AREA COMPUTATIONS:

STA 0+ 000
L=0.00 C=0 m R=0 m

0h 1 00 h 20
=
=
h1
10
h2+10

STA 0+ 020
L=.36 mC=.36 m R=.36 m

L=.73 mC=.73 m R=.73 m

H 1=.36 m H 2=.36 m

H 1=.73 m H 2=.73 m

H 1=0 H 2=0 m
A=2(
A=0 m2

( 1.5 ( .36 ) +5 )+ 5
2

)(.36)

A=3.79 m2

A=2(

( 1.5 ( .73 ) +5 ) +5
2

)(.73)

A=8.10 m2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

STA 0+ 040

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 060

STA 0+ 080

STA 0+ 100

L=1.09 mC=1.09 m R=1.09 m

L=1.45 mC=1.45 m R=1.45 m

L=1.2 mC=1.2 m R=1.2m

H 1=1.09 m H 2=1.09 m

H 1=1.45 m H 2=1.45 m

H 1=1.2 m H 2=1.2 m

A=2(

( 1.5 ( 1.09 ) +5 ) +5
2

)(1.09)

A=12.68 m2

A=2(

( 1.5 ( 1.45 ) +5 ) +5
2

)(1.45)

( 1.5 ( 1.2 ) +5 ) +5
2

)(1.2)

A=17.65 m2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

A=2(

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 120
L=2.18 mC=2.18 m R=2.18 m

H 1=2.18 m H 2=2.18 m

A=2(

( 1.5 ( 2.18 ) +5 ) +5
2

STA 0+ 140

STA 0+ 160

L=1.93 mC=1.9 m R=1.86 m

L=2.32 mC=2.27 m R=2.22 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1. 5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=1.95 m H 2=1.84 m

H 1=2.36 m H 2=2.19 m

( 10C ) + ( H 1+ H 2 )( 5+1.5 ( C ) ] }
A=1/2{

( 10C ) + ( H 1+ H 2 )( 5+1.5 ( C ) ]
A=1/2{

)(2.18)

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 180

STA 0+ 200

L=3.12 mC=3.06 m R=3.01 m

L=3.64 m C=3.64 m R=3.64 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=3.64 m H 2=3.64 m

H 1=3.17 m H 2=2.96 m

A=2(

( 1.5 ( H 1 )+ 5 ) +5
2

STA 0+ 220
L=4 mC=4 m R=4 m

H 1=4 m H 2=4 m
)(C )

A=2(

( 10C ) + ( H 1+ H 2 )( 5+1.5 ( C ) ]
A= 1/2
{
UNIVERSITY OF THE EAST
MANILA

A=56.27 m
PROPOSED 1.5 KM ROAD WAY

COE CIVIL ENGG DEPARTMENT

( 1.5 ( H 1 )+ 5 ) +5
2

)(C )

EARTHWORK COMPUTATION
ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 240

STA 0+ 260

STA 0+ 280

L=4.35 mC=4.35 m R=4.35m

L=4.64 mC=4.64 m R=4.64 m

L=4.85 mC=4.85 m R=4.85m

H 1=4.35 m H 2=4.35 m

H 1=4.64 m H 2=4.64 m

H 1=4.85 m H 2=4.85 m

( 1.5 ( H 1 )+ 5 ) +5

A=2(
)(C )
UNIVERSITY
OF THE EAST
2 MANILA

A=2(
PROPOSED 1.5 KM ROAD WAY

COE CIVIL ENGG DEPARTMENT

( 1.5 ( H 1 )+ 5 ) +5
2

)(C )

( 1.5 ( H 1 )+ 5 ) +5
A=2(
)(C )
EARTHWORK COMPUTATION
2

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 300
L=4.99m C=4.99 m R=4.99 m

H 1=4.99 m H 2=4.99 m
UNIVERSITY OF THE EAST MANILA

A=2(

( 1.5 ( H 1 )+ 5 ) +5

)(C )

COE CIVIL ENGG DEPARTMENT


2

STA 0+ 320

STA 0+ 340

L=2.99 mC=2.96 m R=2.93 m

L=2.93 mC=2.9 m R=2.87 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=3.02 m H 2=2.9 m

H 1=2.96 m H 2=2.84 m

EARTHWORK COMPUTATION
PROPOSED 1.5 KM ROAD WAY

ARANDA, EDWARD B.

