Professional Documents
Culture Documents
Project Report On Hexamine
Project Report On Hexamine
Project Report
On
HEXAMINE
CERTIFICATE
This is to certify that Mr. , Roll no. of B.E. Semester VIIIth (Chemical)
has successfully completed his project Report on HEXAMINE, during
the academic year 2009-10.
Date of Submission:
Acknowledgement
I would like to take this opportunity to express my sincere regards and deep
sense of gratitude to my Head of the department & my guide Prof. M.G. Desai. I am
thankful to my guide Prof. M.G. Desai , for not only guiding me for this project
report, but also encouraging me and finding time for reading and commenting on
manuscript.
His encouragement kept my spirit alive and lifted my moral up to very high
level of interest during the preparation of this project report.
I am highly thankful of library staff and my guide for providing valuable
references throughout the preparation of this project report. I would like to thank my
college authorities who gave me the internet facility to get some data and other
required information.
I would also like to take this opportunity to thank all my friends without whom
support I would not be able to complete this project report in time.
Finally, my grateful acknowledgements are of those who have helped me
directly or indirectly for preparing this project report.
INDEX
SR.
NO
1.
CHP.
NO.
1.1
1.2
1.3
1.4
2.
2.1
2.2
3.
3.1
3.2
3.3
4.
CHAPTER
INTRODUCTION
Regulatory history
Uses
Health Effects
Product specification
LITERATURE SURVEY
6
7
7
7
10
10
11
13
Process selection
Process description
Schematic representation of manufacturing process
13
13
15
16
MATERIAL BALANCE
4.1
4.2
4.3
4.4
4.5
4.6
5.
ENERGY BALANCE
5.1
5.2
5.3
5.4
5.5
6.
6.1
6.2
6.3
6.4
6.5
6.6
PAGE
NO.
16
18
20
20
21
22
23
EQUIPMENT DESIGN
23
24
26
27
27
28
Design of shell
Design of head
Design of jacket
Design of agitator
Design of flange
Design of bracket support
28
31
33
34
39
45
7.
7.1
7.2
7.3
7.4
7.5
7.6
8.
50
Process control
Control centre
Instrumentation
Flow control
Ratio control
Alarm and safety trips and interlock
50
51
51
52
53
53
54
COST ESTIMATION
8.1
8.2
8.3
8.4
8.5
8.6
8.7
10.
UTILITIES
61
63
67
11.
70
Plant location
Site selection criteria
Plant layout
70
71
73
76
11.1
11.2
11.3
12.
Pollution control
Material safety data sheet
54
55
56
56
59
59
59
61
REFERENCES
CHAPTER-1 INTRODUCTION
An estimate five (5) million pounds per year of hexamine are consumed to make
commercial explosives. Hexamine demand from the phenolic resin segment has
declined due to increased competition from formaldehyde free resins and other resins
that offer performance advantages.
The production of nitrilotriacetic acid (NTA) may be the largest application for
hexamine (40 to 60 million pounds per year). However, since hexamine for this use is
manufactured as a captive intermediate (in solution) this segment is usually not
included in the production statistics.
1.3 Health Effects
Acute Health Effects: Irritating to the skin and eyes on contact. Inhalation will
cause irritation to the lungs and mucus membrane. Irritation to the eyes will
cause watering and redness. Reddening, scaling, and itching are characteristics
of skin inflammation. Follow safe industrial hygiene practices and always
wear protective equipment when handling this compound.
Unit
Standard
Content
99
Moisture
0.5
Ash
0.03
Heavy metals
0.001
Chloride
0.015
Sulphates
0.02
Ammonium
0.001
Liquid
Molecular Weight:
18-30
Freezing Point:
Critical Temperature:
Not pertinent
Critical Pressure:
Not pertinent
Specific Gravity:
Not pertinent
Not pertinent
Not pertinent
Not pertinent
Not pertinent
Heat of Combustion:
Not pertinent
Heat of Decomposition:
Not pertinent
Heat of Solution:
Heat of Polymerization:
Not pertinent
Heat of Fusion:
Limiting Value:
0.09 psia
2. Ammonia
Molecular Weight:
17.03
33.35 at 760 mm Hg
77.7
Color:
Colorless
133.0
1425 / 1657
2097.2
2226.2
2105.6
42.8
33.1
31.8
23.4
14.1
0.690
0.682
0.639
0.580
Vapor Pressure:
0.6 at 0 C
651 / 1204
3 out of 4
Flammability :
Reactivity
:
2.2 PROPERTIES OF HEXAMINE
1 out of 4
0 out of 4
Chemical name
Hexamethylenetetramine
Formula
Molecular Weight
:
:
(CH2)6N4
140.19
Sublimation Temperature
285 295C
Flash Point
250C
1.33 g/cm3
Bulk Density
Particle Size
Specific Heat
36.5 cal/C
28.8 kcal/mol
1,003 kcal/mol
Solubility in Water
20C
25C
60C
874 g/L
867 g/L
844 g/L
:
:
:
8 to 9
0.0035 mbar
CHAPTER-3
3.1 PROCESS SELECTION AND DETAIL PROCESS DESCRIPTION
PROCESS 1:
4 NH3
(CH2)6N4
+ 6 H2O
+ 746 kJ
The formation of Hexamine takes place in the reactor. Due to the large amount of
water, hexamine produced, is remain dissolved in water. Therefore from reactor it will
feed to the Triple Effect Evaporator.
