PROYEK

: NOLI - BEKASI

PERIHAL

: REKAPITULASI

BAGIAN

: PERHITUNGAN KERJA TAMBAH KURANG - 4

TANGGAL

: MARET 2012

DIBUAT OLEH

: PT.TATAMETRIKA NUSANTARA

NO.

URAIAN

TOTAL

(44,683,520)

PLUMBING

95,971,960

ELECTRICAL

2,613,690

FIRE FIGHTING

35,070,240

FIRE ALARM
TELEPON DAN DATA

(26,544,120)

TATA UDARA (AC)

117,217,360

TATA UDARA (FAN)

274,129,960

TOTAL

453,775,570

:
:
:
:

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG PLUMBING
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

HARGA

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

Unit

Bh

VOLUME
DEVIASI
KERJA + / -

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE
CHANGE SHEET

PLUMBING
- Portable grease trap, stainless steel
Ukuran 400 x 400 x 300 mm
- Biotech 10 M3/day
- Sus Screan

Unit

2
-

(1)

3,700,750
70,000,000

3,700,750
1,350,000

Sub Total Pulmbing - Office Building


II

3,700,750

11,102,250

7,401,500

OFFICE BUILDING

AS BUILT DRAWING

70,000,000

(70,000,000)

OFFICE BUILDING

AS BUILT DRAWING

6,750,000

6,750,000

OFFICE BUILDING

AS BUILT DRAWING

73,700,750

17,852,250

(55,848,500)

Pemipaan Air Bersih


- Pipa PPR-PN 10
dia. : 20 mm

10

10

22,490

22,490

224,900

224,900

GUARD HOUSE BUILDING

AS BUILT DRAWING

: 15 mm

19,490

19,490

155,920

155,920

GUARD HOUSE BUILDING

AS BUILT DRAWING

- Fitting dan accessories

lot

258,190

258,190

258,190

258,190

GUARD HOUSE BUILDING

AS BUILT DRAWING

- Gate valve 10 K, dia. 20 mm

bh

95,710

95,710

95,710

95,710

GUARD HOUSE BUILDING

AS BUILT DRAWING

- Material bantu

lot

500,000

500,000

500,000

500,000

GUARD HOUSE BUILDING

AS BUILT DRAWING

III Pemipaan Air Bekas, Kotor dan Vent


- Pipa PVC AW (10 kg/cm2)
dia. : 100 mm

(SW)

75,400

75,400

301,600

301,600

GUARD HOUSE BUILDING

AS BUILT DRAWING

(WW)

31,570

31,570

126,280

126,280

GUARD HOUSE BUILDING

AS BUILT DRAWING

lot

169,220

169,220

169,220

169,220

GUARD HOUSE BUILDING

AS BUILT DRAWING

22,080

22,080

44,160

44,160

GUARD HOUSE BUILDING

AS BUILT DRAWING

lot

14,970

14,970

14,970

14,970

GUARD HOUSE BUILDING

AS BUILT DRAWING

unit

7,000,000

7,000,000

7,000,000

7,000,000

GUARD HOUSE BUILDING

AS BUILT DRAWING

- Floor Drain, dia. 50 mm

bh

242,950

242,950

242,950

242,950

GUARD HOUSE BUILDING

AS BUILT DRAWING

- Pekerjaan galian tanah dan urugan kembali

lot

31,080

31,080

31,080

31,080

GUARD HOUSE BUILDING

AS BUILT DRAWING

- Material bantu

lot

2,000,000

2,000,000

2,000,000

2,000,000

GUARD HOUSE BUILDING

AS BUILT DRAWING

11,164,980

11,164,980

: 50 mm
- Fitting dan accessories
- Pipa Vent PVC D (5 kg/cm2)
dia. : 40 mm
- Fitting dan accessories

- Septic Tank, type Biological filter (Bioseptic)


Kapasitas

: 6 - 8 orang

Sub Total Pulmbing - Guard House Building


TOTAL PEKERJAAN PLUMBING

(44,683,520)

2 / 13

BQ - OFFICE BUILDING

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

:
:
:
:

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG ELECTRICAL
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