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

ENGR. MARK ANTHONY L. ESCOBER

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

PAGE 43
34

STA 0+ 360

STA 0+ 380

STA 0+ 400

L=2.85 mC=2.82 m R=2.79 m

L=2.91 mC=2.88 m R=2.85 m

L=1.97 mC=1.87 m R=1.88 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1C
LC H 2J
KJ
=
;
=
5+ 1.5h 1 105 1.5 H 2+5
5
EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA

H 1=2.88 m H 2=2.77 m
COE CIVIL ENGG DEPARTMENT

1=2.94 m H 2=2.82mARANDA, EDWARD B.


PROPOSED 1.5 KM ROAD H
WAY

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

H 1=2.00 m H 2=1.85 m
ENGR. MARK ANTHONY L. ESCOBER

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

PAGE 43
34

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

S TA 0+420

STA 0+ 440

STA 0+ 460

L=2.25 mC=2.22 m R=2.19 m

L=2.01 mC=1.98 m R=1.95 m

L=1.91 mC=1.89 m R=1.85 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=2.27 m H 2=2.17 m

H 1=2.03 m H 2=1.93 m

H 1=1.93 m H 2=1.83 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 480

STA 0+ 500

STA 0+ 520

L=2.12 mC=2.16 m R=2.20 m

L=1.78 mC=1.72 m R=1.77 m

L=1.35 mC=1.4 m R=1.44 m

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

h1C
LC H 2C
RC
=
;
=
5+ 1.5h 1 105 1.5 H 2+5
5

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 1=2.09 m H 2=2.23 m

H 1=2.00 m H 2=1.85 m

H 1=1.33 m H 2=1.46 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 540

STA 0+ 560

STA 0+ 580

L=.89 mC=.93 m R=.97 m

L=.48 mC=.52 m R=.57 m

L=0 m C=.05 m R=.1 m

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 1=.88 m H 2=.98 m

H 1=.47 m H 2=.58 m

H 1=0 m H 2=.1 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 600

STA 0+ 620

STA 0+ 640

L=.25 mC=.2 m R=.16 m

L=.54 m C=.5 m R=.45m

L=.16 mC=.2 m R=.25 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 1=.252m H 2=.16 m

H 1=.54 m H 2=.45 m

H 1=.16 m H 2=.25 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 660

STA 0+ 680

STA 0+ 700

L=.48 mC=.53 m R=.59 m

L=1.10 mC=1.16 m R=1.22 m

L=1.61 mC=1.55 m R=1.48 m

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=.47 m H 2=.6 m

H 1=1.08 m H 2=1.24 m

H 1=1.64 m H 2=1.45 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 720

STA 0+ 740

L=1.79 mC=1.72 m R=1.66 m

L=1.85 mC=1.79 m R=1.72 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=1.82m H 2=1.63 m

H 1=1.89 m H 2=1.69 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

L=1.73 mC=1.73 m R=1.73 m

H 1=1.73 m H 2=1.73 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2
A=20.32m

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

STA 0+ 760

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 780
L=1.16 mC=1.16 m R=1.16 m

H 1=1.16 m H 2=1.16 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2
A=12.97 m2

STA 0+ 800
L=1.08 mC=1.03 m R=.98 m

L=1.58 mC=1.53 m R=1.47 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=1.1 m H 2=.97 m

H 1=1.6 m H 2=1.44 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

STA 0+ 820

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 840

STA 0+ 860

STA 0+ 880

L=1.55 mC=1.49 m R=1.43 m

L=1.78 mC=1.71 m R=1.64 m

L=2.37 m C=2.29 m R=2.22 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=1.58 m H 2=1.41 m

H 1=1.82m H 2=1.61 m

H 1=2.42 m H 2=2.17 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2
EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 900

STA 0+ 920

STA 0+ 940

L=1.92 mC=1.85 m R=1.78 m

L=3.23 mC=3.19 m R=3.14 m

L=3.86 mC=3.81m R=3.76 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=1.96 m H 2=1.75 m

