SESA GOA LTD.

SHUTDOWN PLANNING BF/ SP

PLAN/INST/08

FOLLOWING ACTIVITES ARE PLANNED FOR THE SHUTDOWN OF BF/SP ON DATE 18/01/1014 SR NO DESCRIPTION OF THE PLANNED ACTIVITY SGL PERSON RESPONSIBLE MCK ENG TECH DEPT. RESPONSIBLE PLANNED TIME(HRS ) ACTUAL TIME(HRS) STATUS

1 2 3 4 5 6 7
SR NO

HEAD ESP OIL PRESSURE PT CALIBRATION MAIN SINTER UPS SERVICING LEVEL SWITCH INSTALLATION IN FUEL&FLUX PROPORTIONING REDUNDANT POWER SUPPLY TO BE TAKEN INLINE LEVEL SWITCH CHECKING IN PROPORTIONING LEVEL SWITCH CHECKING IN SCREENING DD

SHRIPAD DESAI

ANIKET ANIKET MAYANK ANUP SANJAY ANIKET

RAJESH SHEKHAR RAJESH GOPI SHEKHAR SHEKHAR

INST INST INST/MECH INST INST INST

1.50 2.00 2.00 2.00 1.00 1.00

DESCRIPTION OF THE MANDATORY ACTIVITY SGL

ENGG. RESP MCK ENG TECH

DEPT. RESPONSIBLE

PLANNED TIME(HRS )

ACTUAL TIME(HRS)

STATUS

1 2 3 4 5 6 7

MAIN EXHAUST FAN MONTHLY CHECKLIST BF GAS FLOW ELEMENT CLEANING&CALIBRATION CA FLOW ELEMENT CLEANING&CALIBRATION WEIGH FEEDER #1 CALIBRATION H1,H2 WEIGH SCALE VERIFICATION P7 &C3 WEIGH SCALE VERIFICATION WB INDICATOR CHECKING& ZERO CALIBRATION

SHRIPAD DESAI

ANIKET ANUP ANUP MAYANK MAYANK/SANJAY ANUP/ANIKET SANJAY

SHEKHAR GOPI GOPI RAJESH RAJESH GOPI SHEKHAR

INST INST INST INST/MECH INST INST INST

1.00 2.00 2.00 3.00 4.00 4.00 2.00

SHUT DOWN NOTICE


THERE WILL BE A SHUTDOWN FOR BLAST FURNACE/ SINTER PLANT ON DATE 18/01/2014 .ALL PERSONNEL WILL HAVE TO REPORT FOR DUTY AS PER THE TIMINGS GIVEN BELOW.

SR.
1 2 3 4 5 6 7

PERSONNEL NAME
ANIKET ANUP PARAB MAYANK GOPI RAJESH SHEKHAR SANJAY SGL INSTRUMENTATION

DUTY TIME
8.00AM 8.00AM 8.00AM 8.00AM 8.00AM 8.00AM 8.00AM