DETAILED ESTIMATE OF SURVEY WORK FOR THE CONSTRUCTION OF ROAD

FROM SALAM ABAD TO GOHALAN (RD 5700 TO RD 11700M)


LENGTH IN KMS:6.00
S.No

Item

Unit

Quantity

Rate

Amount

Jungle cutting for clearance of line through


thin bushes:Progress :
1labour/2kms=3Labours

No

3.00

173.20

519.60

Reconaissance survey in hilly


terrain:Progress:2labour/5kms

No

2.40

173.20

415.68

Carriage of survey equipments to the site of


work and back to the past station:1labour/km

No

6.00

173.20

1039.20

Levelling without chainage(Rough levelling to


achieve grade)in hilly
terrain.:Progress:10labour/1.5km

No

40.00

173.20

6928.00

Ranging without chainage of


baseline,canal/road alignments,transmission
lines and cross lines in hilly
terrain.:Progress2 labour/2.5kms

No

4.80

173.20

831.36

Taking long sections touching every 25 mtrs


and all chainage points to depth the complete
topography of N.L in hilly terrain:Progress
6Labour/0.80Kms

No

45.00

173.20

7794.00

Taking cross sections on base


lines/alignments by levelling instruments upto
a length of 80 mtrs.on either sides.:Progress
8Labour/3.0Kms

No

16.00

173.20

2771.20

Making temporary burjies along the


alignment of canals and roads at 2.5km
interval including labour for white
washing.:Progress 3Labour/1.5kms

No

12.00

173.20

2078.40

Water carier for the field works:Progress


1labour/day for 6days

No

6.00

173.20

1039.20

10

P/F country wooden pegs Rough levelling


vide item no 4:Progress:15 nos/3kms=30;Lsection vide item 6: Progress:50
Nos/0.80Km=375Nos;x-sections vide item
(7)15Nos/30kms=3Nos;Total=408Nos

No

408.00

12.00

4896.00

11

Providing and applying paint,0.5lit/km

lit

3.00

150.00

450.00

12

Engagement of vehicle for carriage of


equipment from office to site and back(Men
and material)lead 10kms from Uri to site.

LS

400.00

400.00

TOTAL

29162.64

NOTE:The survey estimate has been frammed on the basis of sanctioned schedule of rates
for survey by design directorate J&K,and the rates envisaged in the estimate from PMGSY
sanctioned shedule of labour.

NOTE:The survey estimate has been frammed on the basis of sanctioned schedule of rates
for survey by design directorate J&K,and the rates envisaged in the estimate from PMGSY
sanctioned shedule of labour.