The concentration of hexamine is increased from 26% to 60%. Then the concentrated
feed is charged to the crystallizer, where hexamine crystals are formed.
Hexamine in crystalline form is continuously withdrawn from the crystalliser and
separated from the mother liquor by centrifugation. The mother liquor is purified in a
filtration unit and returned to the Hexamine process. The separated Hexamine is dried
to the desired rest moisture content in a drying unit before being bagged and packed.
The Hexamine produced by this process meets highest requirements for all down
stream uses. The Hexamine crystals are pure white and show best flow characteristics.
PROCESS 2:
In this process, gaseous Ammonia from store and Formaldehyde process gas are
directly introduced into the Hexamine reactor without intermediate condensation. The
Formaldehyde process gas is generated either by a Metal Oxide Catalyst process or by
a Silver Catalyst process for the production of Formaldehyde. The formation and
crystallization of Hexamine take place in the same reactor. The heat of reaction, i.e.
the heat of formation of Hexamine, and the heat of solution of are directly used for the
evaporation of excess water, Methanol and other condensable components
accumulating in the mother liquor within the reactor. Hexamine in crystalline form is
continuously withdrawn from the reactor and separated from the mother liquor by
centrifugation. The mother liquor is purified in a filtration unit and returned to the
Hexamine process. The separated Hexamine is dried to the desired rest moisture
content in a drying unit before being bagged and packed.
CHAPTER-4
MATERIAL BALANCE:
Basis: Plant is to be designed to consume 1000-kg/batch of formaldehyde. Reactants
used:
DATA:
Components
Molecular Weight
30
17
18
140
Formaldehyde
Ammonia
Water
Hexamine
Reaction:
6CH2O +
Formaldehyde
4NH3
Ammonia
(CH2)6N4 + 6H2O
Hexamine
Water
4.1 Reactor:
Assuming 90% conversion of reactants into hexamine.
CH2O = 1000 Kg
NH3
Reactor
1
= 377.7 Kg
Hexamine = 700 kg
= 1000/0.37
= 2702.7 kg/batch (Aq. Formaldehyde solution)
water added:
= 2702.7 - 1000
= 1702.7 kg/batch
KG/BATCH
1000
1702.7
377.7
TOTAL
3080.4
OUTPUT
Hexamine
Water (produced)
Water (as reactant)
HCHO
NH3
KG/BATCH
700
540
1702.7
100
37.7
3080.4
U1 = 2500 W/m2K
U2 = 2000 W/m2K
U3 = 1000 W/m2K
Ts = 150C = 443 K (Temp of steam to the 1st effect)
Boiling point of solution in last effect = 90C
Overall temperature drop T = 150 90
= 60C
Assuming heat loads equal in all sides
Q1 =
Q2
=
Q3
U1A1T1 = U2A2T2 = U3A3T3
For equal heat transfer surface
U1T1 = U2T2 = U3T3
T1 = U2/U1 T2
T = T1 + T2 + T3
T = T1 [ 1 + U1/U2 + U1/U3 ]
60 = T1 [ 1 + 1.25 + 1.25 ]
T1 = 12C
Similarly,
T2 = 15.8C
T3 = 31.6C
Now,
T1 = Ts - T1
= 150 12 = 138C
T2 = 138 15.8 = 122.2C
T3 = 122.2 31.6 = 90.6C
Now we assume that amount water evaporated in every effect is same
i.e.
mv1 = mv2 = mv3 = mv
mf = m1 + mv1 + mv2 + mv3
mf = m1 + 3mv
10784 = 4673 + 3 mv
mv = 2037 kg
4.3 Crystallizer:
M.L. = 4920 kg
Feed = 1550.57
kg
Hexamine crystals
Crystalliz
er
= 1282.7
KG/DAY
2800
1866.68
HCHO soln
NH3 soln
1080
455.6
Total
6202.28
4.4 Centrifuge:
PPT = 987.7kg
Feed = 737.552kg
Centrifug
e
M.L.= 1193 kg
Input :
Feed
OUTPUT
Hexamine crystals
Hexamine
dissolved
Water
HCHO soln
NH3 soln
KG/DAY
1282.7
1517.3
1866.68
1080
455.6
6202.28
Hexamine = 1282.7 kg
Total = 1411 kg
Mother Lye = 1540 kg
INPUT
Hexamine
Water
Process water
KG
1282.7
384.8
1282.7
2950.2
OUTPUT
Hexamine
Water
M.L.
KG
1282.7
128.27
1540
2950.97
4.5 Drier:
Feed = 1411 kg
water)
Drier
KG
1282.7
128.27
1410.97
OUTPUT
Hexamine
Water
Water evap.
