INTERFACE MANAGEMENT SKILLS

FOR COMPLEX PROJECTS

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore

SALEH KAFAMI – SKTEC CONSULTING


DISCLAIMER:

This presentation is based on my views


and experiences and does not represent
the view of any companies.

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
PRESENTATION CONTENT:
• Introduction
• Objective
• Risks associated with Modular Prefabrication
• Interface Management Skills
• Interface management Master Plan
• Communications
• Planning & Integrated project schedule
3

• A Risk Mitigation Method PPRR


• Conclusion Pre-Fabrication & Modular Construction ASIA Summit 2014
21-24 Jan Furama Riverfront, Singapore
OBJECTIVE

The objective of this presentation is:


Collaboration : role of Interface management
Finding the
All people & parties who are involved
methods as a in the
delivery of a project are the drivers of a SAME
Collaboration to:
BOAT with different responsibilities and tasks to
get to Minimize
the samethe destination with the
RISKS associated best
with delivery of
Complex benefits;
manner to achieve Projects and
noPrefabrication
matter which and
position they are. Modular Constructions
4

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
MODULAR PRE-FABRICATED PACKAGES

Modular Fabrication ’ s Factors and selection


A Large Scale
Scope definition of each Modules
International Project
Interfaces identification for each sub project
Interface management for safe delivery
Risk mitigation on interface management
 Interface management team and organization
Sub Projects,
 Planning and scheduling
Modular Fabricated
Packages and multi national
 Communication and meeting
collaboration is a NEED for Large 5
 Continuous progress monitoring & control
Scale Projects
 Recovering
Pre-Fabrication & Modular Construction ASIA Summit 2014
21-24 Jan Furama Riverfront, Singapore
Any mismatches in the
What is a major cause of
project interfaces cause big
projects cost over run and
delay on project delivery and
schedule delay?
excessive re-works.
6

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
MODULAR PRE-FABRICATED PACKAGES

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
MODULAR PRE-FABRICATED PACKAGES

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
PROJECTS INTERFACES

Interfaces
Iceberg

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
A PROJECT INTERNAL Interfaces
MODEL Upstream
Offshore
Jackets
A Topsides & Flares
Conventional
LNG Subsea Pipelines
Project LNG Processing &
Onshore
Condensate
Utilities
EXTERNAL
Interfaces Operating Base 10

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
INTERFACES IN PROJECT PHASES
Iterfaces

• Jacket (Design Contractor)


Engineering • Topside (Engineering Contractor)
• Pipeline (Design Contactor)

• EPC’s procurement Team


Procurement • Several Suppliers

Fabrication : • EPC Construction team


• Jacket Fabrication Contactor
• Topside Fabrication and several
modules fabricators
• Pipe coating fabricators

• Jacket installation parties 11

Installation • Topside installation contractors


• Pipe and cable laying companies

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
RISKS ASSOCIATED WITH MODULAR PRE-
FABRICATED PACKAGES

 Scope
 Schedule
 Cost
 Quality INTERFACE
 MANAGEMENT
Technical and tactical Changes
 Mismatching interfaces
 Unfinished works
 Logistics and transportation
 Testing and commissioning 12

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
RISK MANAGEMENT

Interface management is:

Project Risk
Mitigation

13

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
PROJECT STAKEHOLDERS

Government / Community
Interface management
Stakeholders Diversity Factors
Project Owner
Operating Company Project Management
Custom and Team
Geographical Standards Attitude and
cultural and
Locations and rules approaches
Offshore management Team
languages
Onshore Project management
Team

Exploratio 14
Jacket Topsides Pipe line
n and Flare and
Process Utility Operating Base
Drilling EPC Bridges EPC EPC System EPC System EPC EPC
EPC
Pre-Fabrication & Modular Construction ASIA Summit 2014
21-24 Jan Furama Riverfront, Singapore
RISK MITIGATION ON INTERFACE MANAGEMENT
MAIN STEPS

 Developing Interface management Master


Plan
 Communication
 Integrating the interface management and
project scheduling
15

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
INTERFACE MANAGEMENT MASTER PLAN
(IMMP)
IMMP is a master plan to Identify:
 The project Stakeholders
 The external & internal interfaces
 The interface owners
 The owners relations
 The actions / Scopes
 Technical change management method
 The action timing
 Major interface milestones 16

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
PROJECT INTERFACE MASTER PLAN
(IMMP)

Interface management master plan


Rules and Governance
Government / Project Owner Contractors Suppliers /
Community • Business plans • Scopes Fabricators
• Rules and • Standards • Interfaces
standards • Scopes
• Cost • Sites
• Limits • Boundaries
• Schedule • Subcontractors
• Local • Interfaces
• Qualities facilities
requirements • Schedule • Delivery points
• Cost • Transportation
• Etc
17

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
PROJECT INTERFACE MANAGEMENT MASTER
PLAN PURPOSES

1. Rules of engagement

2. Gain Alignment

3. Mitigate interface related risks

18

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
INTERFACE MASTER PLAN AS A TOOL

19

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
IMMP AS A INTERFACE MANAGEMENT TOOL

 Interface concept alignment

 Alignment methods

20

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
PROJECT INTERFACE MANAGEMENT
MASTER PLAN OWNERS & USERS
IMP Owners
 Project interface manager (Main contributor)
 Project manager (supervising)
 Scope manager (contributing and assisting)
 Engineering Manager (assisting)
 Interface coordinators (input)

IMP Users
21
 All parties involved

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
INTERFACE MANAGEMENT ORGANISATION

Upstream EPC interface coordinator


Upstream EPC Jacket EPC Topside EPC Pipeline EPC
interface interface interface interface
coordinator coordinator coordinator coordinator
Offshore Jacket EPC interface coordinator
interface
Drilling manager Engineering Engineering Engineering
interface interface interface interface
Coordinator Coordinator
Topside EPC interface coordinator
Coordinator Coordinator