HARGA
VOLUME
DEVIASI
KERJA + / -

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

14

12

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

8,678,400

OFFICE BUILDING

AS BUILT DRAWING

ELEKTRIKAL
2

Penerangan
Fixtures
- Exit Lamp 10 W

bh

723,200

723,200

1,446,400

10,124,800

Pengadaan dan Pemasangan Rak Kabel


- Kabel Ladder

400 x 100

(Elektrikal)

10

10

306,200

3,062,000

3,062,000

OFFICE BUILDING

AS BUILT DRAWING

- Kabel Ladder

300 x 100

(Elektrikal)

70

70

262,800

18,396,000

18,396,000

OFFICE BUILDING

AS BUILT DRAWING

- Kabel Tray

200 x 50 m (Elektronik)

10

10

322,300

3,223,000

3,223,000

OFFICE BUILDING

AS BUILT DRAWING

- Kabel Tray

300 x 50 m (Elektronik)

70

70

381,760

26,723,200

26,723,200

OFFICE BUILDING

AS BUILT DRAWING

17,991,470

6,532,080

17,991,470

11,459,390

OFFICE BUILDING

AS BUILT DRAWING

7,978,480

79,520,470

71,541,990

- Fitting dan material bantu

lot

6,532,080

Sub Total Electrical - Office Building


Instalasi
- Instalasi Lampu
Kabel NYM 3 x 2,5 mm2 dalam conduit PVC dia. 20 mm
- Instalasi Stop Kontak
Kabel NYM 3 x 2,5 mm2 dalam conduit PVC dia. 20 mm

ttk

40

40

199,690

430,880

7,987,600

17,235,200

9,247,600

UTILITY BUILDING

AS BUILT DRAWING

ttk

10

10

371,780

809,220

3,717,800

8,092,200

4,374,400

UTILITY BUILDING

AS BUILT DRAWING

723,200

723,200

4,339,200

4,339,200

UTILITY BUILDING

AS BUILT DRAWING

11,705,400

29,666,600

17,961,200

- Exit Lamp 10 W

Sub Total Electrical - Utility Building


1

Panel
- LP-GH

unit

3,966,300

3,966,300

3,966,300

3,966,300 GUARD HOUSE BUILDING

AS BUILT DRAWING

Penerangan
Fixtures
- Lampu V-Shape 1 x 36 W

bh

270,300

270,300

270,300

270,300 GUARD HOUSE BUILDING

AS BUILT DRAWING

- Lampu Downlight PLC 18 W


- Saklar Tunggal

bh
bh

1
1

1
1

100,120
29,390

100,120
29,390

100,120
29,390

100,120 GUARD HOUSE BUILDING


29,390 GUARD HOUSE BUILDING

AS BUILT DRAWING
AS BUILT DRAWING

- Saklar Seri
- Stop Kontak 1P
Instalasi

bh
bh

2
2

2
2

38,540
31,080

38,540
31,080

77,080
62,160

77,080 GUARD HOUSE BUILDING


62,160 GUARD HOUSE BUILDING

AS BUILT DRAWING
AS BUILT DRAWING

- Instalasi Lampu
Kabel NYM 3 x 2,5 mm2 dalam conduit PVC dia. 20 mm
- Instalasi Stop Kontak

ttk

146,690

146,690

293,380

293,380 GUARD HOUSE BUILDING

AS BUILT DRAWING

ttk

173,000

173,000

346,000

346,000 GUARD HOUSE BUILDING

AS BUILT DRAWING

5,144,730

5,144,730

Kabel NYM 3 x 2,5 mm2 dalam conduit PVC dia. 20 mm


Sub Total Electrical - Guard House Building
Instalasi
- Instalasi Lampu
Kabel NYM 3 x 2,5 mm2 dalam conduit PVC dia. 20 mm
- Instalasi Stop Kontak

ttk

173,200

372,670

692,800

1,490,680

797,880

TRUCK SCALE BUILDING

AS BUILT DRAWING

ttk

226,010

489,090

452,020

978,180

526,160

TRUCK SCALE BUILDING

AS BUILT DRAWING

1,144,820

2,468,860

1,324,040

Kabel NYM 3 x 2,5 mm2 dalam conduit PVC dia. 20 mm


Sub Total Electrical - Truck Scale Building
TOTAL PEKERJAAN ELECTRICAL

95,971,960
3 / 13

BQ - OFFICE BUILDING

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

:
:
:
:

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG FIRE FIGHTING
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

KONTRAK
(BQ)

