Task Name

WHRU Overall

Duration

Start

Finish

Predecessors
Resource
Names

720 hrs

Sat 26/11/11 8:00

Mon 26/12/11 8:00

Scraffolding outside of WHRU at cover of coil 1,2,3

48 hrs

Sat 26/11/11 8:00

Mon 28/11/11 8:00

WTH

Stop WHRU F-001 burner and close guillotine (oil still circulate)

16 hrs

Mon 28/11/11 16:00

Tue 29/11/11 8:00 2

PTT

Open Cover coil 1,2,3 (oil still circulate) opposite manifold side

8 hrs

Tue 29/11/11 8:00

Tue 29/11/11 16:00 3

CKC

Open Man Hole

4 hrs

Tue 29/11/11 8:00

Tue 29/11/11 12:00 3

CKC

Blind Fuel , N2 , Amonia

4 hrs

Tue 29/11/11 8:00

Tue 29/11/11 12:00 3

TEI

Thermal Scan Internal

2 hrs

Tue 29/11/11 12:00

Tue 29/11/11 14:00 5,6

Thermoscan return bend by Inspection (oil still circulate)

2 hrs

Tue 29/11/11 16:00

Tue 29/11/11 18:00 4

PTT
PTT

Isolate+ Vent+ Drain

48 hrs

Tue 29/11/11 18:00

Thu 1/12/11 18:00 8

10

Blind

12 hrs

Thu 1/12/11 18:00

Fri 2/12/11 6:00 9

TEI

11

Cold cut tube at lowest row of coil 1 (only 1 side) 18x2=32 joint

36 hrs

Fri 2/12/11 6:00

Sat 3/12/11 18:00 10

CKC

12

Cold cut tube at lowest row of coil 3 (only 1 side) 18x2=32 joint

36 hrs

Sat 3/12/11 18:00

Mon 5/12/11 6:00 11

CKC

13

Cleaning by high pressure water with BJV nozzle

48 hrs

Mon 5/12/11 6:00

Wed 7/12/11 6:00 12

TEI

14

Dry and Clean Internal Tube

24 hrs

Wed 7/12/11 6:00

Thu 8/12/11 6:00 13

TEI

15

Inspection after cleaning

24 hrs

Thu 8/12/11 6:00

Fri 9/12/11 6:00 14

PTT

16

Taper and PT check crack at before fit up (take photo for evidence)

24 hrs

Fri 9/12/11 6:00

Sat 10/12/11 6:00 15

CKC

17

Welding ; PT root and cover by contactor (take photo for evidence)

84 hrs

Sat 10/12/11 6:00

Tue 13/12/11 18:00 16

CKC

18

RT

84 hrs

Tue 13/12/11 18:00

Sat 17/12/11 6:00 17

CKC

19

Fill oil

72 hrs

Sat 17/12/11 6:00

Tue 20/12/11 6:00 18

TEI

20

Pressure test

8 hrs

Tue 20/12/11 6:00

Tue 20/12/11 14:00 19

TEI

21

Drain

48 hrs

Tue 20/12/11 14:00

Thu 22/12/11 14:00 20

TEI

22

Remove Blind

12 hrs

Thu 22/12/11 14:00

Fri 23/12/11 2:00 21

TEI

23

Tap hot oil from header make up temp. for thermoscan

6 hrs

Fri 23/12/11 2:00

Fri 23/12/11 8:00 22

PTT

24

Close cover

24 hrs

Fri 23/12/11 8:00

Sat 24/12/11 8:00 23

CKC

Project: 2000_WHRU ESP v2003 rev 0


Date: Tue 29/11/11 17:20

Critical

Baseline Milestone

Split

Critical Split

Milestone

Task Progress

Critical Progress

Summary Progress

Baseline

Task

Summary

Baseline Split

Split

Project Summary

Baseline Milestone

Task Progress

Critical Split

Milestone

Baseline

Critical Progress

Summary Progress

Baseline Split

Task

Summary
Page 1