Professional Documents
Culture Documents
Guide To Pressure Vessel Codes 1
Guide To Pressure Vessel Codes 1
INTRODUCTION
There is an increasing use of national and international codes on unfired
pressure vessels in BHELs Plants as well as in the works of BHELs Vendors.
While interpretation of the Codes is possible by going through the actual
codes, it is felt necessary that salient features of some of the regularly used
national and international codes will be useful in concise form and in the form
of a comparative statement.
Some work in this regard was already done by Bhopal and Hyderabad Plants.
This Publication is an attempt to assist the Specialists, Executives and
Supervisors at Shop Floor level as a reference document. The efforts put in
by the Quality Services Group of Bhopal and Ramachandrapuram in
compiling this useful booklet is acknowledged.
Secunderabad
May 5, 1984.
(P.S.THILAK)
Dy. General Manger
Corporate Quality Assurance
B.S.5500 : 1976
A. SCOPE OF THE COSES
Covers design, constructions,
inspection,
testing
and
certification of unfired fusion
welded pressure vessels.
Sections include:
1. General (Definitions and
responsibility of purchaser,
manufacturer,
inspectors
etc.)
2. DESIGN
3. MANUFACTURE
WORKMANSHIP
&
5. APPENDICES
mandatory)
(all
non-
IS 2525 : 1969
Covers
minimum
construction
requirements for design, fabrication,
inspector, testing, and certification of
fusion welded unfired pressure
vessels, in ferrous and non-ferrous
materials.
1)
2)
3)
4)
I.B.R
Covers design, construction, testing and
certification of boilers mainly. However
chapter XV Heat exchangers etc., and
similar vessels recommended that heat
exchangers and similar vessels be
constructed following the applicable
regulations, covered under different
General, material & design.
chapters.
Usually Chapter XII shell type boilers of
Fabrication and welding
Inspection test, marking and welded construction is being followed.
Also regulation 523A stipulates that
records.
Appendices (both mandatory and feed water heaters may be constructed
as per chapter XII.
non-mandatory)
Hence reference is mostly made to
chapter XII shell type boilers of welded
constructions is being followed.
Also regulation- 523 A stipulates that
feed water heaters may be constructed
as per chapter XII.
Hence reference as per chapter XII
ONLY.
For
workmanship
various
chapters covered are:
Chapter I
General requirement
II
Material for construction
XII Shell type boilers of
welded construction.
Equipments governed by I.B.R. are as
noted below:
1) All boilers.
2) Steam pipes with pressure 3.5
Kg/ SQ. Cm. Or with dia
exceeding 254 mm in I.D and
with out limitations of pressure.
3) Equipments like feed water
heaters etc connected after
boilers etc connected after boiler
feed pump in which steam is the
medium.
This standard does not included the
following:
1.Vessels which design pressure
exceeding 210 KG/Cm2
2.Vessels with O.D/I.D > 1.5
3.Vessels operating under internal
pressure below 1 Kg/Cm2
4.Vessels with I.D. > 150 mm
IS 2525: 1969
I.B.R
Construction
category.
NDT
permitted
material
100%
all
Spot
M0 & M1,M2
M 3, M4
Austenitic
steels.
Visual
only M0,
Austenitic
steels
Max,
thickness
(mm)
None
except
M0, M1-40
M2-30
M3-20
M4-15
Austenitic
none
M0-25
Austenitic
steels
none.
Upper
Temperature
limits
Values
to be
based
on
design
life
time
etc., as
per
table
2.3
Note
Note
Same
as 350o C
category
Lower
temperature
limit
For M0
M1, M2,
M3, M4
Less
than
10oC above
For M0
M1, M2,
M3, M4
Less
than
20oC
above
Category D joints
connecting communicating
chambers of nozzles to main
sheels, to heads, to
transitions in diameters
IS 28 25 : 1969
B.