HARGA

TERPASANG
(AS BUILT
DRAWING)

VOLUME
DEVIASI
KERJA + / -

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

IV PEKERJAAN PEMADAM KEBAKARAN


- Portable Fire Extinguisher
Dry Chemical Powder, kaps. 5 kg
- Bracket PFE, support dan material bantu

unit

2,331,190

2,331,190

2,331,190

2,331,190 GUARD HOUSE BUILDING

AS BUILT DRAWING

lot

282,500

282,500

282,500

282,500 GUARD HOUSE BUILDING

AS BUILT DRAWING

2,613,690

Sub Total Fire Fighting - Guard House Building


TOTAL PEKERJAAN FIRE FIGHTING

2,613,690
2,613,690

4 / 13

BQ - OFFICE BUILDING

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

:
:
:
:

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG FIRE ALARM
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

HARGA

TERPASANG
(AS BUILT
DRAWING)

KONTRAK
(BQ)

VOLUME
DEVIASI
KERJA + / -

TERPASANG
(AS BUILT
DRAWING)

KONTRAK
(BQ)

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

III FIRE ALARM


Instalasi
- Beam Detector

ttk

(6)

433,160

433,160

2,598,960

(2,598,960)

WAREHOUSE BUILDING

AS BUILT DRAWING

ttk

(7)

433,160

433,160

3,032,120

(3,032,120)

WAREHOUSE BUILDING

AS BUILT DRAWING

ttk

(7)

433,160

433,160

3,032,120

(3,032,120)

WAREHOUSE BUILDING

AS BUILT DRAWING

ttk

(7)

433,160

433,160

3,032,120

(3,032,120)

WAREHOUSE BUILDING

AS BUILT DRAWING

ttk

(7)

433,160

433,160

3,032,120

(3,032,120)

WAREHOUSE BUILDING

AS BUILT DRAWING

Kabel NYA 2 x 1.5 mm2 dalam conduit PVC dia 20 mm


- Alarm Bell
Kabel NYA 2 x 1.5 mm2 dalam conduit PVC dia 20 mm
- Manual Push Button
Kabel NYA 2 x 1.5 mm2 dalam conduit PVC dia 20 mm
- Jack Phone
Kabel NYA 2 x 1.5 mm2 dalam conduit PVC dia 20 mm
- Indicator Lamp
Kabel NYA 2 x 1.5 mm2 dalam conduit PVC dia 20 mm
- Beam Detector

ttk

1,366,920

8,201,520

8,201,520

WAREHOUSE BUILDING

AS BUILT DRAWING

ttk

1,366,920

9,568,440

9,568,440

WAREHOUSE BUILDING

AS BUILT DRAWING

ttk

1,366,920

9,568,440

9,568,440

WAREHOUSE BUILDING

AS BUILT DRAWING

ttk

1,366,920

9,568,440

9,568,440

WAREHOUSE BUILDING

AS BUILT DRAWING

ttk

1,366,920

9,568,440

9,568,440

WAREHOUSE BUILDING

AS BUILT DRAWING

14,727,440

46,475,280

31,747,840

Kabel NYA 2 x 1.5 mm2 dalam metal conduit dia 20 mm


- Alarm Bell
Kabel NYA 2 x 1.5 mm2 dalam metal conduit dia 20 mm
- Manual Push Button
Kabel NYA 2 x 1.5 mm2 dalam metal conduit dia 20 mm
- Jack Phone
Kabel NYA 2 x 1.5 mm2 dalam metal conduit dia 20 mm
- Indicator Lamp
Kabel NYA 2 x 1.5 mm2 dalam metal conduit dia 20 mm
Sub Total Fire Alarm - Warehouse Building
III FIRE ALARM
Instalasi
- Detector
Kabel NYA 2 x 1.5 mm2 dalam conduit PVC dia 20 mm
- Detector
Kabel NYA 2 x 1.5 mm2 dalam metal conduit dia 20 mm

ttk

ttk

16

16

(16)

116,760

116,760

1,868,160

(1,868,160)

UTILITY BUILDING

AS BUILT DRAWING

324,410

5,190,560

5,190,560

UTILITY BUILDING

AS BUILT DRAWING

1,868,160

5,190,560

3,322,400

16

Sub Total Fire Alarm - Utility Building


TOTAL PEKERJAAN FIRE ALARM

35,070,240

5 / 13

BQ - OFFICE BUILDING

:
:
:
:

