CHRONOLOGY

 DPR clearance from CEA on 19.09.2002


 Cost as per DPR = Rs. 431.56 Cr.
 Completion of main components:

Name of Package Date of Award Completion Remarks


Storage Reservoir 13.06.2007 July 2013
Head Race Tunnel 02.04.2003 September 2018 Work rescinded
(HRT) twice
Surge Shaft 18.05.2009 January 2012
Penstock 27.05.2005 December 2014
Power House (E&M) 15.02.2007 June 2017

 BVPCL constituted a Panel of Experts (PoE) on 22.10.2016 to


Review/Validate the usage of SAILMA-550-HI Steel in penstock through an
independent expert technical committee.
 Leakage observed at Anchor Block-10(AB-10) during Hydro fill Test.
 Repair of AB-10 recommended & carried out in the presence of PoE from
July 2018 to February 2020.