Al Matrafiya Housing Project ‐ Tentative Programme

SL. 1st Month 2nd Month 3rd Month 4th Month 5th Month 6th Month 7th Month 8th Month 9th Month 10th Month 11th Month 12th Month 13th Month 14th Month 15th Month 16th Month

NO ITEM WEEKS 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Clients Letter of Award

Programme of Work
Preparation and Submission of Detailed Programme
Client Review and Approval

Data Collection and Site Evaluation


Existing Topographical Survey Report
Existing Utilities Information
Traffic Study Report

Methodology, Analysis & Conceptualisation


Analysis
y of Existingg Land Use Surveys
y and site information
Urban Design Methodology
Urban Design Principles and Development Rationale
Inquiry by Design Documentation for Workshop
Worksop
Complete Project Inception Report
Submission of Project Inception Report
Client's Approval

Topographical Survey
3D topographical Survey
Verify and confirm existing Topographical Report
Clients Submission

Geotechnicall Investigation
Site Investigation
Submission of Report
Clients Approval

Urban Design
Transportation Engineering, analysis & mapping
Civil Engineering analysis & mapping
L d
Landscape A l i and
Analysis dMMapping
i
Planning And Policy Analysis
Urban Plan Concept Design
Design Workshop
Preparation & Submission
Client Review & Approval of Urban Plan

Landscape Plan
Preparation of Draft Concept Landscape Plan
Preparation of Concept Landscape Strategy
Preparation & Submission
Client Review & Approval

Primary Roads and Infrastructure Design


Concept Grading Plan
Roads Layout
Submission and Approval
Potable Water Network
Sewerage Network
Drainage Network
Electrical Network
Telecom Network
Irrigation Network
Fire Fighting Network
Preparation & Submissionof Primary utilities drawings
Client Review & Approval

Secondary Roads and Infrastructure Design


Roads Layout
Submission and Approval
Potable Water Network
Sewerage Network
Drainage Network
Electrical Network
Telecom Network
Irrigation Network
Fire Fighting Network
Preparation & Submissionof Primary drawings
Client Review & Approval

Value Engineering
Concept Design
Detailed Design

Tender Documents
Technical Specifications
Tender Drawings Preparation
Bill of Quantities
Cost Estimate