CLASSIFICATION
VESSELS
I.B.R
OF Classification: Class I
Application: No limits
thickness: inch
limits of
Minimum
Classification: Class II
Limits of Application: When the
following limits are not exceeded:
a. Working pressure 105 psi
b. Working
pressure
in
psi
multiplied by ID in inches - 5250
Minimum thickness: Boilers upto 36
inches I D 5/16 inch.
Classification: Class III
Limits of Application: when the
following limits are not exceeded:
Vessels are classified in three
groups on the bases of use,
thickness. Joint design and
efficiency materials of construction
and Quality Control requirements.
not
Minimum
specified
in
a
Appendix
D None
austenitic
steels
Minimum
specified,
None
austenitic
steels.
I.B.R.
10
C. MATERIAL REQUIREMENTS
Materials should take into account the
fabrication and operating conditions.
Special consideration should be given
for use below 0o C. Any special limits
e.g. w.r.t. Composition, heat treatment
should be agreed upon at the time of
enquiry or order.
High alloy steels are listed in Table UHA23 and appendix HA given suggestions on
the selection and treatment of austenitic
chromium Nickel steels. High alloys steel
casting are mentioned in Table 23. The
stress values are to be multiplied by
casting quality factor of UG-24.
11
IS 2525 : 1969
I.B.R
Class 3 vessels may use the above Electrodes (R: 538) They shall comply
mentioned prohibited materials and with the regulations of 94 to 98.
also IS 2041 (steel plates for
pressure vessels), IS 1570 (wrought
steels general engineering purposes),
IS 2002 (Steel plates for boilers).
Nothing in the foregoing precluded
the use of otherwise suitable material
agreed upon. Special care to be
taken for weld ability and ductility. No
such material shall have an
elongating (on 5.65 50) of less than
100-Rm
where Rm is the tensile
2.2
strength in kgf/mm2 subjected to a
minimum of 16% fore carbon
manganese steels. 14 % for alloy
steels other than austenitic and 25%
for austenitic steels. Material for lugs,
baffles, etc. to be weldable quality All
materials shall be supplied in
accordance with IS 1387 1967, and
threaded fasteners in accordance
with IS 1369-1967.
12
for
13
I.B.R
14
15
I.B.R
16
D. MANUFACTURE AND
WORKMANSHIP
GENERAL
GENERAL
1.
2.
A
position
identification 2.
system for pressure parts is
necessary so that they can
be traced back to their origin.
3.
17
I S 2525 : 1969
GENERAL
I.B.R
GENERAL
1.
2.
MATERIALS
(Procedure
for
identification):
All plates, rivets and bars used in
the construction of boilers shall
be tested and found to conform
with the regulations to conform
with the regulations. A certificate
in form II, III, III-A and IV.
3.
Concentration
of
joints 3.
should be avoided such that
no two main seams come
together under an acre angle
or cross each other. Where
unavoidable,
the
intersections should be radio
graphed 100 mm on each
side of inter section be
staggered by five (5) times
the thickness of thicker plate.
Welding of attachments near
main seams to be avoided. If
unavoidable welds should
cross rather than stop
abruptly near seams.
18
B S 5500: 1976
Thermal cut ferritic alloy steel shall be All materials to be impact tested shall
dresses by grinding or machining.
be inspected for surface cracks.
Visual examination for laminations, Adjoining edges of longitudinal joints
crackers, slag inclusions may be to be preliminary formed to avoid flat
supplemented by N.D.T.
spots after rolling.
2. Prior to forming, visual examination
of plates, followed by thickness
measurement, to be done.
3. Austenitic steels for hot working
shall be heated uniformly in neutral or
oxidizing temp. Deformation below
900o C and local heating is
prohibited.
After
hot
working,
softening to be carried out by heating,
at a recommended temp, hot less tan
30 minutes. Descalling to done.
19
IS 2825: 1969
1. Where thickness < 25 mm, cold
shearing may be used provided
edges are chipped or machined
one quarter of plate thickness or
minimum. 3 mm.
