Concrete Works
All materials used for the concrete works stated herein shall comply with
the General Concrete Specification where applicable and the requirements
specified herein.
4.3.2
Open Drains
Open surface drains shall be constructed of precast concrete drain channels
of concrete Class 'B' and to the dimensions as shown on the drawings. The
invert units shall be to B.S.340 and shall be cured for a minimum of 28
days before being laid. The sections shall be in 60 cm. lengths with a
minimum thickness of 50 mm. true to required shapes, sizes and
dimensions and have smooth internal faces. No rendering on the inside
faces will be allowed.
4.3.3
4.3.4
Scupper Drains
Scupper drains where required at openings in the roadside kerbs shall be
constructed with base slabs and side walls in situ reinforced concrete slabs of
precast concrete, all of concrete Class 'B'.
4.3.5
4.3.6
DRAINAGE