KG
1282.7
12.824
115.44
1410.964
CHAPTER-5
ENERGY BALANCE
5.1 REACTOR :
Base temp 0C
In reactor temp is 60C to 70C
Cp for HCHO soln:
3.42 KJ / Kg K
Cp for NH3:
2.226 KJ / Kg K
Cp for Hexamine:
0.153 KJ / Kg K
Cp for water:
4.176 KJ / Kg K
HEAT INPUT = m Cp t
= m Cp t HCHO + m Cp t NH3
= (2702.73.42 35+273) + (377.772.226308)
= 3105220.21 KJ / batch
HEAT OUTPUT = m Cp t
= m Cp t HCHO + m Cp tWater + m Cp tNH3 + m Cp t Hexamine
= (100.3x3.43x353) + (2242.520x4.17353) + (37.8042.226353) +
(700x0.153x353)
= 3384580.27 KJ / Batch
Heat of reaction at 68C = 745 KJ/mol
Therefore, (700/140) 745 = 3725 KJ/batch (heat generated)
CHAPTER-6
PROCESS EQUIPMENT DESIGN
6.1 Triple Effect Evaporator
Design data for the evaporator in the first effect:
Feed inlet
= 6706.5 kg
Product outlet
= 4666.68 kg
Water evaporated
= 2040 kg
Steam inlet
= 2040 kg
Pressure of steam
= 5 kg/cm2
Temperature of steam
= 150 C
= 138 C
= 3.46 kg/cm2
= 40 m2
= 2500 W/m2 C
We assume that c.s. area of tubes are 25% of the total c.s. of evaporator.
Cross section area of evaporator = 208253.7/0.25
= 833014.8 mm2
Diameter of evaporator, do : /4 do2 = 833014.8
do = 1.029 m
Downcomer area = 25% of 833014.8
= 208253.7 mm2
Diameter of downcomer = 208253.7 4 /
= 514.9 mm
MECHANICAL DESIGN
The required data are as following:
Internal pressure = 5 kg/cm2
External pressure = 1.033 kg/cm2
Poissons ratio = 0.3
Modulus of Elasticity = 1.9105 N/mm2
Allowable stress, f = 966.5 kg/cm2
Height of the evaporator, H = 2710 mm
Inside Diameter of the evaporator, Di = 1030 mm
SHELL THICKNESS:
Thickness of shell required to withstand internal pressure:
ts = P ri / (f j - O.6 P) + C.A
Where, ri = inside radius of shell
P = internal design pressure
f = maximum allowable stress
j = joint efficiency
(If we go for double welded butt joint with 10% radiography) then j = 0.85 & CA =
1.5 mm
= 4.3637 515/ (966.5 0.85-0.6 4.3637) + 1.5
2
(f = 966.5kg/cm )
= 0.42cm
ts = l.06 ts
=1.06 4.2 = 4.452 mm
Let ts = 8 mm
Thickness of shell required to withstand external pressure:
We find thickness by graphically method
Let ts = 8 mm, t = 8 - 1.5 = 6.5 mm
D0 = Di + 2t 1.5 = 1044.5 mm
L/D0= 2.59
D0/t = 160.69
From graph given in illustrated of process equipment design. (Appendix - C)
A=0.00014
B = 3500 Psi = 246.48 Kg/cm2
Pallow = B / (Do/t) = 1.533 Kg/cm2
Pd < Pallow, satisfied
So ts= 8mm
= 6.05 mm.
GASKET WIDTH:
do/di = [y-Pm]/[y-p(m-1)] ___________________(a)
where, do = outside diameter of gasket
di = inside diameter of gasket
Internal diameter of flange = O.D of shell
di= 1.046 meter
Put the value in Eq-(a) then
do/di = 1.023,
do = 1.07m
minimum gasket width = (do-di)/2 = (1.07 1.046) /2 = 0.014 m
Hence minimum gasket width N =14 mm
Basic gasket seating width bo = N/2 =7mm = 0.275 > 0.25
Effective gasket seating width b = (bo)0.5/2
= 1.323 mm
Mean diameter of gasket G = (1.07+1.046) / 2 = 1.058 m
BOLT DESIGN:
Load due to design pressure, (operating pressure)
H= (/4) G2P
= /4 (1058)2 (1.133/100) = 9960.7 kgf
Load to keep joint tight under operation
Hp = G2bmxp
= 1058 2 1.323 2.75 1.133 = 27402.36 kgf
Total operating load,
W1 = H + Hp
= 9960.7+27402.36 = 37363.06 kgf
Load to seat gasket under bolting up condition,
W2= G b y
= 1058 1.323 251.77/100 = 11071.32 kgf
Bolt area required at operating condition
Am1 = W1 / fb
= 37363.06/816.5
= 45.76 cm2
Bolt area required at bolting up condition
Am2 = W2 / fa
= 11071.32/ 1020.7
= 10.846 cm2
Root area of bolt = 0.302 x 2.5422
= 1.9483 cm2
Amax. = 45.76 cm2
So no. of bolts required. = Am / 1 .9483
= 45.76/1.9483 = 23.48
Use 24 nos. of bolts
Bolt circle diameter is, C = B + 2(g1+ R)
B = ID of shell = 1.03 m
g1 = 1.5 thickness of shell = 1.5 x 8 = 12 mm
R = (do-Do)/2 + dbh/2 + th
(dbh=22mm, assume)
(10701046)/2 + 22/2 + 8 = 31 mm
C= 1030 + 2 (12+ 31) = 1116 mm
Bolt spacing = C / n
= 1116/ 24
= 146.084mm = 146 mm
Bs is not in range of 45 to 75 mm so take n = no. of bolts = 50
Bs = 70 mm
Thickness of flange t mm,
Mo = MD + MG + MT
Where MD = HD hD
HD = hydrostatic force acting on inside area of flange
HD = /4 B2 P
= /4 (10302) (1.133/100)
= 9440.48 kgf
hD = (C-B)/2
= (1116-1030)/2
= 43 mm
MD = 9440.4843
= 405.94 kgf
M G = H G hG
HG = Wm1- /4 G2P
= 37363.06 993.07
HG = 36369.99 kgf
hG = (C-G)/2
= (1116-1058)/2
= 29 mm
MG = 1054.7 kgfm
M T = H T hT
HT = /4 G2 P - /4 B2 P
HT = 52024.54
hT = (2C B - G )/2
= 72 mm
MT = 3745.76 kgfm
MO = 405.94+1054.7+3745.76
= 5206.4 kgfm
Ma . Ffo/Ffa
= 2119 1020.7/1257.9
= 1719.42 kgfm < MO
Mmax = MO = 5206.4 kgfm
Thickness of flange.