Caron steels may be mained,
chipped ground or flame cut but
alloy steels and non-ferrous
materials shall not be flame cut
unless agreed upon.
Preheating may be required and
visual examination for flaws
laminations, inclusions shall be
made special inspection may be
required for cracks on cut surfaces
and HAZ in high carbon and alloy
steels
Hand flame cut edges shall be
chipped or machined 3 mm
minimum or one quarter plate
thickness
2. Seams may be welded prior to
forming but must be radio graphed
fully after wards. In carbon steels
< 25 mm and alloy steels DP or
MCD to be done.
I.B.R
1. Chapter XII. Regulation 541
plates which are to flame- cut by
machine without subsequent heattreatment, grinding or machining,
shall not have or machining, shall
not have a carbon content higher
than 0.26 percent. Where the
carbon content exceeds 0.26
percent. Heart-treatment grinding
or machining shall be carried out.
BS 5500: 1976
5. TOLERANCES
I) Assembly Tolerance:
I) Alignment tolerance
a. Longitudinal joints and spherical joints Thickness Longitufor plate thickness e.
dinal
Middle line
Upto in t
e
alignment
(12.5 mm)
Circumferential
t
<10 mm
>10 and 50 mm
1 mm
Over
1/8 in (3 t
10% of e or 3 mm into mm mm)
(whichever smaller) (125-19
mm)
> 200 mm
As agreed upon
Lesser of
1/8 t or
in
(19
mm)
b) Circumferential joints:
Middle line
alignment
e
10 mm
> 10 and
60 mm
1 mm
10% of e or the
thinner part.
> 200 mm
As agree upon.
E/4 mm
3mm
Lesser of e/16 or
10mm.
21
I.B.R.
I) Alignment tolerance
5. TOLERANCES:
of
mm
22
b) Circumferential joints
e 20 mm
e/4 mm
20 < e 40 mm
5 mm
E > 40 mm
Lesser of e/8
or 20 mm
23
I.B.R
5.2 (R-544)
a) The difference between the
internal diameter of the drum
measured at any cross section
shall not exceed 1 % nominal I.D.
The departure shall not exceed:
i) Upto and including 36 I.D.
0.375%
ii) Over 36 upto and including 45
I.D. 0.35%
iii) Over 45 I.D.
24
Dia of end
permissible
increase in the
depth of dishing
< 3000 mm
1.25% of dia
3000-7600mm 3.8 mm
< 7600 mm
0.5% of dia
25
I.B.R
Tolerance
5 mm
0.25%
Notwithstanding
these,
the
governing factor shall be the
misalignment tolerances.
Max. deviation from straightness
is to be 0.3% of total length or 5
meters length, for shells over 2
meters long.
26
At nozzle positions, greater ovality Sharp bends, flat spots etc, are
is permitted if justified by not permitted.
calculations.
Measurement must be made to
surface of parent plate and not to
a weld, fitting or raised part.
For vessels to be vertically
installed but checked horizontally
dia, should be measured twice 90o
a part after turning the shell
through 90o. The sets should be
averaged and ovality calculated.
27
I.B.R.
b) Out of roundness is to be
less than 1% of I.D. on
D1 + 1250 ; (D1 = I.D.)
200
Whichever is smaller.
At nozzle positions greater values
may be permitted. Irregularities in
profile (checked by 20o gauge)
shall not exceed 3 mm + 5% of
min. plate thickness. The max.
value may be increased by 25% if
the length of irregularity is less
than of length of shell ring.
28
Cold rolling after forming permitted For vessels made or pipes, pipe
(for small rectification) but N.D.T. standards are applicable.
must be done. For vessels made
of pipes, pipe standards are
applicable.
6. WELDED JOINTS
Welding procedures and welders
to be qualifies. Test plates to be
used only on purchasers request.
Consumables used shall be those
used in qualification tests.
29
I.B.R
6.2
30
AND
F.2.
POST
WELD
TREATMENT (PWHT)
Require for:
HEAT
31
I.B.R
32
B.S.5500: 1976
establish that material
adversely affected.
not
33
34
I.B.R.
