This document provides instructions for scheduling a background MRP run job for plant 1011 using transaction code MDBT. It involves creating a variant called mrp_1011, entering plant code and other settings, and saving the variant. The second part involves scheduling the variant wk-37 as a background job. The last part provides steps to evaluate the MRP run results using transaction code MD07 and firming planned order proposals.
This document provides instructions for scheduling a background MRP run job for plant 1011 using transaction code MDBT. It involves creating a variant called mrp_1011, entering plant code and other settings, and saving the variant. The second part involves scheduling the variant wk-37 as a background job. The last part provides steps to evaluate the MRP run results using transaction code MD07 and firming planned order proposals.
This document provides instructions for scheduling a background MRP run job for plant 1011 using transaction code MDBT. It involves creating a variant called mrp_1011, entering plant code and other settings, and saving the variant. The second part involves scheduling the variant wk-37 as a background job. The last part provides steps to evaluate the MRP run results using transaction code MD07 and firming planned order proposals.
CREATE BACK GROUND JOB TO BE SCHEDULED FOR MRP RUN FOR PLANT 1011
TRANSACTION CODE MDBT
1.Select the variant button
1. Create variant =mrp_1011
2. Press enter
1. Enter plant code as 1011
2. Processing key as =NETCH 3. Create purchase req=1 4. Scheduling lines=3 5. Create MRP List =1 6. Planning mode=1 7. Scheduling=1 8. Click the box for Display material list 9. Click attribute in the top left corner or press F6 10.Meaning =MRP run for 1011 11.Finally Save
1.result is variant saved as wk-37
Schedule Back ground job vaiant MRP_1011 for MRP Run
Transaction Code MDBT
1.Select the variant and click button
1. Press schedule once
schedule
2. Click back button Twice
3.
1.Result =request with variant wk-37 is scheduled
1. Select the variant and press the button Display scheduling
2. From the available list select the variant and press the button Results
3. You can see the results at the BOTTOM SCREEN.
4.
Evaluate MRP run T.Code MD07
1. Se4lect the plant code as 1011 2. Select the MRP Controller 3. Press enter 4. Select Yes to Prepare the List 5. Select the material of attention and press F5 to view further details 6. From detailed screen per material ceated thru MRP List and Press F8 to under go change mode 7. Select the check box planned order for Firming the Proposal 8. Firm order will be displayed with asterik mark in the stock requirement list 9. This is to be repeated for other material also.
1. Double click against the so that material so
that pop screen will appear
2.Press F8 to go under change
mode
2.Tich the check box Plad order to firm the the proposal
3. You can see asterik mark against the proposal which are having astrik mark