Proposal
EFERT Manufacturing Division
I&E Department
Engro Fertilizer, Daharki
Aug 2023
www.engro.com
MG-SET Reliability Proposal - EFERT Manufacturing Division
MG-SET – Overview
MG-Set is the backbone of the Ammonia-II plant since all power to this unit is being supplied through MG-Set.
The Ammonia-II plant was relocated from USA in 1992 and is rated at 60 Hz. The purpose of the MG-Set is to generate
2.4kV, 60 Hz power to meet the requirements of the Ammonia-II plant.
Make Brush
A detailed preventive maintenance regime exists for MG-SET to ensure its reliable operation which is covered through below PMs:
Control & Excitation Panel Servicing 2 years Major Inspection 2022 – Supported by ENG1
Team*
Power Cable Testing 4 years
*OEM- Brush Electric refused to provide engineering services for MG-
MG-SET Life Assessment Testing SET Major inspection but ENG1 team supported well throughout the
4 years
engineering & services process. All future correspondence regarding
Major Inspection spares & engineering services will be done with ENG1 team as they have
10 years (However, MI done after
30 years in LTR’22)
all the required dimensions & data for this critical machine
Interventions – Upgradation & Replacement Projects
www.engro.com 4
MG-SET Reliability Proposal - EFERT Manufacturing Division
Preventive
Maintenance Rotor Poles (Motor & Main Stator Coils
Oil Cooler / Pump
Generator) (Motor & Generator)
Intervention
Required*
www.engro.com 6
MG-SET Reliability Proposal - EFERT Manufacturing Division
Proposal-1
1 Unavailability of spares & rely on existing PM regimes & planned Major inspection. -
Retain current philosophy
- Procurement of 2 spare Stator Coil sets & plan complete replacement of 3 set
of stator coils for both Motor & Generator as recommended by ENG1. (1 Set of
Stator coil is available) – Replacement plan 5 years
Proposal-2
2 Spares Procurement & Vulnerable - Procurement of 2EA Rotor poles for both Motor & Generator as spares.- 50*
parts Replacement Replacement plan in next Health Assessment
*Budgetary Quotes are still awaited from ENG1 as they were not providing quotes due to long pending payments issue. (LC issue)
However, we expect to receive the quotes soon as the payments have been released now.
www.engro.com 7
Thank You!