American Constructors Case Study
American Constructors Case Study
As the construction of WOC was one of the major assignment of ACI, the
main problem faced by it was the completion of project in time.
Although the team had been working on the World Outreach Church
project for over a year and it was nearing completion, the project deadline
was preponed.
The project was originally scheduled for completion by March 2010 but
the client desired to get it done by Thanksgiving holiday, November
26,2009.
Tom Grott, the project manager for ACI recognised the impossibility of the
project and compromised by addition of few additional weeks to the
clients desired date and finally the completion date was pushed to
December 14, 2009 before Christmas season..
As the impeding deadline was creating significant tension on the site, the
project manager of ACI, with his team evaluated the progress of their
building expansion project on September 24 ,2009.
Oppurtunity