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG TELEPON DAN DATA
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

KONTRAK
(BQ)

HARGA

TERPASANG
(AS BUILT
DRAWING)

VOLUME
DEVIASI
KERJA + / -

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

TELEPON DAN DATA


A

Peralatan Utama Telephone


- PABX 8PTT/8 Ext

Unit

- Operator Consule

(1)

21,164,900

21,164,900

(21,164,900)

OFFICE BUILDING

AS BUILT DRAWING

Include

- MDF 100 Pairs

Unit

(1)

1,469,000

1,469,000

(1,469,000)

OFFICE BUILDING

AS BUILT DRAWING

- Arrester

Unit

(1)

1,751,500

1,751,500

(1,751,500)

OFFICE BUILDING

AS BUILT DRAWING

24,385,400

(24,385,400)

Sub Total Telepon dan Data - Office Building


- Telepon

ttk

(6)

143,200

859,200

(859,200)

FILLING BUILDING

AS BUILT DRAWING

ITC 2 x 2 x 0.6 mm2 dalam PVC conduit dia. 20 mm


- Data
UTP Cat 6 E dalam conduit PVC dia. 20 mm

ttk

(4)

217,230

868,920

(868,920)

FILLING BUILDING

AS BUILT DRAWING

1,728,120

(1,728,120)

UTILITY BUILDING

AS BUILT DRAWING

UTILITY BUILDING

AS BUILT DRAWING

Sub Total Telepon dan Data - Filling Building


IV TELEPON DAN DATA
Instalasi
- Telepon

ttk

(1)

143,200

143,200

(143,200)

143,200

(143,200)

ITC 2 x 2 x 0.6 mm2 dalam PVC conduit dia. 20 mm


Sub Total Telepon dan Data - Utility Building
- Telepon

ttk

(1)

115,870

115,870

(115,870) TRUCK SCALE BUILDING

AS BUILT DRAWING

ITC 2 x 2 x 0.6 mm2 dalam PVC conduit dia. 20 mm


- Data
UTP Cat 6 E dalam conduit PVC dia. 20 mm

ttk

(1)

171,530

171,530

(171,530) TRUCK SCALE BUILDING

AS BUILT DRAWING

287,400

Sub Total Telepon dan Data - Truck Scale Building


TOTAL PEKERJAAN TELEPON DAN DATA

(287,400)
(26,544,120)

6 / 13

BQ - OFFICE BUILDING

:
:
:
:

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG HVAC
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

HARGA

TERPASANG
(AS BUILT
DRAWING)

KONTRAK
(BQ)

VOLUME
DEVIASI
KERJA + / -

TERPASANG
(AS BUILT
DRAWING)

KONTRAK
(BQ)

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

PEKERJAAN TATA UDARA


I

Unit AC
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas
- Type
Kapasitas

: Split wall

Unit

3,584,930

3,584,930

3,584,930

OFFICE BUILDING

AS BUILT DRAWING

: 1/2 PK
: Split wall

Unit

3,801,320

3,801,320

3,801,320

11,403,960

7,602,640

OFFICE BUILDING

AS BUILT DRAWING

Unit

3,960,650

3,960,650

7,921,300

11,881,950

3,960,650

OFFICE BUILDING

AS BUILT DRAWING

Unit

(4)

4,810,410

4,810,410

19,241,640

(19,241,640)

OFFICE BUILDING

AS BUILT DRAWING

Unit

14

(14)

8,103,230

8,103,230

113,445,220

(113,445,220)

OFFICE BUILDING

AS BUILT DRAWING

Unit

12

(12)

9,112,320

9,112,320

109,347,840

(109,347,840)

OFFICE BUILDING

AS BUILT DRAWING

: 3/4 PK
: Split wall
: 1 PK
: Split wall
: 1,5 PK
: Split wall
: 2 PK
: Split wall
: 2,5 PK
: Ceilling Cassette

Unit

13,627,430

13,627,430

13,627,430

OFFICE BUILDING

AS BUILT DRAWING

Unit

15,926,980

47,780,940

47,780,940

OFFICE BUILDING

AS BUILT DRAWING

Unit

20,905,510

146,338,570

146,338,570

OFFICE BUILDING

AS BUILT DRAWING

Unit

25,724,000

128,620,000

128,620,000

OFFICE BUILDING

AS BUILT DRAWING

Unit

10,000,500

20,001,000

20,001,000

OFFICE BUILDING

AS BUILT DRAWING

13

(20)