tf = ((YMmaxCF)/fB)^0.5 + C.A.+ M.A.
here, C.A. = corrosion allowance and M.A. = mechanical allowance
Assuming that CF = 1
For SS-304 C.A. = 0
K=
= 1186/1030
= 1.15
(k2log10K/(k2-1))
Y=
Y = 25.579
tf = 11.56 cm.
tf = 115.6+5
C/n
= 2626/24
= 146 mm
Bolt pitch correction factor = CF = (Bs/(2d+t))0.5
= (146/(219.05+115.6))0.5
= 0.974
(CF)1/2 = 0.987
tf = 0.987 115.6
= 114 mm
CHAPTER:7
INSTRUMENTATION AND PROCESS CONTROL
Instrumentation and process control deal with the measurement and control of
physical conditions required for mass production of high iuality products.
Instrumentation and process control ensures high output and uniform quality of
products and to ensure that least amourt of raw material are used. Physical science
have been used to argument over sense of temperature, viscosity, pressure and color,
we arc incapable of sensing within narrow slits, dillerence in temperature, speed,
color or light intensity. It produces mechanical aids that never get tired, seldom get
into trouble but are accurate and sensitive in response for long period of time while
also eliminating the elements of human errors.
The primary objective of the designer when specifying instrumentation and control
schemes are:
A. Safe plant operation:
o To keep the process variable within safe operating limits.
o To dictate dangerous situation as they develop and provide alarm automatic
shut down system.
o To provide interlock and alarms to prevent dangerous operating system.
B. Production Rate: To achieve the desired product output.
C. Product Quality: To maintain the product composition within, the specified quaiity
standards.
D. Cost: To operate at lowest production cost commensurate with the objective but
sometimes it may be better strategy to produce a better quality at a higher cost.
E. In a typical chemical plant, these objectives arc achieved by combination of
automatic
control, manual monitoring and laboratory analysis.
The reaction vessel is the heart of the plant operation. Its performance determines
product quality and its efficiency is a major contributing factor to the total plant
production.
For temperature control cascade loop is used. The controlling variable is jacket
heating oil steam, which is allowed to adjust a jet point of a secondary loop; whose
response to change is rapid. Reaction temperature controller varies set point of jacket
temperature control ioop. The advantage of this loop is that a change in supply is
corrected for in sleeve loop and does not upset master controllers.
7.3 Instrumentation:
Selection installation maintenance and operations of an instrumentation system are of
great importance to the company. Adequate effective instrumentation provides one
way to increase quality control, while maintaining or reducing prices ir the face of
higher cost of material supplied and labour. We will describe here the instrumentation
system for temperature, pressure, and levels and flow rate measuremems. We have to
select instrument which satisfy both our perfect technical and economy.
CHAPTER-8
Cost Estimation
Cost estimation mainly consists of three parts:
1. TOTAL CAPITAL INVESTMENT
2. TOTAL PRODUCTION COST
3. PROFITABILITY
TOTAL CAPITAL INVESTMENT
FIXED
CAPITAL
INVESTMENT
WORKING CAPITAL
(10% OF FCI)
DIRECT COST
INDIRECT COST
1. Purchased equipment
2. Construction expanse
3. Contractors fees
4. Piping installation
4. Contingency
5. Electrical installation
6. Building installation
7. Yard improvement
8. Service facilities
9. land
EQUIPMENT
NO. OF
EQUIPMENT
COST IN $
COST IN Rs.
1.
Reactor
32,400
14,90,400
2.
Triple effect
evaporator
494,100
2,27,29,060
3.
Crystallizer
46,800
21,52,800
4.
Centrifuge
12,900
5,93,400
5.
Drier
155,900
71,71,400
6.
Filter bag
19,700
9,06,200
7.
Agitator
4,000
1,84,000
8.
Storage tank
104,400
48,02,400
9.
Pump
22,500
10,35,000
10.
Compressor
69,600
32,01,600
TOTAL
-------
868,340
4,42,66,260
Instrument costs, installation cost constitute the major portion of capital investment
required for instrumentation. Total instrumentation cost depends on the amount of
controller required.
This cost is always 2-8% of fixed capital investment.