H 1=3.27 m H 2=3.1 m

H 1=3.92 m H 2=3.71 m

( 10 C ) +
( 10 C ) +
1
UNIVERSITY
OF1THE
MANILA
(H1+H2)(5+1.5(C)]}
A=
{ EAST
A= { (H1+H2)(5+1.5(C)]}
2
2
ARANDA, EDWARD B.
PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

( 10 C ) +
EARTHWORK
COMPUTATION
1
A= { (H1+H2)(5+1.5(C)]}
2
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 0+ 960

STA 0+ 980

STA 1+000

L=4.45 mC=4.35 m R=4.26 m

L=4.82m C=4.47 m R=5.11 m

L=5.26 mC=4.92 m R=4.59 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1C
LC H 2C
RC
=
;
=
5+ 1.5h 1
5
1.5 H 2+5
5

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=4.58 m H 2=4.14 m

H 1=5.38 m H 2=6.32 m

H 1=5.85 m H 2=4.17 m

UNIVERSITY OF THE EAST MANILA

( 10 C ) +
10 C ) +
ARANDA, EDWARD B.
PROPOSED 1.5 KM ROAD(WAY
1
1
A=ENGG
{ (H1+H2)(5+1.5(C)]}
A= { (H1+H2)(5+1.5(C)]}
COE CIVIL
DEPARTMENT
2
2

EARTHWORK COMPUTATION

( 10 C ) +
1
(H1+H2)(5+1.5(C)]}
A=
ENGR.{MARK
ANTHONY L. ESCOBER
2

PAGE 43
34

STA 1+020

STA 1+040

STA 1+060

L=2.14 m C=2.03 m R=1.92m

L=2.09 mC=1.98 m R=1.87 m

L=3.62 mC=3.52 m R=3.43 m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

H 1=2.17 m H 2=1.81 m

H 1=3.73 m H 2=3.33 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA

H 1=2.21 m H 2=1.86 m

COE CIVIL ENGG DEPARTMENT

PROPOSED 1.5 KM ROAD WAY

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

ARANDA, EDWARD B.

ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+080

STA 1+100

STA 1+120

L=5.23 mC=5.19 m R=5.15 m

L=.59 mC=.65 m R=.32 m

L=8.59 mC=8.60 m R=8.61m

h1R
LR RH 2
=
=
10+ 1.5h 1
10
1.5 H 2

CH 1 CL CH 2
CR
=
;
=
5+ 1.5h 1
15 5+ 1.5 H 2
5

h1
L
h2
C
= ;
=
1.5 h 1+ X X h 2+10X 5 X
EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA

H 1=5.29 m H 2=5.09 m
COE CIVIL ENGG DEPARTMENT

1=.58 m H 2=.29 m ARANDA, EDWARD B.


PROPOSED 1.5 KM ROAD H
WAY

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

C/X =J/5-X

H
1=.01
m H 2=.27
m L. ESCOBER
ENGR.
MARK
ANTHONY
A CUT =1.2987 m2

PAGE 43
34

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+140

STA 1+160

STA 1+180

L=.71 mC=.71 m R=.71m

L=1.59 mC=1.59 m R=1.59 m

L=2.41 mC=2.41 m R=2.41 m

H 1=.71 m H 2=.71 m

H 1=1.59 m H 2=1.59 m

H 1=2.41 m H 2=2.41 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

A=7.6 m

A=18.43 m

A=29.91m

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+200

STA 1+220

STA 1+240

L=3.06 mC=3.06 m R=3.06 m

L=3.50 mC=3.50 m R=3.50 m

L=3.71 mC=3.71 m R=3.71 m

H 1=3.06 m H 2=3.06 m

H 1=3.50 m H 2=3.50 m

H 1=3.71 m H 2=3.71 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

A=39.96 m2

A=47.25 m2

A=50.86 m2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+260
L=3.69 mC=3.69 m R=3.69 m

H 1=3.69 m H 2=3.69 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2
A=50.52 m

STA 1+280
L=6.14 mC=5.83 m R=5.51m

L=4.73 mC=4.67 m R=4.61m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=6.55 m H 2=5.18 m

H 1=4.79 m H 2=4.56 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

STA 1+300

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+320
L=4.29m C=4.22 m R=4.15 m

