S.No:44
1.
Date 22.02.2013
Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)
2.
3.
Nil.
4.
Nil.
5.
MR.M.E.MANIKANDAN(2141)
5.1
Staff (VEESONS)
5.2
6.
Utkal Engineers:
Boiler: Supervisor:01 IB
05; Riger-03;grinder-0 Helper-07(Total=20)
7.
8.
Site status:
VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1) Bed material bunker monorail beam erection work
completed.
2) Steam drum pressure transmitter piping modification work
u/p.
3) Feed water Common header to WHRB & FBC line Supports
work Completed.
4) Dea. Outlet to feed pump suction piping support work U/P.
5) Air Ducting outer stretch welding work U/P.
6) Air heater outlet to esp inlet duct support welding work
completed.
ESP;
1) Roof beam Plat form work Completed.
2) ESP sealing roof erection work u/p.
3) Discharge frame level alignment work completed.
Prepared by (Name):
M.E.MANIKANDAN
Signature:
M.E.MANIKANDAN
Signature:
Staff No : 2141