(Douglas Guibunda) Weekly Status Report For week ending 10/11/2013

Carry Over From Week 04 November 2013 10 November 2013 Tasks


Recovery data email and creating new mails accounts from all Users at DPWorld Maputo Support all email issues of all departments and other issues systems

Planned Dates
02.09.13

Actual Dates

Comments

Until end

Almost done (98%)

04.11.13

08.11.13

successfully

Support All users regarding 04.11.13 IT systems


08.11.13

08.11.13

successfully

Check issues clean Room Data Center

08.11.13 Until end

successfully Successfully 12%

Creation news profiles and installation 02.11.13 new softwares for New PC Desktop Core I5 regarding Zodiac migration.

This Week Recovery data emails from all users and creating new mails box

Support All users regarding IT systems

Support all emails issues


Check issues clean Room Data Center Creation news profiles and installation new softwares for New PC Desktop Core I5 regarding Zodiac migration

SUPPORT DPWORLD MAPUTO issue reported and solved

Gate Out/IN ( nothing to report all running normally) Planning (all running normally) Maintenance (all running normally) Accounting (mails box issues solved and support and all running normally) Satellite (nothing to report all running normally) HSSE (all running normally) Operations (all running normally) Laydown (problems of network connection, we are working to fix the issues)

Planned for next week Monitoring All activity of networks through solo winds SMS gateway (Project) Monitoring All activity of networks through solo winds Check Up the all Systems all department regarding Information Tecnology Support all Users