Scenario: Production order is released and operation 0010 is started. As soon as operation
0010 is confirmed, GI will happen automatically. GI is nothing but component consumption to a
production order which means stock of components at production input storage location will
deplete.
We will test this by 2 ways:
1. By defining backflush in the specific routing (so that it becomes routing specific)
2. By defining backflush at material master level (this will make it permanent)
Select the row and go to component allocation. Tick the backflushing indicator as shown:
Save it
MMBE
Please note that, quantity of Raw13 has not changed
{If we dont maintain backflush indicator in either of places then GI will not happen
automatically, in that case user has to go to Goods Movement screen in CO11N
transaction}