305,370

305,370

10,077,210

3,969,810

12

12

1,124,100

13,489,200

: 2 PK
: Ceilling Cassette
: 2,5 PK
: Ceilling Cassette
: 3 PK
: Ceilling Cassette
: 4 PK
: Ceilling Duct
: 2 PK

1.2 Kabel Power AC


- NYM 3 x 2.5 mm dalam conduit PVC dia. 20 mm

titik

- NYM 4 x 4 mm dalam conduit PVC dia. 25 mm

titik

33
-

(6,107,400)

OFFICE BUILDING

AS BUILT DRAWING

13,489,200

OFFICE BUILDING

AS BUILT DRAWING

1.3 Pipa Refrigerant


- dia. 1/4" + 3/8" + kabel kontrol

12

60

48

77,260

77,260

927,120

- dia. 1/4" + 1/2" + kabel kontrol

24

-24

(48)

86,780

86,780

2,082,720

- dia. 1/4" + 5/8" + kabel kontrol

216

120

(96)

95,940

95,940

- dia. 3/8" + 5/8" + kabel kontrol

120

60

(60)

103,880

- dia. 3/8" + 3/4" + kabel kontrol

60

60

7 / 13

4,635,600

3,708,480

OFFICE BUILDING

AS BUILT DRAWING

(2,082,720)

(4,165,440)

OFFICE BUILDING

AS BUILT DRAWING

20,723,040

11,512,800

(9,210,240)

OFFICE BUILDING

AS BUILT DRAWING

103,880

12,465,600

6,232,800

(6,232,800)

OFFICE BUILDING

AS BUILT DRAWING

146,360

8,781,600

8,781,600

OFFICE BUILDING

AS BUILT DRAWING

BQ - OFFICE BUILDING

:
:
:
:

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG HVAC
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

HARGA

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

VOLUME
DEVIASI
KERJA + / -

TERPASANG
(AS BUILT
DRAWING)

KONTRAK
(BQ)

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

1.4 Pipa Drain AC, PVC AW (10 kg/cm2) c/w isolasi


-

dia. : 25 mm

96

150

54

66,690

66,690

6,402,240

10,003,500

3,601,260

OFFICE BUILDING

AS BUILT DRAWING

dia. : 20 mm

126

70

(56)

59,360

59,360

7,479,360

4,155,200

(3,324,160)

OFFICE BUILDING

AS BUILT DRAWING

1.5 Fitting dan accessories

lot

2,532,080

109,590

2,532,080

219,180

(2,312,900)

OFFICE BUILDING

AS BUILT DRAWING

1.6 Material Bantu

lot

4,000,000

5,000,000

4,000,000

10,000,000

6,000,000

OFFICE BUILDING

AS BUILT DRAWING

320,446,690

454,155,750

133,709,060

Sub Total Tata Udara - Office Building


II

Unit AC
- Type
Kapasitas

: Split wall
: 1,5 PK

- Type

: Split wall

Kapasitas

Unit

(2)

4,810,410

4,810,410

9,620,820

(9,620,820)

FILLING BUILDING

AS BUILT DRAWING

Unit

(6)

8,103,230

8,103,230

48,619,380

(48,619,380)

FILLING BUILDING

AS BUILT DRAWING

3,584,930

3,584,930

3,584,930

FILLING BUILDING

AS BUILT DRAWING

305,370

305,370

2,442,960

305,370

(2,137,590)

FILLING BUILDING

AS BUILT DRAWING

1,100,250

9,902,250

9,902,250

FILLING BUILDING

AS BUILT DRAWING

(90)

95,940

77,260
95,940

8,634,600

927,120
-

927,120
(8,634,600)

FILLING BUILDING
FILLING BUILDING

AS BUILT DRAWING
AS BUILT DRAWING

59,360

59,360

3,324,160

593,600

(2,730,560)

FILLING BUILDING

AS BUILT DRAWING

FILLING BUILDING

AS BUILT DRAWING

: 2 PK

- Type
Kapasitas

: Split wall
: 1/2 PK

Unit

1.2 Kabel Power AC


- NYM 3 x 2.5 mm dalam conduit PVC dia. 20 mm

Titik

- NYM 3 x 2.5 mm dalam metal conduit dia. 20 mm

Titik

1.3 Pipa Refrigerant


- dia. 1/4" + 3/8" + kabel kontrol
- dia. 1/4" + 5/8" + kabel kontrol

(7)

12

m
m

90

20 mm

lot

56

10

(46)

1.5 Fitting dan accessories

lot

1.4 Pipa Drain AC c/w isolasi


-

dia.

