i)There must be entry of bss engineer name with signature in security resistor once
in week .
ii) All cable lie loose must be tied with cable tie . All cable must be connected
through cable tray or cable route .
iii)Team must ensure all security guard have mop and cleaner to clean BTS shelter
once a week. And Bss team to blow dust in equipment once a week.
iv) Must list point open which will be communicated to admin . below are some of