For our convenience we take it as 6% of fixed capital investment.
Therefore,
Cost of instrumentation & control = 0.06 * 20,12,10,272.70
= Rs. 1,20,72,616.36 ---------------(C)
4. PIPING:
The cost of piping covers labor, valve, fitting, pipe, support & other item involved in
erection of all piping used in the process.
This cost is always 3-20% of fixed capital investment.
But For our convenience we take it as 10% of fixed capital investment.
Therefore,
Cost of piping
= 0.1 * 20,12,10,272.70
=Rs. 2,01,21,027.27 ---------------- (D)
5. ELECTRICAL INSTALLATION:
The costs for electrical installation consist primarily of installation, labor & material
for power & lighting. The electrical installation consists mainly of four major
components namely power wiring, lighting, transformation & service & instrument &
control wiring.
This cost is always2-10 % of fixed capital investment.
But For our convenience we take it as 7% of fixed capital investment.
Therefore,
Cost of electrical installation
= 0.07 * 20,12,10,272.70
= Rs. 1,40,84,719.09 ---------- (E)
6. BULIDING INSTALLATION:
The cost for building including services consists of expense for labor, material &
supply involved in the erection of all building connected with the plant. In this cost of
plumbing, heating, lighting, ventilation & similar services are included.
This cost is always 3-18 % of fixed capital investment.
But For our convenience we take it as 11% of fixed capital investment.
Therefore,
Cost of building installation
= 0.11 * 20,12,10,272.70
= Rs. 2,21,33,130 ----------- (F)
7. YARD IMPROVEMENT:
Cost of fencing, grading, roads, sidewalk, railroad siding, landscaping & similar item
constitute the portion of yard improvement.
= 0.04 * 20,12,10,272.70
= Rs. 80,48,411 ------------ (G)
8. SERVICE FACILITIES:
Utilities for supplying steam, water, power, compressed air & fuel lies in the service
facilities. Waste disposal, fire protection & miscellaneous service item such as first
aid & cafeteria equipment are included in this.
This cost is always 8-20 % of fixed capital investment.
But For our convenience we take it as 9% of fixed capital investment.
Therefore,
Cost of service facility
= 0.09 * 20,12,10,272.70
= Rs. 1,81,08,924.54 ------------- (H)
9. LAND:
The cost of land & the accompanying surveys & fees depends on the location of
property & may vary by cost factor.
This cost is always 1-2 % of fixed capital investment.
For our convenience we take it as 2% of fixed capital investment.
Therefore,
Cost of land = 0.02 * 20,12,10,272.70
= Rs. 40,24,205 ----------------- (I)
Now,
Direct Cost = (A) + (B) + (C) + (D) + (E) + (F) + (G) + (H) + (I)
= Rs. 16, 09, 68, 218 ------------------------- (A#)
B. CALCULATION OF INDIRECT COST:
1. ENGINEERING &SUPERVISION:
The cost of construction design & engineering, drafting, purchasing, accounting,
construction & cost engineering, travel, reproductions are included in this cost.
This cost is always 4-21 % of fixed capital investment.
For our convenience we take it as 12% of fixed capital investment.
Therefore,
Engineering & supervision cost = 0.12 * 20,12,10,272.70
= Rs. 2,41,45,232.72 -------- (A)
2. CONSTRUCTION EXPENSE:
This includes temporary construction & operation, construction tool & rental office,
home office at construction site etc.
This cost is always 4-16 % of fixed capital investment.
For our convenience we take it as 13% of fixed capital investment.
Therefore,
Construction expense
= 0.13 * 20,12,10,272.70
= Rs. 2,61,57,335.45 ----------- (B)
3. CONTRACTORS FEES:
The contractors fee varies for different situation but it is always 2-6 % of fixed
capital investment.
For our convenience we take it as 3% of fixed capital investment.
Therefore,
Contractors fees
= 0.03 * 20,12,10,272.70
= Rs. 60,36,308.181 ------------ (C)
4. CONTINGENCIES:
A contingency factor is usually included in an estimate of capital investment to
compensate for unpredictable events such as storms, floods, strikes, price change,
small design change etc.
This is always 5-15 % of fixed capital investment.
For our convenience we take it as 5% of fixed capital investment.
Therefore,
Contingencies
Now,
Total indirect cost
= 0.05 * 20,12,10,272.70
= Rs. 1,00,60,513.64 --------------- (D)
= (A) + (B) +(C) + (D)
= Rs. 6, 63, 99, 390 ------------------ (B#)
Therefore,
Fixed Capital Investment = Direct Cost + Indirect Cost
= (A#) + (B#)
= Rs. 22, 73, 67, 607.8
8.2 CALCULATION OF TOTAL CAPITAL INVESTMENT (TCI):
TCI = FCI + WORKING CAPITAL ---------- (1#)
Working Capital is always 10% of TCI.
Therefore equation (1#) become,
TCI = FCI + 0.1 TCI 0.9 TCI
= 22, 73, 67, 607.8
Therefore,
Rs/Kg
15
Rs/Annum
1,80,00,000
28
0.06
1,26,93,072
15,840
3,07,08,912
= 0.10 * 6,26,71,249
= Rs. 62,67,124.9--------- (b)
The cost for utilities such as steam, electricity, process & cooling water, compressed
air varies depending on the amount of consumption.