Survey
Project Fabrication Fabrication
Pipeline Pipe laying
EPC interface coordinator
interface
interface interface interface interface
Coordinator Coordinator Coordinator Coordinator
manager
Process plant EPC interface coordinator
Reservoir Transportation Transportation
Riser interface
interface interface interface
Coordinator
Coordinator OnshoreCoordinator Coordinator
interface Utilities EPC interface coordinator
manager
Installation Installation 22
Cable laying
interface interface interface
Coordinator Operating Base
Coordinator EPC interface coordinator
Coordinator

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
SOME TIPS ABOUT THE IMMP

 IMP should be provided within base line


project docs such as PEP, PMP …

 Interface management requirements shall


be sufficiently defined in project contracts.

 IMP shall be prepared in early stage of the


project detail engineering (a draft is good
to be provided during FEED) 23

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
COMMUNICATION

How? What ? When? Whom?


 Right information in the right format and right time to
the right people

• Right information
• Right time
• Right format
24

To the right people


Pre-Fabrication & Modular Construction ASIA Summit 2014
21-24 Jan Furama Riverfront, Singapore
COMMUNICATION TOOLS

 Information Exchange Forms

 Interface Point Form

 Interface Agreement Form


25

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
COMMUNICATION FORM DESIGN

1- Work Flow

2. Tools

26

3. People
Pre-Fabrication & Modular Construction ASIA Summit 2014
21-24 Jan Furama Riverfront, Singapore
SCHEDULE INTEGRATION
Project
EPC3 Cont
Owner
Schedule
EPC2 Cont Schedule
Schedule EPC4
Cont
Schedule

Project EPC5
EPC1 Cont Integrated Cont.
Schedule Schedule Schedule 27

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
SCHEDULE CONTENTS

Project Integrated Schedule Should include:

 High Risk Milestones


 External Interface Milestones
 The Critical Path based on interface Milestones

Contractors Schedules Should include:

 External and internal interface milestones


 Critical path considering the high risk external interfaces 28

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
INTEGRATED SCHEDULE SOLUTION

 A common Interface Management solution

 High Risk Interface Points

 The Interface Breakdown Structure (IBS)


 Integrate IBS into P6
 Interdependency between interface points /
agreement and other project activities
29
 Tracking Interface Progress (All Stakeholders)

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
INTEGRATING INTERFACE SCHEDULE

Integrated Schedule Impacts


Project Integrated Schedule Reports

These reports should be provided by


project planning team to be reviewed
in project interface meeting

30

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
PROJECT INTEGRATED SCHEDULE REPORTS

 Progress discrepancy report


 Project progress exception report
 Project schedule recovery report
 Critical path status
 Interfaces status
 Schedule floating status

These reports should be provided by project


planning team to be reviewed in project
interface meetings 31
PPRR Risk management model

Prevention
Preparing a risk management plan
•Prevention
Preparedness • Preparedness
Conduction a business impact analysis
Response
P P
Preparing an incident response plan
Recovery
R
Developing a recovery plan
R
• Response • Recovery
32

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
PPRR Risk management model

P:Take actions to reduce or eliminate the


likelihood or effects of an incident
P:Take steps before an incident to ensure
effective response and recovery
R: Contain, control or minimise the
impacts of an incident
R: Take steps to minimise disruption and
recovery times
33

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
Bow- Tie Method

34

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
BOW- TIE METHOD FOR INTERFACE RISKS
Prevention Response

Reco sources
Sche Project

very dule
tion
er Co tion &
Mast terface

Reco ce Points
Plan

Plan
rdina

PROJECT
n

INTERFACE

very

he
PROJECT
d ul e
er Pla

ct Re
ica

ct Sc
RISK EFFECTS
o

rated

Delay and
c t In

very
mun

MITIGATION High Cost RECOVERY

fa
Reco
Proje

Proje
ehold

Inter
Proje

Integ
Co m
Stak

35

Recovery
Preparedness Pre-Fabrication & Modular Construction ASIA Summit 2014
21-24 Jan Furama Riverfront, Singapore
CONCLUSIONS

 Modular Prefabrication is a proven alternative


methodology to traditional construction method,
delivered to the site complete with expected
standards to suit the project’s requirements.

 Modules can be fully fitted out, including


prefabricated structure, installed equipment,
mechanical services, piping, electrical,
instrumentation with all wiring, lighting, safety and 36

control system
Pre-Fabrication & Modular Construction ASIA Summit 2014
21-24 Jan Furama Riverfront, Singapore
CONCLUSIONS

 EPC Projects, Modular Packaging and multi national


collaboration is a NEED for Large Scale Projects.
 Depending on the projects nature each EPC project could
be implemented in different place by a qualified proven
skilled project team under an integrated project
management system.
 Several EPC projects put a large scale project in jeopardy of
mismatching and conflicts in result.
 Any Large scale Project needs a proper interface 37

management Team

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
CONCLUSIONS

 All parties should be engaged in the interface


management
 Master Interface Plan is a Tool to mitigate the Risks
 Proper Communication is a must for Risk mitigation
 An integrated Master schedule is an abstract What
has to deliver When?

38

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore
QUESTIONS?

?
?
?
Pre-Fabrication & Modular Construction ASIA Summit 2014
39

21-24 Jan Furama Riverfront, Singapore


INTERFACE MANAGEMENT SKILLS
FOR COMPLEX PROJECTS

Pre-Fabrication & Modular Construction ASIA Summit 2014


21-24 Jan Furama Riverfront, Singapore

SALEH KAFAMI – SKTEC CONSULTING