6: SPECIFICATION, QUANTITY
AND COSTING OF BUILDINGS
MODULE -1
FEBRUARY 1, 2019
BY
RAKESH R
Assistant Professor, BGSSAP
+91 - 9844660661
15ENG 4.6: SPECIFICATION, QUANTITY AND COSTING OF BUILDINGS
MODULE 6
STEPS
1. Assume Qty
2. Calculate QTY with respect to each item considered
3. Cost of Materials
4. Cost of Labour
5. Cost of Tools and Plant
6. Cost of Overhead and water charges
7. Profit
8. Rate per unit
Sand
Aggregates
B Cost of Labours
1. Head Mason 0.5 days 90 Per day 45 .Rs
2. Mason 3 days 70 Per day 210 .Rs
3. Skilled labour 2 days 40 Per day 80 .Rs
4. Helper 3 days 30 Per day 90 .Rs
Total cost of Material and Labour 6809 .Rs
Sand
Aggregates
Cost of Labours
1. Head Mason 2 days 90 Per day 180 .Rs
2. Mason 3 days 70 Per day 210 .Rs
3. Skilled labour 2 days 40 Per day 80 .Rs
sand. =
A Cost of Materials
1. Stones 12.5 Cu.m 120 /cu.m 1500 .Rs
2. Cement 22 cu.m 110 /cu.m 2420 .Rs
3. Sand 4.3 cu.m 160 /cu.m 688 .Rs
B Cost of Labours
1. Head Mason 0.5 days 90 Per day 45 .Rs
2. Mason 3 days 70 Per day 210 .Rs
3. Skilled labour 2 days 40 Per day 80 .Rs
4. Helper 3 days 30 Per day 90 .Rs
Total cost of Material and Labour 5033 .Rs
sand. =
B Cost of Labours
1. Head Mason 0.5 days 90 Per day 45 .Rs
2. Mason 3 days 70 Per day 210 .Rs
3. Skilled labour 2 days 40 Per day 80 .Rs
4. Helper 3 days 30 Per day 90 .Rs
Total cost of Material and Labour 5333 .Rs
Sand =
Aggregates =
B Cost of Labours
1. Head Mason 0.5 days 90 Per day 45 .Rs
2. Mason 3 days 70 Per day 210 .Rs
3. Skilled labour 2 days 40 Per day 80 .Rs
4. Helper 3 days 30 Per day 90 .Rs
Total cost of Material and Labour 2851.5 .Rs
cement=
sand=
B Cost of Labours
1. Head Mason 0.5 days 90 Per day 45 .Rs
2. Mason 3 days 70 Per day 210 .Rs
3. Skilled labour 2 days 40 Per day 80 .Rs
4. Helper 3 days 30 Per day 90 .Rs
Total cost of Material and Labour 4432.5 .Rs
As per Indian standard Size of Each Brick is 19x 9x 9 cm and size of Brick along with mortar around
it is 20x 10x 10 cm.
Volume of motor in 10 Cu.m of Brickwork is = volume of Brick masonry - Actual volume of Brick
in masonry.
= 10 – 5000 x (0.19 x 0.09 x 0.09)
= 2.3 cu.m
increase the volume by 50 % to fill frog and as wastage = 2.3 + 1.15 = 3.45 cu.m
cement=
Sand=
B Cost of Labours
1. Head Mason 0.5 days 90 Per day 45 .Rs
2. Mason 3 days 70 Per day 210 .Rs
3. Skilled labour 2 days 40 Per day 80 .Rs
4. Helper 3 days 30 Per day 90 .Rs
Total cost of Material and Labour 42555 .Rs
Sand =
B Cost of Labours
1. Head Mason 0.5 days 90 Per day 45 .Rs
2. Mason 3 days 70 Per day 210 .Rs
3. Skilled labour 2 days 40 Per day 80 .Rs
4. Helper 3 days 30 Per day 90 .Rs
Total cost of Material and Labour 3055 .Rs
Painting on a wall
Take -100 Sqm
B Cost of Labours
1. Painter 0.5 days 90 Per day 45 .Rs
2. Helper 3 days 70 Per day 210 .Rs
Total cost of Material and Labour 13355 .Rs
B Cost of Labours
1. Plumber 2 days 90 Per day 180 .Rs
2. Helper 6 days 70 Per day 420 .Rs
Total cost of Material and Labour 21300 .Rs