As a rough approximation it is always 10-20% of total product cost.
For our convenience we take it as 10% of total product cost.
Therefore,
Utility cost
= 0.10 * 6,26,71,249
= Rs. 62,67,124.9------------- (c)
= 0.06 * 20,12,10,272.70
= Rs. 1,20,72,616.36 ------- (d)
5. OPERATING SUPPLIES:
In any manufacturing operation, many miscellaneous supplies are needed to keep the
process functioning efficiently & it is not included in the raw material cost.
It is always 15% of maintenance & repair cost.
Therefore,
Operating supplies cost
= 0.15 * 1,20,72,616.36
= Rs. 18,10,892.45 ----------- (e)
6. LABORATORY CHARGES:
The cost of laboratory test for control of operation & for product quality is covered in
this cost.
For quick estimates, this is always 10-20% of operating labor cost.
For our convenience we take it as 10% of operating labor cost.
Therefore,
Laboratory charges
= 0.10 * 62,67,124.9
= Rs. 6,26,712.49-------- (f)
= 0.01 * 6,26,71,249
= Rs. 6,26,712.5---------- (g)
Therefore,
Direct product cost
2. LOCAL TAXES:
The magnitude of local property taxes depends on the particular locality of the plant
& regional laws.
This is always 2-4% of fixed capital investment.
For our convenience we take it as 2% of fixed capital investment.
Therefore,
Local taxes
3. INSURANCE:
Insurance rate depends on the type of process being carried out in the manufacturing
operation & on the extent of available protection facilities.
It is always 1% of fixed capital investment.
Therefore,
Insurance
Therefore
Fixed charges
Therefore,
Manufacturing cost
= 0.50 * 62,67,124.9
= Rs. 31,33,562.45 -------------- (E#)
= 0.20 * 62,67,124.9
= Rs 12,53,424.98 ---------- (k)
= 0.02 * 6,26,71,249
= Rs. 12,53,425 ---------- (l)
= 0.01 * 6,26,71,249
= Rs. 6,26,712.49 ----- (m)
4. INTEREST:
Interest is considered to be compensation paid for the use of borrowed capital.
Therefore,
General expenses
Therefore,
Total product cost
= 0.01 * 6,26,71,249
= Rs. 6,26,712.49 ----- (n)
= 390,000 * 300
= Rs. 11,70,00,000 --------- (I#)
Now,
Gross profit
Therefore,
Net profit
Now,
Rate of return
= 5.70%
Now,
Payback period:
Chapter 9
Material Safety Data Sheet
Hexamine MSDS
Section 1: Chemical Product and Company Identification
Product Name:
Methenamine
Catalog Codes:
SLM4459, SLM3688
CAS#:
100-97-0
RTECS:
MN4725000
TSCA:
TSCA 8(b) inventory: Methenamine
CI#:
Not available.
Synonym:
Hexamine; Hexamethylenetetramine
Chemical Name:
Methenamine
Chemical Formula: C6H12N4
Section 2: Composition and Information on Ingredients
Composition:
Name
CAS #
% by Weight
Methenamine
100-97-0
100
Toxicological Data on Ingredients: Methenamine: ORAL (LD50): Acute: 569 mg/kg
[Mouse].
Section 3: Hazards Identification
Potential Acute Health Effects: Hazardous in case of skin contact (irritant), of eye
contact (irritant), of ingestion, of inhalation.
Potential Chronic Health Effects:
CARCINOGENIC EFFECTS:
Not available.
MUTAGENIC EFFECTS:
Mutagenic for bacteria and/or yeast.
TERATOGENIC EFFECTS:
Not available.
DEVELOPMENTAL TOXICITY: Not available.
Repeated or prolonged exposure is not known to aggravate medical condition.
Section 4: First Aid Measures
Eye Contact:
Check for and remove any contact lenses. In case of contact, immediately flush eyes
with plenty of water for at least 15 minutes. Cold water may be used. Get medical
attention.
Skin Contact:
In case of contact, immediately flush skin with plenty of water. Cover the irritated
skin with an emollient. Remove contaminated clothing and shoes. Cold water may be
used. Wash clothing before reuse. Thoroughly clean shoes before reuse. Get medical
attention.
Serious Skin Contact:
Wash with a disinfectant soap and cover the contaminated skin with an anti-bacterial
cream. Seek immediate medical attention.
Inhalation:
If inhaled, remove to fresh air. If not breathing, give artificial respiration. If breathing
is difficult, give oxygen. Get medical attention.
Serious Inhalation:
Evacuate the victim to a safe area as soon as possible. Loosen tight clothing such as a
collar, tie, belt or waistband. If breathing is difficult, administer oxygen. If the victim
is not breathing, perform mouth-to-mouth resuscitation. Seek medical attention.
Ingestion:
Do NOT induce vomiting unless directed to do so by medical personnel. Never give
anything by mouth to an unconscious person. If large quantities of this material are
swallowed, call a physician immediately. Loosen tight clothing such as a collar, tie,
belt or waistband.
Serious Ingestion: Not available.
Section 5: Fire and Explosion Data
Flammability of the Product:
Auto-Ignition Temperature:
Flash Points:
Flammable Limits:
Products of Combustion:
Flammable.