ST A 1+340
L=3.67 m C=2.76 m R=2.76 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1C LC
=
h 1+5
5

STA 1+360
L=2.99 mC=2.92 m R=2.85 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=4.35 m H 2=4.09 m

H 1=4.48 m H 2=2.76 m

H 1=3.03 m H 2=2.81 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+380

STA 1+ 400

STA 1+ 420

L=6.23 mC=6.13m R=6.03 m

L=5.78 mC=5.67 m R=5.56 m

L=5.88 mC=5.79 m R=5.7 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=6.36 m H 2=5.91 m

H 1=5.91m H 2=5.44 m

H 1=5.99 m H 2=5.6 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+ 440

STA 1+ 460

STA 1+ 480

L=5.43 mC=5.35 m R=5.26 m

L=4.9 mC=4.81 m R=4.72 m

L=4.23 mC=4.14 m R=4.05 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=5.52m H 2=5.17 m

H 1=4.99 m H 2=4.64 m

H 1=4.31 m H 2=3.98 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+500

STA 1+520

STA 1+540

L=3.56 mC=3.47 m R=3.38m

L=2.95 mC=2.86 m R=2.78 m

L=2.62 mC=2.54 m R=2.46 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=3.63 m H 2=3.32 m

H 1=3 m H 2=2.73 m

H 1=2.66 m H 2=2.42 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+560

STA 1+580

STA 1+600

L=2.29 mC=2.22 m R=2.15 m

L=1.67 mC=1.6 m R=1.53 m

L=.88 mC=.81 m R=.73 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=2.32 m H 2=2.12 m

H 1=1.69 m H 2=1.51 m

H 1=.89 m H 2=.72 m

( 10 C ) +
( 10 C ) +
1
UNIVERSITY
OF1THE
MANILA
(H1+H2)(5+(C)]}
A=
{ EAST
A= { (H1+H2)(5+(C)]}
2
2
ARANDA, EDWARD B.
PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

( 10 C ) +
EARTHWORK
COMPUTATION
1
A= { (H1+H2)(5+(C)]}
2
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+620

STA 1+640

STA 1+660

L=.04 m C=.13 m R=.21 m

L=0.94 mC=1.05 m R=1.15 m

L=.85 mC=.96 m R=1.07 m

I h 1 LR
h2L
=
=
1.5 h 1
10
1.5 h2+10

I h 1 LR
h2L
=
=
1.5 h 1
10
1.5 h2+10

I h 1 LR
h2L
=
=
1.5 h 1
10
1.5 h2+10

H 1=.04 m H 2=.22 m

H 1=.91 m H 2=1.19 m

H 1=.82 m H 2=1.11 m

UNIVERSITY OF THE EAST MANILA

( 10 C ) +
( 10 C ) +
ARANDA, EDWARD B.
PROPOSED 1.5 KM ROAD WAY
1
1
(H1+H2)(5+1.5(C)]}
(H1+H2)(5+1.5(C)]}
A=ENGG
{ DEPARTMENT
A= {
COE CIVIL
2
2

EARTHWORK COMPUTATION

( 10 C ) +
1
(H1+H2)(5+1.5(C)]}
A=
ENGR.{MARK ANTHONY L. ESCOBER
2

PAGE 43
34

STA 1+680

STA 1+700

STA 1+720

L=2.01 mC=1.88 m R=1.75 m

L=3 mC=2.87 m R=2.75m

L=1.24 m C=1.15 m R=1.08 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=3.08 m H 2=2.68 m

H 1=1.26 m H 2=1.06 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

UNIVERSITY OF THE EAST MANILA

H 1=2.06 m H 2=1.71 m

COE CIVIL ENGG DEPARTMENT

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

EARTHWORK COMPUTATION
PROPOSED 1.5 KM ROAD WAY

ARANDA, EDWARD B.

ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+740

STA 1+760

L=.4 m C=.53 m R=.65m

L=.3 mC=.42 m R=.54 m

L=.76 mC=.88 m R=1 m

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1
EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA

H 1=.39 m H 2=.68 m
COE CIVIL ENGG DEPARTMENT

STA 1+780

1=.29 m H 2=.56 m ARANDA, EDWARD B.


