Offshore Drilling
Lesson 3
Wellheads and Casing
1
Wellheads and Casing
2
Conventional Riser Drilling
FLOATER
SEA WATER
DRILLING RISER
HYDROSTATIC
CHOKE LINE
MUD HYDROSTATIC
BOP
DEPTH
SEAFLOOR
PRESSURE 3
Conventional Riser Drilling
- Install 30-in Conductor -
FLOATER
DRILLPIPE
~200 30”
DRILLING RISER
CHOKE LINE
D 30”
~1,050
20”
Drill 26-in hole to 1,050 ft below mudline
Riser optional - Mud returns to surface or
seafloor
Run 20-in Conductor to ~ 1,000 ft below mudline
Cement to mudline 5
Conventional Riser Drilling
- Install 13 3/8-in Surface Csg.
FLOATER
DRILLING RISER
CHOKE LINE
BOP
8
Wellheads and Casing
9
Wellheads and Casing
10
Wellheads and Casing
11
Fig.4-10.
Typical
sealing
arrangement
for subsea
wells.
12
13
Depth BML
240 ft
1,100 ft
4,100 ft
8,600 ft
10,100 ft
14
15
Permanent
Guide
Structure.
Temporary
Guide Base
16
17
Utility
Guide Frame
Hole Opener
Temporary
Guide Base
18
Procedure for Starting a Well
25
Gas in the
Water Column
g f = (g ob − g p )Fσ + g p
29
g f = (g ob − g p )Fσ + g p
Where:
30
For offshore drilling:
1
g ob = [ 0.44 d + 0.4335 ρp f f(d KB − d − d F )]
d KB
Where:
d KB = depth measured from the kelly bushing, ft
d = water depth, ft
d F = height of flowline above the water, ft
3
ρ f = formation bulk density, g/cm
31
1
g ob = [ 0.44 d + 0.4335 ρp f f(d KB − d − d F )]
d KB
32
Get ρ f from
density log.
Get Fσ from
this plot.
Get gp
Calculate gf
38
Fig. 4-8. Plot of a leak-off test.
39
Fracture Gradient Calculation
BOPs
Casing
Drillpipe
41
Fig. 4-9.
Sub-sea
cementing
system.
42
Fig.4-10.
Typical
sealing
arrangement
for subsea
wells.
43
Metal-to-Metal Casing Annulus Seal
Upper Metal
Seal Lips
Resilient
Compression
Element
Lower Metal
Seal Lips
45
Casing Hanger and Pack-off
Assembly
48
Seal Test - Example
V = 11 bbl
4,000 ft
50
With no leak, the system will require
51
Obviously, 0.1 bbl would be difficult to
measure. The annular volume between the
seal and the cement is
(996 - 500) ft * 0.1815 bbl/ft = 90 bbl of
mud
Now,
?
∆ V = 6*10 * 90 ∆ P + 3*10 * 11 ∆ P bbl
-6 -6
53
54
Plug for
testing
casing seal
to full
working
pressure.
55
Test Procedure
1. Set seal
2. Land test plug in wellhead,
sealing off below the seal
3. Displace mud with water for test
4. Close pipe rams
5. Pump slowly down the choke line,
preferably in stages, to protect the
casing in case of leaks
56
Test Evaluation
58
Test Evaluation, cont.
59
Drilling Procedures
from a floater
etc.
60
Drilling Procedures
Tentative Hole and Casing Sizes
61
Drilling Procedures
Tentative Hole and Casing Sizes
62
General Rules
67
General Rules
68
General Rules
Anchoring
69
General Rules
Anchoring
71
72
Shallow Gas Plan
73
Shallow Gas Plan
74
Shallow Gas Plan
75
36” Hole Plan
76
36” Hole Plan
77
36” Hole Plan
79
36” Hole Plan
80
36” Hole Plan
82
36” Hole Plan
85
26” Hole Plan
86
26” Hole Plan
87
26” Hole Plan
88
26” Hole Plan
89
26” Hole Plan
91
26” Hole Plan
95
26” Hole Plan
97
26” Hole Plan
100
101
102