You are on page 1of 3

DAILYREPORTFROM SITE

S.No:44

1.

Date 22.02.2013

Site: M/s Baldev alloys pvt. LTD.


Vwta020,VWHA052,053,054

Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)

Site vacation reg m

2.

Details of communications sent to HO


on

Daily report, Roof truss purlin clarification sen

3.

Details of consignments / materials


received from HO / others

Nil.

4.

Details of payments received from HO /


others

Nil.

5.

Attendance with details


:

MR.M.E.MANIKANDAN(2141)

5.1

Staff (VEESONS)

Mr. DINESH KUMAR.S (1832)

5.2

6.

Contract Workers (Contractor wise)

Important brief feedback about Fabrication


/ Erection / Commissioning (delay with
reference to schedule, major problems
etc.,)

Utkal Engineers:
Boiler: Supervisor:01 IB
05; Riger-03;grinder-0 Helper-07(Total=20)

1.contractor man power shortage

2. Radiography film required from con


3.customer side insert plates

7.

Materials, documents, payments urgently


required from HO with details

8.

Any urgent / important site complaints

UTKAL Engineering Should be


increasing his manpower.
Utkal engineering tools &
tackles Shortage.(welding
machine & cutting set, Grinding
machine)

Site status:

VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1) Bed material bunker monorail beam erection work
completed.
2) Steam drum pressure transmitter piping modification work
u/p.
3) Feed water Common header to WHRB & FBC line Supports
work Completed.
4) Dea. Outlet to feed pump suction piping support work U/P.
5) Air Ducting outer stretch welding work U/P.
6) Air heater outlet to esp inlet duct support welding work
completed.

ESP;
1) Roof beam Plat form work Completed.
2) ESP sealing roof erection work u/p.
3) Discharge frame level alignment work completed.

Prepared by (Name):

M.E.MANIKANDAN
Signature:

Checked & Approved by (Name) :

M.E.MANIKANDAN
Signature:

Staff No : 2141

Staff No. :2141

You might also like