PROPOSED 1.5 KM ROAD H
WAY

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

H 1=.73 m H 2=1.04 m
ENGR. MARK ANTHONY L. ESCOBER

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

PAGE 43
34

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+800

STA 1+820

STA 1+840

L=1.17 mC=1.28 m R=1.4 m

L=2.54 m C=2.54 m R=2.54 m

L=9.01 mC=8.86 m R=8.71m

H 2L
RL LH 1
=
=
10+ 1.5h 2
10
1.5 H 1

H 1=2.54 m H 2=2.54 m

H 1R LR RH 2
=
=
h 1+10
10
h2

( 10 C ) +
1
A= { (H1+H2)(5+ C)]}
2

H 1=1.13 m H 2=1.45 m

( 10 C ) +
1
A= { (H1+H2)(5+1.5(C)]}
2

A=31.85 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

H 1=9.29 m H 2=8.46 m

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+860

STA 1+880

STA 1+900

L=8.19 mC=8.04 m R=7.88 m

L=7.26 mC=7.1 m R=6.94 m

L=6.37 m C=6.2m R=6.23 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=8.45 m H 2=7.64 m

H 1=7.5 m H 2=6.72 m

H 1=6.46 m H 2=6.14 m

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

( 10 C ) +
1
A= { (H1+H2)(5+(C)]}
2

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STA 1+920

STA 1+940

STA 1+960

L=3.67 m C=3.54 m R=3.41m

L=4.55 mC=4.38 m R=4.2m

L=3.07 m C=2.94 m R=2.84 m

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1R LR RH 2
=
=
h 1+10
10
h2

H 1=3.77 m H 2=3.32 m

H 1=4.72 m H 2=4.06

H 1=3.14 m H 2=2.78 m

( 10 C ) +
1 0+000STATION 0+020
STATION
A= { (H1+H2)(5+(C)]}
2
L=20 m A 1=0 m2 A 2=3.79 m2

( 10 C ) +
1
STATION 0+020STATION
0+040
A= { (H1+H2)(5+(C)]}
2
L=20 mVOLUME
A 1=3.79 m2 ACOMPUTATIONS:
2=8.10 m2

( 10 C ) +
1
STATION 0+040STATION
0+060
A= { (H1+H2)(5+(C)]}
2
L=20 m A 1=8.10 m2 A 2=12.68 m2

C1=0m

C2=.36m

C1=.36m

C2=.73m

C1=.73m

C2=1.09m

D1=10m

D2=11.08m

D1=11.08

D2=12.19m

D1= 12.19m

D2=13.27m

V =VEVC

V =VEVC

V =VEVC

1
VE= ( A 1+ A 2)(20)
2

1
VE= ( A 1+ A 2)(20)
2

1
VE= ( A 1+ A 2)(20)
2

UNIVERSITY OF THE EAST MANILA

20
Vc= ( C 1C 2 )( D 1D 2 )
12

20
Vc=
( C 1C 2 )( D 1D 2 )
PROPOSED 1.5 KM
ROAD
12 WAY

COE CIVIL ENGG DEPARTMENT

Ve=37.94 m3

EARTHWORK COMPUTATION

20
( C 1C 2 )( D 1D 2 )
ARANDA, EDWARD B. Vc=
12

ENGR. MARK ANTHONY L. ESCOBER

Ve=118.94 m3

Ve=207.82m3

PAGE 43
34

STATION 0+060STATION 0+080

STATION 0+080STATION 0+100

STATION 0+100STATI ON 0+120

L=20 m A 1=12.68 m2

L=20 m A 1=17.65 m2

L=20 m A 1=14.16 m2

A 2=17.65 m2

A 2=14.16 m 2

A 2=28.93 m 2

C1=1.09m

C2=1.45m

C1=1.45m

C2=1.20m

C1=1.45m

C2=2.18m

D1= 13.27m

D2=14.35m

D1= 14.35m

D2=13.60m

D1=14.35m

D2=16.54m

V =VEVC
1
UNIVERSITY
MANILA
VE= OF( ATHE
1+ EAST
A 2)(20)
2

COE CIVIL ENGG DEPARTMENT

20
Vc= ( C 1C 2 )( D 1D 2 )
12

V =VEVC

V =VEVC

1
VE= ( A 1+ A 2)(20)
2

1
VE= (EARTHWORK
A 1+ A 2)(20)COMPUTATION
2

PROPOSED 1.5 KM ROAD WAY

20
Vc= ( C 1C 2 )( D 1D 2 )
12

ARANDA, EDWARD B.

