapuram it is
recommended to bypass village.