Different temperatures may be
necessary to obtain proper stress
relieving. The part to be stress
relieved shall be brought slowly upto
the specific temperature and held at
that temperature for a period
proportionate on the basis of at least
2 minutes per millimeter of the
maximum thickness of the part
(approximately one hour per 25 mm of
thickness) and shall be left to cool in
the furnace to a temperature to which
for the parts with a thickness greater
than 20 mm does not exceed 400o C.
After withdraw from the furnace the
part shall be allowed to cool in a still
atmosphere.
A temperature time diagram of the
stress relieving process shall be
provided for a welded shell or drum
and a similar diagram for other
pressure parts when the Inspection
Authority requires it.
During heat treatment official test
plates shall be inside the boiler.
Where the shell is subjected to a
primary stress relieving treatment
identical to the final heat treatment to
be given to the boiler, the test shell
during
primary
treatment
and
hereafter cut up and tested without
waiting for the final treatment of the
boiler.
Where the shell is not subject to
primary stress relieving treatment or is
subjected to primary stress relieving
treatment, which is not identical with
the final heat treatment the test plates
may be placed inside any other boiler
of comparable dimensions, which is to
be heat treated in accordance with
this chapter.
Temperature
charts
shall
be
submitted to indicate that the test
plates and the boiler they represent,
have been subjected to identical
heating,
soaking
and
cooling
treatment.
35
36
I.B.R
37
Heating
rates
2200c/hr
for
thickness upto 25mm.
5500/ e00 /hr on 550C /hr which
ever greater, for thickness greater
than 25 mm.
During heating, temp, variation to
be less than 1500 C with 4500 mm
length.
Cooling rates (Cooling TO 4000 C)
275
2750 C /hr for t < 25 mm.
5870 C /e0 C /hr which ever
greater for t>25 mm.
Below 4000 C, cooling in still air.
Temperature re the actual ones
determined by thermo couples.
Holding times are given in Table
4.4.5.1. but in general are 2 Heating rate- 2200 C/hr divided by the
minutes per mm thickness.
max. Metal thickness in inches. (but
not more than 2220 C/hr).
Cooling rate- 2780 C/hr divided by the
max. metal thickness in inches.
The heading and cooling rates need
not be less than 560 C/hr.
Soaking time-1 hr per inch thickness
upto 2 inches.
38
I.B.R.
39
CONTROL
40
I.B.R.
(604)
a) No welder shall be engaged on
welding o boilers or steam pipes
unless he is qualified and
possesses a certificate.
(607)
b) The certificate shall be valid for 2
years.
c) The test specimens shall be
examined under x-ray. One tensile
test, forward bend test one reverse
bend test, two macro examinations
shall be conducted. For filler welds
one root bend and one face bend
test shall have to be conducted.
41
F.3.DETAILS OF DESTRUCTIVE
TESTS FOR ALL APPROVAL
TESTS:
a)
b)
c)
d)
e)
f)
42
I.B.R.
44
I.B.R.
of the total length of the seam
shall be permitted.
b) Where the defects are located
in a single continuous length the
permissible extent of repair shall
be decided by the Inspecting
Authority.
3.6 Additional
Rejection (561):
Tests
before
45
46
I.B.R
(561)
Every portion of the longitudinal
and circumferential butt-welded
seams or the shell of the boiler
shall be subjected to radiographic
examinations.
The
methods
employed
in
obtaining the radiographs shall be
such as to show clearly difference
equal to 2% of the thickness at the
welded joints. To determine
whether this result is being
attained an indicator of approved
form which includes a portion,
equivalent to not more than 2% of
the joint thickness shall be placed
in the thickness shall be placed in
the vicinity of the weld so as to
make
a
record
on
each
radiograph.
Each section of every weld shall
be marked so that the radiographs
can be easily correlated to the
particular part of the seam
represented.