Not available.
CLOSED CUP: 250C (482F).
Not available.
These products are carbon oxides (CO, CO2),
nitrogen oxides (NO, NO2...).
Odor:
Odorless.
Taste:
Not available.
Molecular Weight: 140.19 g/mole
Color:
White.
pH (1% soln/water): Not available.
Boiling Point:
Not available.
Melting Point:
Sublimation temperature: 280C (536F) [Lewis, R.T., Hawley's Condensed Chemical
Dictionary]
263 C [Merck Index]
Critical Temperature:
Specific Gravity:
Vapor Pressure:
Vapor Density:
Volatility:
Odor Threshold:
Water/Oil Dist. Coeff.:
Ionicity (in Water):
Dispersion Properties:
Not available.
1.331 @ -5 C (23 F) (Water = 1)
Not applicable.
4.9 (Air = 1)
Not available.
Not available.
Not available.
Not available.
See solubility in water.
Solubility:
Soluble in cold water.
Insoluble in diethyl ether.
Soluble in chloroform.
Soluble in alcohol.
Section 10: Stability and Reactivity Data
Stability: The product is stable.
Instability Temperature: Not available.
Conditions of Instability: Heat, incompatible materials
Incompatibility with various substances: Reactive with oxidizing agents.
Corrosivity: Non-corrosive in presence of glass.
Special Remarks on Reactivity:
Reacts violently with Na2O2.
Decomposes when in prolonged contact with strong acids and concentratred solutions
of organic acids.
Special Remarks on Corrosivity: Not available.
Polymerization: Will not occur.
Section 11: Toxicological Information
Routes of Entry: Inhalation. Ingestion.
Toxicity to Animals: Acute oral toxicity (LD50): 569 mg/kg [Mouse].
Chronic Effects on Humans: MUTAGENIC EFFECTS: Mutagenic for bacteria
and/or yeast.
Other Toxic Effects on Humans: Hazardous in case of skin contact (irritant), of
ingestion, of inhalation.
CHAPTER- 10
UTILITIES
(A)
Utility Requirement
(B)
Labour Requirement
1. Utilities
The work utilities is now generally used for the ancillary service needed in operation.
These services will normally be supplied form a central site facility. The utilities requi
ed include.
1. Water
2. Electricity
3. Steam requirement for process heating
4. Storage & movement of raw materials/products
5. Fire protection
6. Maintenance facilities
7. Plant sewer system and waste disposal
Water:
Water is vital for any plant following types of water used for the plant.
Cooling water:
Natural and forced draft cooling towers are generally used to provide the cooling
water required on site. Water cay bt deacon form a river, lake of form wells.
Some treatment is necessary for once through system to prevent scale f small quantity
of surface active agents is added to the water. So it increases the solubility of the salt
in the water by preventing. Prevented by adding corrosion inhibitors such as,
chromate or surfaces acidic phosphates.
Dematerialized Water:
Dematerialized water form which all the minerals have been removed by ionexchange, is used when pure water is needed for process use and as boiler feed water.
Fire water:
Requirement for fire water are intermittent and assumed that other services will be
shunt if necessary to provide sufficient water capacity. The fire water lop system
should be so designed that breakdown at a specific hydrant does nto put the entire
system out of operation. Provision should be made for emergency connection of the
fire water system into the large reservoir of water. Sea water and brackish water is
often used if plant is located at the coastal area.
Sanitary water:
It must be free disease causing bacteria and potable Treated water is chlorinated to
destroy bacteria. Sanitary water systems are operated at 20-30 psi. An elevated water
storage tank is installed to ensure uninterrupted flow of water.
Utility water:
Utility water is used for miscellaneous washing operations such as cleaning an
operating area. It should be free form sediments. Notices should be put to wan
personnel not to drive this.
Electricity:
The power required for motor drivers, righting and general use, may be generated on
site, but usual it is purchased form the local supply company. In our plant main air
blower is the high power consuming equipment. As in our plant large quantity of
excess is available, we produce power in plant itself by using steam turbine. Actually
electricity is one of the by-products of our company.
The voltage at which the supply is taken will depend on the demand. In this case three
phases 415V is used for general industrial purpose and 210V single phase for lighting
and other low l)0 requirments.
Steam:
The steam for process heating is usually generated in waste heat boilers using the
most economic fuel available. In our plant we produce steam in Reboiler-I&II Steam
is used for power generation In power plant.
