You are on page 1of 2

DETAILED ESTIMATE

I. DIRECT COST
A. LABOR COST
Clearing/Layouting
Foreman
Helper/Laborer
Subgrade Preparation
Foreman
Skilled Helper/Laborer
Form works (Install/dismanling included)
Foreman
Carpenter
Helper/Laborer
SPL - Installation of Culvert Steel Reinforcement
Foreman
Carpenter
Helper/Laborer
Concrete Works
Foreman
Helper/Laborer

QTY UNIT
68.1 sqm
1
2
3
68.1 sqm
1
4
5
29 sqm
1
1
4
6
0.0032 kgs
1
1
2
4
9.272 cum
1
6
7

MAN-HOUR
P/MAN-HOUR
0.7048 m-hr/sqm 45.83 P/m-hr
2.00 days
500 /day
2.00 days
300 /day
2
45.83
1.7621 m-hr/sqm 47.50 P/m-hr
3.00 days
500 /day
3.00 days
350 /day
3
48
6.68 m-hr/sqm 43.75 P/m-hr
4.00 days
500 /day
4.00 days
400 /day
4.00 days
300 /day
4
43.75
10,159 m-hr/kgs 46.88 P/m-hr
1 days
500 /day
1 days
400 /day
1 days
300 /day
1
47
18.12 m-hr/cum 41.07 /m-hr
3.00 days
500 /day
3.00 days
300 /day
3
41.07
Sub-Total A

TOTAL

2,200
1,000
1,200
2,200

5,700
1,500
4,200
5,700
8,400
2,000
1,600
4,800
8,400
1,500
500
400
600
1,500
6,900
1,500
5,400
6,900
24,700.00

B. MATERIALS COST
QTY
70
7.696
9
6
32
3

Cement
Fine Aggregates
Coarse Aggregates
1/2" Thick Plywood
2*2 Rough Lumber
CWN 2"

UNIT
Bags
cum
cum
Pcs
BF
Kgs

Unit Price
245 /bag
1700 /cum
1700 /cum
720 /Pcs
40 /BF
60 /kg
Sub-Total B

TOTAL
17,037
13,083
15,762
4,267
1,261
189
51,599.03

C. SPL - MANUAL HAULING COST

N/A
N/A

Sub-Total C
D. FREIGHT AND HANDLING

2 Trip

2000

4,000
4,000

Sub-Total D
E. EQUIPMENT COST

N/A
DIRECT COST TOTAL (DC)

80,299.03

II. INDIRECT COST


0% (A+B+C) OT, Supervision, Transportation
10% (A+B+C) Contractors Profit/Mark up
10% (A+B+C) Overhead,Contingency, and Miscellaneous
0% (DC+OST+CP/MU+OCM) VAT

7,629.90
7,629.90
-

INDIRECT COST TOTAL


III. TOTAL (I+II)

15,259.81
PROJECT COST

95,558.83

PROPOSED GROUTED RIPRAP


DETAILED ESTIMATE
I. DIRECT COST
A. LABOR COST
QTY UNIT
Staking and Layouting
27 sqm
Foreman
1
Helper/Laborer
2
3
Excavation - Common
5.4 cum
Foreman
1
Helper/Laborer
8
9
Hand Placed Rock Riprap 68.27 cum
Foreman
1
Skilled Helper/Laborer
2
Helper/Laborer
8
11
Concrete Works
20.48 cum
Foreman
1
Mason
1
Helper/Laborer
8
10
Backfill - w/ compaction
1.35 cum
Foreman
1
Helper/Laborer
8
9

MAN-HOUR
0.889 m-hr/sqm
1 days
1 days
1
13.33 m-hr/cum
1 days
1 days
1
3.867 m-hr/cum
3 days
3 days
3 days
3
11.72 m-hr/cum
3 days
3 days
3 days
3
53.33 m-hr/cum
1 days
1 days
1

45.83
500
300
45.83
40.28
500
300
40.28
40.91
500
350
300
41
41.3
500
400
300
41
40.28
500
300
40

RATE
P/m-hr
/day
/day
P/m-hr
/day
/day
P/m-hr
/day
/day
/day
P/m-hr
/day
/day
/day
P/m-hr
/day
/day
Sub-Total A

Amount
1,100
500
600
1,100
2,900
500
2,400
2,900
10,800
1,500
2,100
7,200
10,800
9,900
1,500
1,200
7,200
9,900
2,900
500
2,400
2,900
27,600.00

B. MATERIALS COST
Boulders
Cement
Fine Aggregate
3" D x3m Long PVC pipe
Empty Rice Sack

QTY
68.27
205
17.07
12
18

UNIT
cum
Bags
cum
pcs
pcs

Unit Price
1400 /cum
240 /bag
1700 /cum
220 /pc
15 /pc

Amount
95,578
49,154
29,015
2,640
270
Sub-Total B 176,657.15

C. MANUAL HAULING COST


Sub-Total C
D. FREIGHT AND HANDLING

2 Trip

N/A

1800 /Trip

3,600
3,600

Sub-Total D
E. EQUIPMENT COST

N/A

DIRECT COST TOTAL (DC)


II. INDIRECT COST
0% (A+B) OT, Supervision, Transportation
10% (A+B+C) Contractors Profit/Mark up
10% (A+B+C) Overhead,Contingency, and Miscellaneous
2% (DC+OST+CP/MU+OCM) VAT
INDIRECT COST TOTAL
III. TOTAL (I+II)

PROJECT COST

Page 2 of 5

207,857.15
20,426
20,426
4,974
45,825.60
253,682.75

You might also like