Transmission Circle Bhagalpur

(Progress Report)

Sl No. Name of the Project Scheme/Plan NIT
No.
Status of work Working
Agency
Work Incharge
1 132 KV D/C Kahalgaon-
Sultanganj
RSVY Foundation- 222 no completed
Stringing -31 Km completed out of 66.48
Km.
Erection-198 completed
PGCIL AEE PGCIL
2 132 KV D/C Sultanganj-
Lakhisarai
RSVY Foundation- 251 completed,Left-21
Stringing -0.450Km
Erection-73 completed,Left-199
PGCIL AEE PGCIL
3 132 KV D/C Banka(PG)-
Sultanganj
SP Plan Foundation completed-2 nos
Left-174
Ramchandar
Rao
AEE Banka
Sri Vijay Kumar
4 132 KV Line bay extension
work at Sultanganj
SP Plan/RSVY 4 nos way completed by PGCIL at G|S|S
STG
PGCIL AEE PGCIL