ELEMENT COST ANALYSIS - Form 1

JOB TITLE :

CLIENT

LOCATION :

TENDER DATE :

INFORMATION TOTAL PROJECT


Project and Contract Information
Project Details and Site Condition :

Contract :

Market Conditions :
Contract Particulars :

Cost Fluctuation :

Type of Contract :

Government

Competitive Tender List


RM

Basis of tender
Bills of Quantities

Open/Selected
Competition

Private

Bills of Appr. Quantities

Negotiated

Provisional Sum

RM

Shc. of Rates/
Spec. & Drawings

Serials

Prime Cost Sum

RM

Contract Period Stipulate By Client

Preliminaries

RM

Contract Period Stipulate By Builders

Contingencies

RM

Number of Tender Issued

Contract Sum

RM

Number of Tender Received

Int/Jv/L

ANALYSIS OF SINGLE BUILDING


Design/Shape Information
Accommodation and Design Features :

Areas :

Functional Unit :
0.00 m2

Lower Ground Floor


Ground Floor
Upper Floor

m2
m2
\ m2

GROSS FLOOR AREA

External Wall Area


Gross Floor Area

Design/Shapes
Percentage of Gross Floor Area
m2 (a) Below Grd. Flr.
m2

m2

(b) Single Storey


Construction

(c) Two-Storey
Construction

m (d) 3-Storey
Construction
m
(e) 4-Storey
\m
Construction

=
Usable Area
Circulation Area
Ancillary Area
Internal Division

m2
m2
m2
m2

GROSS FLOOR AREA

m2

Av. Below Grd. Floor

Floor Space NOT Enclosed

m2

At Ground Floor

Roof Area

m2

Above Ground Floor

Storey Heights :

(Measured Flat On Plan)


Brief Cost Information
Contract Sums
Provisional Sums
Prime Cost Sums
Preliminaries
Contingencies

RM
RM
RM
RM
RM

Contract Sums less Contingencies

Functional Unit Cost But


Excluding External WorksRM
being
being
RM

of Remainder of Contract Sum


of Remainder of Contract Sum

/m2

INSTITUTION OF SURVEYORS MALAYSIA


BUILDING COST INFORMATION CENTRE
ELEMENT COST ANALYSIS - Form 2

SUMMARY OF ELEMENT COSTS


GROSS FLOOR AREA :

M2

Total Cost of Cost per m2


Element
GFA
RM
RM

TENDER DATE :
Preliminaries Shown Separately
Element
Element
Element
Reinforced
Unit
Unit
Rate
Ratio
Concrete
Quantity
RM
per m2 GFA
m3

Reinforcement

Formwork

kg

m2

P.C.Sum
Allowed

Tendered
Sum

1 Substructure
1A Piling
1B Work Below Lowest Floor Finish
2
2A
2B
2C
2D
2E
2F
2G
2H

Group Element Total


Superstructure
Frame
Upper Floor
Roof
Stairs
External Walls
Windows & External Doors
Internal Walls & Partition
Internal Doors
Group Element Total

3
3A
3B
3C
3D

Finishes
Internal Wall Finishes
Internal Floor Finishes
Internal Ceiling Finishes
External Finishes
Group Element Total

Fittings and Furnishings

5
5A
5B
5C
5D
5E
5F
5G
5H
5J

Services
Sanitary Appliances
Plumbing Installation
Refuse Disposal
Air-conditioning & Ventilation System
Electrical & Telephone Installation
Fire Protection Installation
Lift & Conveyor Installation
Communication Installation
Special Installation

5K Builder's Profit & Attendance on Services


5L

Builder's Work in Connection With


Services
Group Element Total

Sub-total excl. External Works,


Preliminaries and Contingencies
6
6A
6B
6C
6D
6E

External Works
Site Work
Drainage
External Services
Ancillary Buildings
Recreational Facilities
Group Element Total

Preliminaries
Total Excluding Contingencies

INSTITUTION OF SURVEYORS MALAYSIA


BUILDING COST INFORMATION CENTRE
ELEMENT COST ANALYSIS - Form 3

BRIEF SPECIFICATION
GROSS FLOOR AREA :
ELEMENT
1 Substructure
1A Piling
1B Work Below Lowest Floor Finish
2 Superstructure
2A Frame
2B Upper Floor
2C Roof
2D Staircase
2E External Walls
2F Windows & External Doors
2G Internal Walls & Partition
2H Internal Doors
3

Finishes

3A Internal Wall Finishes


3B Internal Floor Finishes
3C Internal Ceiling Finishes
3D External Finishes
4

Fittings and Furnishings

Services

5A Sanitary Appliance
5B Plumbing Installation
5C Refuse Disposal
Air-conditioning & Ventilation
5D
System
5E Electrical Installation
5F Fire Protection Installation
5G Lift & Conveyor Installation
5H Communication Installation
5J Special Installation
Builder's Profit & Attendance on
5K
Services
Builder's Work in Connection with
5L
Services
6

External Works

6A Site Work
6B Drainage
6C External Services
6D Ancillary Buildings