You are on page 1of 1

ID

Task Name

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56

Overall programme
Signing of contract Agreeement
Commencement of services
Inception Report
Site Reconnaissance
Data Collection
Topographical surveys
Preparation Inception report
Submit Inception report
Feasibility Study
Detailed site survey
Awaiting Geotechnical investigation and report
Preparation draft feasibility report
Approval draft feasibility Report
Prepare final feasibility report
Submit Final feasibility report
Preliminary Design
Architectural Design
Structural design
Preparation of BLP drawings (Architectural)
Preparation of BLP drawings (Structural)
Await approval of CWA, CEB, WMA
Obtain Clearance
Collate and submit drawing to Municipality Curepipe
Await Approval for BLP
Obtain Approval for BLP
Detailed Design
Detailed Structural Design
Preparation of structural drawings
Tender Documentation
Preparation of Tender documents
Issue draft tender to clients for review
Client's comment on tender Document
Prepare final Tender Document and issue to client
Approval of Tender document
Tendering and Evaluation of Tenders
Press Notice
Floating of Tenders
Tender period
Return of Tenders
Tender Evaluation (Technical)
Client's Approval of Technical evaluation report
Tender evaluation (Financial)
Client's Approval of tender committee's recommendations
Clarifications, negotiation and correspondence
Award of Contract
Construction Stage
Mobilisation
Clearing Site
Establish Benchmark
Joint Survey
Issue drawings
Construction
Issue of taking over certificate
Demobilisation and clearing of site
Handing over to client

Project: HR and QM assignment Gantt


Date: 4/14/2015

Duration
387 days
1 day
1 day
10 days
5 days
3 days
7 days
5 days
0 days
21 days
3 days
15 days
5 days
5 days
1 day
0 days
60 days
15 days
15 days
5 days
5 days
5 days
0 days
5 days
15 days
0 days
20 days
10 days
10 days
21 days
10 days
3 days
5 days
3 days
0 days
56 days
1 day
15 days
25 days
1 day
1 day
1 day
1 day
1 day
10 days
0 days
197 days
15 days
10 days
1 day
5 days
7 days
160 days
1 day
5 days
0 days

Start
1/9/2014
1/9/2014
1/10/2014
1/13/2014
1/13/2014
1/13/2014
1/16/2014
1/20/2014
1/24/2014
1/27/2014
1/27/2014
1/27/2014
2/10/2014
2/17/2014
2/24/2014
2/24/2014
2/25/2014
2/25/2014
3/18/2014
4/8/2014
4/8/2014
4/15/2014
4/21/2014
4/22/2014
4/29/2014
5/19/2014
5/20/2014
5/20/2014
6/3/2014
6/17/2014
6/17/2014
7/1/2014
7/4/2014
7/11/2014
7/15/2014
7/16/2014
7/16/2014
7/17/2014
8/7/2014
9/11/2014
9/12/2014
9/15/2014
9/16/2014
9/17/2014
9/18/2014
10/1/2014
10/2/2014
10/2/2014
10/23/2014
11/6/2014
11/7/2014
11/14/2014
11/14/2014
6/26/2015
6/29/2015
7/3/2015

Finish
7/3/2015
1/9/2014
1/10/2014
1/24/2014
1/17/2014
1/15/2014
1/24/2014
1/24/2014
1/24/2014
2/24/2014
1/29/2014
2/14/2014
2/14/2014
2/21/2014
2/24/2014
2/24/2014
5/19/2014
3/17/2014
4/7/2014
4/14/2014
4/14/2014
4/21/2014
4/21/2014
4/28/2014
5/19/2014
5/19/2014
6/16/2014
6/2/2014
6/16/2014
7/15/2014
6/30/2014
7/3/2014
7/10/2014
7/15/2014
7/15/2014
10/1/2014
7/16/2014
8/6/2014
9/10/2014
9/11/2014
9/12/2014
9/15/2014
9/16/2014
9/17/2014
10/1/2014
10/1/2014
7/3/2015
10/22/2014
11/5/2014
11/6/2014
11/13/2014
11/24/2014
6/25/2015
6/26/2015
7/3/2015
7/3/2015

an '14
Feb '14 Mar '14
Apr '14
May '14
Jun '14
Jul '14
Aug '14
Sep '14
Oct '14
Nov '14
Dec '14
Jan '15
Feb '15 Mar '15
Apr '15
May '15
Jun '15
Ju
6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 1623 2 9 162330 6 132027 4 111825 1 8 152229

Land Surveyor
Land Surveyor
Land Surveyor
RE/ARE
1/24
Land Surveyor
RE/ARE
RE/ARE
2/24

ARE
CAD Operator
4/21
PM
5/19
ARE
CAD Operator
RE/PM
RE/PM
RE/PM
7/15

RE/ARE
RE/ARE

10/1

Technical Officer
Technical Officer
RE/ARE
RE/
PM

Task

Progress

Summary

External Tasks

Split

Milestone

Project Summary

External Milestone
Page 1

Deadline

You might also like