CHAPTER- 11
11.1 PLANT LOCATION
The geographical location of the final plant can have stron influence on the success of
the industrial venture. Considerable care imist he exercised in selecting the plant site,
and many different factors must be considered. Primarily the plant must be located
where. the minimum cost of production and distribution can be obtained but, other
lactors such as room for expansion and safe living conditions for plant operation as
well as the surrounding community are also important. The location of the plant can
also have a crucial effect on the profitability of a project. The choice of the final site
should first be based on a complete survey of the ad and disadvantages of various
geographical areas and ultimately, on the advantages and disadvantages of the
available real estate. The various principal factors that must be considered while
selecting a suitable plant site, are briefly discussed in this section. The factors to be
considered are:
1. Raw material availability.
2. Location (with respect to the marketing area.)
3. Availability of suitable land.
4. Transport facilities.
5. Availability of fabors.
6. Availability of utilities (Water, Electricity).
7. Environmental impact and effluent disposal.
8. Local community considerations.
9. Climate.
10. Political strategic considerations.
11. Taxations and legal restrictions
Availability of Utilities:
The word utilities is generally used for the ancillary services needed in the
operation of any production process. Ihese services will normally be supplied from a
central facility and includes Water, Fuel and Electricity, which are briefly described as
follows: Water: The water is required for large industrial as well as general purposes, starting with
water for cooling, washing, steam generation and as a raw material in the production
of sulfuric acid. The plant therefore must be located where a dependable water supply
is available namely lakes, rivers, wells, seas. If the water supply shows seasonal
fluctuations, its desirable to construct a reservoir or to drill several standby wells. The
temperattire, mineral content, slit a sand content, bacteriological content, and cost for
supply and purification treatment must also be considered when choosing a water
supply. Demineralized water, from which all the minerals hav been removed is used
where pure water is needed l tIle process use, in boiler feed. Natural and forced draft
cooling towers are generally used to provide the cooling water required on site.
Electricity: Power and steam requirements are high in most industrial plants and fuel is ordinarily
required to supply these utilities. Power, fuel and steam are required for running the
various equipments like generators, motors, turbines, plant lightings and general use
and thus be considered, as one major factor is choice of olant site.
Environmental impact and Effluent Disposal:
Facalities must be provided for the effective disposal of the effluent without any
public nuisance. In choosing a plant site, the permissible tolerance levels for various
effluents should be considered and attention should be given to potential requireneuts
for additional waste treatment facilities. As all industrial processes produce waste
products, full consideration must be given to the difficulties and coat of their disposal.
The disposal of toxic and harmful effluents will be covered by local regulations, and
the appropriate authorities must be consulted during the initial site survey to
determine the standards that must be met.
Local Community Considerations:
The proposed plant must fit in with and be acceptable to the local community. Full
consideration must be given to the safe location of the plant so that it does not impose
a significant additional risk to the community.
Climate
Adverse climatic conditions at site will increase costs. Extremes of low temperatures
will require the provision of additional insulation and special heating for equipment
and piping. Similarly, excessive humidity and hot temperatures pose serious problems
and must be co:isidered for selecting a site for the plant. Stronger structures will be
needed at locations subject to high wind loads or earthquakes.
Political And Strategic Considerations:
Capital grants, lax conccsstoils, and other inducements are olten given by
governments to direct new investment to preferred locations; such as areas of high
unemployment. The availability of such grants can he the overriding consideration in
site selection.
Taxation And Legal Restrictions:
State and local tax rates on property income, unemployment insurance, and similar
items vary from one location to another. Similarly, local regulations on zoning,
building codes, nuisance aspects and others facilities can have a major influence on
the final choice of the plant site.
Conclusion: Considering the above factors the plant should be
11.3 PLANT LAYOUT :After the flow process diagrams are completed and before detailed piping, structural
and electrical design can begin, the layout of process units in a plant and the
equipment within these process unit must be planned. This layout can play an
important part in determining construction and manufacturing costs, and thus must be
planned carefully with attention being given to future problems that may arise. Thus
the economic construction and efficient operation of a process nit will depend on how
well the plant and equipment specified on the process flow sheet is laid out. The
principal factors that are considered are listed below:
1. Economic considerations: construction and operating costs.
2. Process requirements.
3. Convenience of operation.
4. Convenience of maintenance.
Costs:
Adopting a layout that gives the shortest run of co pipe between equipment, and least
amount of structural steel work can minimize the coat of construction. However, this
will not necessarily be the best arrangement for operation and maintenance.
Process Requirements:
An example of the need to take into account process consideration is the need to
elevate the base of columns to provide the necessary net positive suction head to a
pump.
Convenience of Operation:
Equipment that needs to have frequent attention should be located convenient to the
control room. Valves, sample points, and instruments should be located at convenient
positions and heights. Sufficient working space and headroom must he provided to
allow easy access to equipment.
Convenience of Maintenance: Heat exchangers need to be sited so that the tube bundles can he easily withdrawn for
cleaning and tube replacement. Vessels that require frequent replacement of catalyst
or packing should be located on the out side of buildings. Equipment that requires
(hsmanhling for maintenance, such as compressors and large pumps, should be places
under cover.
health and Safety Considerations: Blast walls may be needed to isolate potentially hazardous equipment, and confine the
effects of an explosion. At least two escape routes for operators must be provided
from each level in process buildings.
Future Plant Expansion:
Equipment should be located so that it can be conveniently tied in with any future
expansion of the process. Space should be left on pipe alleys for future needs, and
service pipes over-sized to allow for future requirements.
Modular Construction: In recent years there has been a move to assemble sections of plant at the plant
manufacturers site. These modules will include the equipment, structural steel, piping
and instrumentation. The modules are then transported to the plant site, by road or
sea. The advantages of modular construction are:
1. Improved quality control.
2. Reduced construction cost.
3. Less need for skilled labors on site.
The disadvantages of modular construction arc:
1. Higher design costs & more structural stem work.
2.More flanged constructions & possible problems with assembly, on site.