(925,660)

(925,660)

Sub Total Tata Udara - Filling Building


III

(925,660)

(1,851,320)

(925,660)

71,716,260

13,461,950

(58,254,310)

Unit AC
- Type

: Ceilling Suspended

Kapasitas

unit

13,051,500

26,103,000

26,103,000

UTILITY BUILDING

AS BUILT DRAWING

24

24

95,940

2,302,560

2,302,560

UTILITY BUILDING

AS BUILT DRAWING

10

1,100,250

1,100,250

8,802,000

11,002,500

2,200,500

UTILITY BUILDING

AS BUILT DRAWING

20

20

66,690

1,333,800

1,333,800

UTILITY BUILDING

AS BUILT DRAWING

2,000,000

2,000,000

2,000,000

4,000,000

2,000,000

UTILITY BUILDING

AS BUILT DRAWING

: 2,5 PK

- Pipa Refrigerant
dia. 1/4" + 5/8" + kabel kontrol
- Kabel Power AC

ttk

NYM 3 x 2.5 mm dalam metal conduit dia. 20 mm


- Pipa Drain AC, PVC AW (10 kg/cm2) c/w isolasi
dia. : 25 mm
- Material Bantu

m
lot

8 / 13

BQ - OFFICE BUILDING

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

:
:
:
:

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG HVAC
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

HARGA
VOLUME
DEVIASI
KERJA + / -

KONTRAK
(BQ)

Sub Total Tata Udara - Utility Building

TERPASANG
(AS BUILT
DRAWING)

TOTAL HARGA
(BQ)

10,802,000

9 / 13

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

44,741,860

LOKASI

NUMBER/DATE CHANGE
SHEET

33,939,860

BQ - OFFICE BUILDING

:
:
:
:

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG HVAC
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

IV Unit AC
- Type

UNIT

KONTRAK
(BQ)

unit

HARGA

TERPASANG
(AS BUILT
DRAWING)

VOLUME
DEVIASI
KERJA + / -

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

3,584,930

3,584,930

3,584,930 TRUCK SCALE BUILDING

AS BUILT DRAWING

305,370

1,100,250

305,370

2,200,500

1,895,130 TRUCK SCALE BUILDING

AS BUILT DRAWING

: Split wall

Kapasitas

: 1/2 PK

- Kabel Power AC
NYM 3 x 2.5 mm dalam metal conduit dia. 20 mm

titik

- Pipa Refrigerant
dia. 1/4" + 3/8" + kabel kontrol

18

12

77,260

77,260

463,560

1,390,680

927,120 TRUCK SCALE BUILDING

AS BUILT DRAWING

- Pipa Drain AC c/w isolasi

14

10

59,360

59,360

237,440

831,040

593,600 TRUCK SCALE BUILDING

AS BUILT DRAWING

- Fitting dan accessories

lot

80,490

201,230

80,490

402,460

321,970 TRUCK SCALE BUILDING

AS BUILT DRAWING

- Material Bantu

lot

1,500,000

1,000,000

1,500,000

2,000,000

500,000 TRUCK SCALE BUILDING

AS BUILT DRAWING

2,586,860

10,409,610

dia. : 20 mm

Sub Total Tata Udara - Truck Scale Building


TOTAL PEKERJAAN HVAC

7,822,750
117,217,360

10 / 13

BQ - OFFICE BUILDING

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

:
:
:
:

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG HVAC
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