The examination shall be made
from the original films and the
acceptability of the welds shall be
decided
by
the
inspecting
Authority. The welds deemed
unsatisfactory shall be rejected or
dealt with under the condition of %
R 560 and be radio graphed
again. The films shall be retained
by the manufacturer for a
reasonable period for reference
and be available to the Inspecting
Authority, if required.
47
Ultrasonic Testing
i) Before testing weld, the present
material shall be ultrasonically
tested to establish thickness and
any flaws, which might prevent
effective weld examinations.
MARKING
Permanent marking beside the
weld shall be made to correlate
with N.D.T. reports stamping shall
not be done vessels fro low
temperature service.
48
I.B.R
49
FULL RADIOGRAPHY
For radiography and U.T. the foll. Are
unacceptable.
1. Any crack, zone of incomplete fusion
or penetration.
2. Any elongated slag inclusion which is
longer than:
50
51
I.B.R
52
= Diameter of defect.
UNACCEPTABLE DEFECTS
Planar
defects
Linear Porosity
6.0 mm for e 2.
> 75 mm
3.
Linear Porosity
4.
Linear porosity
parallel to weld
axis may
indicated lack
53
of fusion or
penetration and
thus not
permitted.
Worm
(isolated)
(D,P)
Not permitted
54
I.B.R
55
Individual and
Parallel to
major axis
Main
butt
welds
L=e 100 mm
worm e/10 4
mm
Nozzle
&
branch
welds
Inner
half of
cross
sec
Outer
quarter
of cross
sec
Worth
= e/4
4mm
I=c/4
100mm
Worth =
e/8
4mm
I=c/8
1000mm
Individual and
randomly
oriented (not
parallel to axis
of weld)
As isolated pores
Non linear
group
As localized porosity
Plate
thickness
Up to 1/2
Copper inclusions not permitted
in
(12
Under cut
Slight intermitted permitted 12.5mm)
depth < 0.5 mm
Over
Slight
intermitted
permitted
Shrinkage
(12.5 mm)
grooves & root depth < 1.5 mm
Over
1
concavity
(25.4 mm)
Excess
h 3mm
to 2 (25.4
Penetration
mm)
Reinforcement Smoot blending
Over
2
(50
mm)
Overlap
Not permitted
In U.T defects with h 1.5 mm or less should
be ignored
56
Reinforcement
1/6 in (4 mm)
5/32 in (4 mm)
Reinforcement in severe
medium duly vessels shall be:
Plate thickness
I.B.R
and
Max,
reinforcement
Up to 12
1.5
Over 12 up to 25
2.5
Over 25 up to 52
3.0
Over 4 52
4.0
For
light
duty
vessels,
reinforcement shall be < 5 mm
57
H. PRESSURE TESTING
All completed vessel must pass either All complete vessels must pass the
of the following tests?
standard hydrostatic, pneumatic or
proof test.
Standard hydraulic test: Where
required thickness of pressure parts
can be calculated.
Pneumatic test: Where thickness of
pressure parts can be calculated, but
liquid media are not practicable.
Proof
hydraulic
test:
Where
thickness of pressure parts cannot be
calculated.
Combined: Hydraulic/pneumatic test.
Method of testing
Pressure to be increased to 50% of
test pressure gradually and then in
stage of 10% until test pressure is
reached before going close for
inspection, the pressure is to be
lowered below that previously
attained.
The pressure is to be maintained for
at least 30 minutes expect in case of
vessel less than 500 mm dia, and 10
mm thick when the period may be
agreed upon.
(No shock loading (hammer testing)
allowed.
Test Pressure
Pt= 1.25 (P fa/ft X t/t-c)
Where, P= design pressure
fa= Nominal design stress
at least temperature
ft= Nominal design stress
at design
58
I.B.R.
(R 601 Hydraulic and Hammer
tests).
Test Pressure
Pt=
1.3 x
x f1/f2
design
pressure
fi=
f2=
59
t=
Nominal thickness of
section under
consideration.
c=
Corrosion allowance
60
I.B.R
61