Slope stability is important in the design and construction of the earth dams
Some factors affect on the slope stability for the earth dams such as change
Any dam failure or accident to dam can cause a potential hazard to property
and lives of millions of people who dwell downstream of the dam and also
live stock.
OBJECTIVE
Analysis Type
Settings
Slip Surface
Distribution
Advanced
STEP 3: SKETCH AXES
Sketches scaled reference axes around a section of the drawing
STEP 4:SKETCH LINES
Sketch lines on the drawing
STEP 5: DRAW REGIONS
Defines geometric regions
STEP 6: DEFINE MATERIALS TO THE REGIONS
In this study, Analysing the slope stability of wand dam at different levels of water which is located in
Dayala Governorate.
This analysis can be done in different methods and the results are given below.
The soil properties o f the dam is given below:
o Unit weight=21 KN/m^2
o Cohesion=0 kpa
o Internal friction angle(phi)=39 degrees
The relationship between the minimum (F) and water level(m) is given below.
• M1=MORGENSTERN-PRICE
• M2=SPENCER
• M3=BISHOP
• M4=JANBU
• M5=ORDINARY
My analysis using GEO-SLOPE MODEL
A.MORGENSTERN-PRICE B.SPENCER
C.BISHOP D.JANBU
E.ORDINARY
The relationship between the minimum (F) and water level(m) is given below.
• M1=MORGENSTERN-PRICE
• M2=SPENCER
• M3=BISHOP
• M4=JANBU
• M5=ORDINARY
Water JOURNAL MY JOURNAL MY JOURNAL MY JOURNAL MY JOURNAL MY
level(m) VALUES( VALUES( VALUES( VALUES( VALUES( VALUES( VALUES( VALUES( VALUES( VALUES(
M1) M1) M2) M2) M3) M3) M4) M4) M5) M5)
0(dry) 2.029 2.029 2.028 2.029 2.030 2.027 2.027 2.027 2.027 2.027
5 2.014 2.022 2.014 2.022 2.016 2.022 1.960 2.011 1.949 2.006
10 1.977 1.982 1.976 1.981 1.974 1.980 1.918 1.926 1.901 1.906
15 2.009 1.991 2.008 1.991 2.012 1.931 1.962 1.931 1.982 1.936
19 2.025 2.017 2.029 2.017 2.030 2.017 2.027 2.015 2.061 2.146
• The relationship between the minimum (F) and water level(m).It can be seen that the values of
(F) are decreased between (h=0 to 10 m) because the value of soil cohesion equal 0.
• This leads to increasing the pore water pressure inside the dam body, as a result of that the
resisting force decrease, which leads to decrease the values of factor of safety.
• While the values of factor of safety becomes increase when the water level(h) greater than
(10m) due to increase the water forces supported the upstream slope face that decreasing the
driving forces.
LITERATURE REVIEW
S.NO AUTHOR NAME TITLE OF JOURNAL JOURNAL NAME MAJOR FINDINGS
1 Thair J M Evaluation of the upstream Materials Science Analysing Slope stability and
Alfatlawi1,Yahyea K. Al- slope stability of and Engineering Seepage of the dam at
temimi1, Zeena M. earthdams based on upstream side containing
Alomari drawdown conditions - different heads by using
Khassa different Analysis .
Chai Dam: a case study Sudden draw-down of water
level leads to failure in slope
structure of dam
2 Jasim M Abbas , Zainab SLOPE STABILITY ANALYSIS Journal of Analysing slope stability of
Ali Mutiny FOR EARTH DAMS USING Engineering earthen dams by using
(GEO-SLOPE/W) Sciences SLOPE/W analysis containing
different Heads .
Comparing the analysis at
different condtions and at
different heads to finding the
factor of safety.
S.NO AUTHOR NAME TITLE OF JOURNAL JOURNAL NAME MAJOR FINDINGS
3 Mohammed K. Slope Stability Analysis Engineering and Different materials causes
Malik, Ibtisam R. of Haditha Dam after Technology Journal unstability of dam like Dolomite
Karim Earthquakeusing Geo- and Formation of Gypsum in the
Studio Software foundation.
Analysing of slope stability and
seepage of water with different
materials present in the dam by
using different analysis.
4 Usama R. Mishal, Stability Analysis of an Engineering and It is possible to create new
Thair Sh. Khayyun Earth Dam Using Technology Journal methods of calculating the factor
GEOSLOPE Model safety against sliding by adding
under Different Soil more variables to the commonly
Conditions used limit equilibrium method.
PROJECT TIMELINE
11-11-2023 22-11-2023 11-12-2023 20-12-2023
to to to to
21-11-2023 10-12-2023 19-12-2023 25-12-2023
Collection of data
from the sources
Investigating the
data by using GEO-
SLOPE model
Analysing the
results
Preparation of
Thesis
THANK YOU