ENGR. MARK ANTHONY L. ESCOBER

Vc=

20
( C 1C 2 )( D 1D 2 )
12

PAGE 43
34

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STATION 0+120STATION 0+140


2

STATION 0+140STATION 0+160


2

STATION 0+160STATION 0+180

L=20 m A 1=28.93 m

L=20 m A 1=24.38 m

L=20 m A 1=30.44 m

A 2=24.38 m2

A 2=30.44 m 2

A 2=44.71m 2

C1=2.18m

C2=1.90m

C1=1.90m

C2=2.27m

C1=2.27m

C2=3.06m

D1=16.54m

D2=15.69m

D1=15.69m

D2=16.81m

D1=16.81m

D2=19.20m

V =VEVC

V =VE VC

V =VEVC

1
VE= ( A 1+ A 2)(20)
2

1
VE= ( A 1+ A 2)(20)
2

1
VE= ( A 1+ A 2)(20)
2

Vc=

20
( C 1C 2 )( D 1D 2 )
12

Vc=

20
( C 1C 2 )( D 1D 2 )
12

20
( C 1C 2 )( D 1D 2 )
12

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

Vc=

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

STATION 0+180STATION 0+200

STATION 0+200ST ATION 0+220

STATION 0+220STATION 0+240

L=20 m A 1=44.71 m2

L=20 m A 1=56.27 m2

L=20 m A 1=64 m2

A 2=56.27 m 2

A 2=64 m2

A 2=71.88 m2

C1=3.06m

C2=3.64m

C1=3.64m

C2=4m

C1=4m

C2=4.35m

D1=19.20m

D2=20.92m

D1=20.92m

D2=22m

D1=22m

D2=23.05m

V =VEVC

V =VEVC

V =VEVC

1
VE= ( A 1+ A 2)(20)
2

1
VE= ( A 1+ A 2)(20)
2

1
VE= ( A 1+ A 2)(20)
2

Vc=

20
( C 1C 2 )( D 1D 2 )
12

Vc=

20
( C 1C 2 )( D 1D 2 )
12

20
( C 1C 2 )( D 1D 2 )
12

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

Vc=

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

C1=4.35m
C2=4.64m
D1=23.05mD2=23.92m

C1=4.64m C2=4.85m
D1=23.92mD2=24.55m

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

C1=4.85m C2=4.99m
D1=24.55mD2=24.97m

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

C1=4.99m
C2=2.96m
D1=24.97mD2=18.88m

C1=2.96m C2=2.9m
D1=18.88mD2=18.7m

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

C1=2.9m C2=2.82m
D1=18.7mD2=18.46m

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

C1=2.82m C2=2.88m
D1=18.46mD2=18.64m

C1=2.88m C2=1.87m
D1=18.64mD2=15.78m

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

C1=1.87m C2=2.22m
D1=15.78mD2=16.66m

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

C1=2.22m C2=1.98m
D1=16.66mD2=15.94m

C1=1.98m C2=1.89m
D1=15.94mD2=15.64m

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

C1=1.89m C2=2.16m
D1=15.64mD2=16.48m

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

C1=2.16m C2=1.72m
D1=16.48mD2=15.41m

C1=1.72m C2=1.4m
D1=15.41mD2=14.19m

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

C1=1.4m C2=.93m
D1=14.19mD2=12.79m

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43
34

C1=.93m C2= .52m


D1=12.79mD2=11.58m

C1=.52m C2=.05m
D1=11.58mD2=10.15m

EARTHWORK COMPUTATION

UNIVERSITY OF THE EAST MANILA


PROPOSED 1.5 KM ROAD WAY
COE CIVIL ENGG DEPARTMENT

C1=.05m C2=.2m
D1=10.15mD2=10.41m

ARANDA, EDWARD B.
ENGR. MARK ANTHONY L. ESCOBER

PAGE 43