HARGA
VOLUME
DEVIASI
KERJA + / -

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

1,887,040

OFFICE BUILDING

AS BUILT DRAWING

1,473,820

1,110,980

OFFICE BUILDING

AS BUILT DRAWING

407,930

1,473,820

1,065,890

OFFICE BUILDING

AS BUILT DRAWING

1,473,820

407,930

1,473,820

1,065,890

OFFICE BUILDING

AS BUILT DRAWING

1,985,980

3,815,530

1,985,980

3,815,530

1,829,550

OFFICE BUILDING

AS BUILT DRAWING

1,985,980

3,815,530

3,971,960

7,631,060

3,659,100

OFFICE BUILDING

AS BUILT DRAWING

479,350

1,473,820

479,350

1,473,820

994,470

OFFICE BUILDING

AS BUILT DRAWING

1,985,980

3,815,530

3,971,960

7,631,060

3,659,100

OFFICE BUILDING

AS BUILT DRAWING

TERPASANG
(AS BUILT
DRAWING) KRUGER

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

Unit

530,300

1,473,820

1,060,600

2,947,640

Unit

362,840

1,473,820

362,840

Unit

407,930

1,473,820

Unit

407,930

Unit

Unit

Unit

Unit

KONTRAK
(BQ) - VANCO

PEKERJAAN TATA UDARA


I

Unit Fan
- Exhaust Fan
Type

: Wall

Air Flow Rate

: 350

CFM

Lokasi / service : Toilet Office


- Exhaust Fan
Type

: Wall

Air Flow Rate

: 125

CFM

Lokasi / service : Smooking Room


- Exhaust Fan
Type

: Wall

Air Flow Rate

: 225

CFM

Lokasi / service : Toilet Lab


- Exhaust Fan
Type

: Wall

Air Flow Rate

: 225

CFM

Lokasi / service : Toilet Cateen


- Exhaust Fan
Type

: Ceilling

Air Flow Rate

: 400

CFM

Static Pressure

: 0.20

Inch WG

Lokasi / service : Famale Toilet Lt. 1


- Exhaust Fan
Type

: Ceilling

Air Flow Rate

: 350

CFM

Static Pressure

: 0.20

Inch WG

Lokasi / service : Male Toilet Lt. 1


- Exhaust Fan
Type

: Wall

Air Flow Rate

: 270

CFM

Lokasi / service : Pantry


- Exhaust Fan
Type

: Ceilling

Air Flow Rate

: 400

CFM

Static Pressure

: 0.20

Inch WG

Lokasi / service : Male Locker Room

11 / 13

BQ - OFFICE BUILDING

:
:
:
:

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG HVAC
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

UNIT

HARGA

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

VOLUME
DEVIASI
KERJA + / -

KONTRAK
(BQ) - VANCO

TERPASANG
(AS BUILT
DRAWING) KRUGER

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

OFFICE BUILDING

AS BUILT DRAWING

- Exhaust Fan
Type

: Ceilling

Air Flow Rate

: 350

CFM

Unit

Static Pressure

: 0.20

Inch WG

1,985,980

3,815,530

3,971,960

7,631,060

3,659,100

16,620,510

35,551,630

18,931,120

Lokasi / service : Female Locker Room


Sub Total Tata Udara - Office Building
II

Unit Fan
- Exhaust Fan
Type

: Ceilling

Air Flow Rate

: 100

CFM

Static Pressure

: 0.20

Inch WG

Unit

(3)

344,330

884,410

1,032,990

(1,032,990)

FILLING BUILDING

AS BUILT DRAWING

Unit

(1)

362,840

1,473,820

362,840

(362,840)

FILLING BUILDING

AS BUILT DRAWING

Unit

16

16

2,478,610

5,902,950

39,657,760

94,447,200

54,789,440

FILLING BUILDING

AS BUILT DRAWING

Unit

37,851,560

52,787,300

151,406,240

211,149,200

59,742,960

FILLING BUILDING

AS BUILT DRAWING

Titik

28

20

278,860

1,075,500

7,808,080

21,510,000

13,701,920

FILLING BUILDING

AS BUILT DRAWING

200,267,910

327,106,400

126,838,490

7,217,920

23,611,800

16,393,880

WAREHOUSE BUILDING

AS BUILT DRAWING

Lokasi / service : Toilet (M/F)


- Exhaust Fan
Type

: Wall Mounted

Air Flow Rate

: 100

CFM

Lokasi / service : Storage Room


- Exhaust Fan
Type

: Industrial Propeller

Air Flow Rate

: 2,700

CFM

Static Pressure

: 0.39

Inch WG

Lokasi / service : Filling Facilities Lantai 1


- Exhaust Fan
Type

: Axial

Air Flow Rate

: 20,000

CFM

Static Pressure

: 1.25

Inch WG

Lokasi / service :
-

Kabel Power Fan


NYY - 3 x 4 mm2

(8)

Sub Total Tata Udara - Filling Building


III Unit Fan
- Exhaust Fan

Unit

Type

: Industrial Propeller

Air Flow Rate

: 2,000

CFM

Static Pressure

: 0.39

Inch WG

1,804,480

5,902,950

Lokasi / service : Warehouse

12 / 13

BQ - OFFICE BUILDING

PROYEK
PERIHAL
TANGGAL
DIBUAT OLEH

:
:
:
:

NOLI - BEKASI
PERHITUNGAN KERJA TAMBAH KURANG HVAC
MARET 2012
PT.TATAMETRIKA NUSANTARA
VOLUME

NO

DESCRIPTION

- Exhaust Fan

UNIT

Unit

Type

: Industrial Propeller

Air Flow Rate

: 2,700

CFM

Static Pressure

: 0.39

Inch WG

HARGA

KONTRAK
(BQ)

TERPASANG
(AS BUILT
DRAWING)

16

16

VOLUME
DEVIASI
KERJA + / -

KONTRAK
(BQ) - VANCO

TERPASANG
(AS BUILT
DRAWING) KRUGER

TOTAL HARGA
(BQ)

TOTAL HARGA
TOTAL HARGA
TERPASANG (AS
(KERJA +/-)
BUILT DRAWING)

LOKASI

NUMBER/DATE CHANGE
SHEET

2,478,610

5,902,950

39,657,760

94,447,200

54,789,440

WAREHOUSE BUILDING

AS BUILT DRAWING

278,860

1,075,500

21,510,000

21,510,000

WAREHOUSE BUILDING

AS BUILT DRAWING

46,875,680

139,569,000

92,693,320

Lokasi / service : Filling Facilities Lantai 1


-

Kabel Power Fan


NYY - 3 x 4 mm2

Titik

20

20

Sub Total Tata Udara - Warehouse Building


IV Unit Fan
- Exhaust Fan
Type

: Industrial Propeller

Air Flow Rate

: 3,200

CFM

Static Pressure

: 0.39

Inch WG

Unit

(1)

5,977,880

2,977,980

5,977,880

(5,977,880)

UTILITY BUILDING

AS BUILT DRAWING

Unit

(1)

5,961,950

2,478,610

5,961,950

(5,961,950)

UTILITY BUILDING

AS BUILT DRAWING

Unit

(6)

5,961,950

2,478,610

35,771,700

(35,771,700)

UTILITY BUILDING

AS BUILT DRAWING

47,711,530

(47,711,530)

362,840

362,840

Lokasi / service : Emergency Generator Room


- Exhaust Fan
Type

: Industrial Propeller

Air Flow Rate

: 2,550

CFM

Static Pressure

: 0.39

Inch WG

Lokasi / service : Pump Room


- Exhaust Fan
Type

: Industrial Propeller

Air Flow Rate

: 2,700

CFM

Static Pressure

: 0.39

Inch WG

Lokasi / service : Switch Gear Room dan


Boiller Compressor Room
Sub Total Tata Udara - Utility Building
V

Unit Fan
- Exhaust Fan

Unit

Type

: Wall Mounted

Air Flow Rate

: 150

(1)

362,840

1,473,820

(362,840) GUARD HOUSE BUILDING

AS BUILT DRAWING

CFM

Lokasi / service : Guard house


Sub Total Tata Udara - Guard House Building

(362,840)

VI Unit Fan
- Exhaust Fan
Type

: Industrial Propeller

Air Flow Rate

: 2,700

CFM

Static Pressure

: 0.39

Inch WG

Unit

12

12

2,478,610

5,902,950

70,835,400

70,835,400

BLENDING BUILDING

AS BUILT DRAWING

Titik

12

12

278,860

1,075,500

12,906,000

12,906,000

BLENDING BUILDING

AS BUILT DRAWING

83,741,400

83,741,400

Lokasi / service : Filling Facilities Lantai 1


-

Kabel Power Fan


NYY - 3 x 4 mm2

Sub Total Tata Udara - Blending Building


TOTAL PEKERJAAN EXHAUST FAN

274,129,960
13 / 13

BQ - OFFICE BUILDING