Report Latihan Industri Politeknik
Report Latihan Industri Politeknik
1.1
Preliminary
The industrial training was carried out at a firm or an organization
whether the students choose it or it is given to them for one whole semestar.
The main purpose of the industrial training is to produce graduates who are
ready and capable to face their profession academically or non-academically
with a high professionalism appearance.
1
Other than that, the industrial training exposes the students about the
real situation of the working class citizen. The industrial training also helps in
developing social skills in the students.
1.2
Students are only exposed to the basic theory and needed in the
fields of their own. These theory and were mainly according to the
books. With the industrial training in place, students will experience
real life situation in the field. This will make the students use their
knowledge in order to get their works done.
i.
1.2.6
1.3
Report Objectives
1.3.1
i.
ii.
iii.
work.
To expose the students on how to provide a proper
iv.
document.
To build self-confidence in the student while providing the
v.
document.
To complete the prerequisite for the student to pass
industrial training Polytechnic KPTM.
1.4
i.
ii.
iii.
iv.
and
2.1
Introduction of Firm
Organization names
Register No
26961-W
Registered Address
Business Address
Wisma PNFL
No. 8, Jalan Bangsar Utama 9,
Bangsar Utama
59000 Kuala Lumpur
Telephone No
603-22833503
Fax No
603-22826075
contact@pnfl.com.my
Website
www.pnfl.com.my
Type Of Practice
Location
Address
Taman Perling,
81200 Johor Bahru,
Johor Darul Taazim.
Telephone No
60-7-2342348
Fax
60-7-2342349
2.2
Company Background
PNFL are Chartered Quantity Surveyors (member of Royal Institution
PNFL have served many Clients ranging from Government, SemiGovernment and Statutory Bodies to private and public companies,
partnerships and individual Clients from the inception up to the completion of
building and civil engineering works.
PNFL has also planned, established, documented, implemented and
maintained a Quanlity Management System (QMS) based on the
International Standard, MS:ISO 9001:2008 Quality Management System.
2.3
Board of Directors
Executive Chairman
Dato' Hj. Nik Farid Kamil (FISM, FRICS)
Managing Director
Executive Director
Director
Director
i) Executive Chairman
DATO' HAJI NIK FARID KAMIL started his career in Quantity Surveying
in 1970 as a lecturer at the Universiti Teknologi MARA (UiTM) for three
years and in 1972 he became a co-founder of Perunding NFL Sdn.
Bhd., formerly known as Nik Farid Dan Loh Sdn. and Jurukur Bahan
BERAKAN where Dato' Haji Nik Farid Kamil has led the company's
overall development since inception. He has been involved in major
national and international projects including the Dayabumi & GPO HQ
(JV), Heritage Park Putra Jaya, Kompleks Dataran Maybank, Taman
Teknologi Malaysia, Bangunan Dewan Undangan Negeri Terengganu and
Kedah, KLIA Mosque, Hospital Universiti Kebangsaan Malaysia Cheras,
At
KLCC,
ISTAC
and
Putrajaya
projects.
He
is
the
10
11
12
13
2.5
Project Experience
PNFL has experience in various types of construction works and has been a
recognized name in the Malaysia construction industry for decades. PNFL
have many types of construction works including Civil Engineering, Office
and Commercial development, Retail and Industrial training development,
Residential, Hotel, Leisure development, Transport buildings, including
Airport Terminal and Railway stations, Hospital and Medical Centres, Public
buildings including Museum, Mosque and Educational buildings Institutions.
ii) Bank
14
iii) Residential:
Research Center
(ISTAC)
Malaysian Technology Development Park
Malaysian Technology Development Park
Petronas Industrial Training Institute
Nursing Collage, Nilai , Negeri Sembilan
v) Mosque
15
vii) Others
16
2.6
Organization Structure
EXECUTIVE CHAIRMAN
Sr. Hj. Abdul Manap
Abdullah
MANAGING DIRECTOR
Sr. Abd. Halim Rosman
EXECUTIVE DIRECTOR I
Sr. Chua Seow Kwang
TECHNICAL DIRECTORS
(4NOS)
PROJECT MANAGEMENT
QS DEPT
TECH. DEPT
JOHOR BAHRU
QUALITY MANAGEMENT
DEPT.
MS ISO 9001:2008
QUALITY MANAGEMENT
REPRESENTATIVE (QMR)
SENIOR
ZULKARNAIN AYOP
Mardiah
Taufiq
Shafie
Amirul
Hazwani
Faridah
Hawa
17
ADVISOR
Sr. Dato Hj. Nik Farid
Kamil
EXECUTIVE DIRECTOR II
Sr. Teh Siew Leong
Sr. Abd. Halim Rosman
ADMINISTRATION &
FINANCE
JOHOR BAHRU
Nur Maya
Firdaus
2.7 Mission
Precision in work
Neat in presentation
Focus on Clients needs
Leadership in services
PNFL Mission Statement : Together we move forward to continuously provide reliable, technically
excellent and value for money Quantity Surveying and Cost Consultancy
Services to our Clients
18
19
3.1 Following is the summary of all the activity carried out during training
period weekly :
Week 1
(17th December 21st December 20012)
1. Reporting in for industrial training, Perunding NFL Sdn Bhd at 8.30
am.
2. Meet with Encik Zulkarnain, who is a senior contract manager in
Perunding NFL Sdn Bhd.
3. He explains about PNFL Sdn Bhd and explain on some of the
currents projects that are organized by the firm.
4. Introduced to all of the Perunding NFL Sdn Bhd staff.
5. We were requested to see Pn Nur Maya. She explains on the rules
that need to be obeyed in the firm including the dress code.
6. Assigned to our first task which is to update all the drawings
according to their specification.
7. Check some files and need to identify each files content.
8. We were requested to do some taking off for construction drawing
and contract drawing.
9. we were given the task to differentiate each drawing to identify
addition or rejection that happens in every drawing given to us.
Week 2
(24th December 28th December 2012)
20
reference.
Christmas leave (25th December 2012)
Correcting the format of Variation Order and include value in BQ.
Make a list of drawing.
Make a taking off in revised drawing for suction tank.
Week 3
(31st December 2012 4th January 2013)
1.
2.
3.
4.
5.
Week 4
(2nd January 11th January 2013)
1.
2.
3.
4.
5.
6.
7.
Week 5
21
Week 6
(21st January 25th January 2013)
4. Provide a paperwork for request for change (RFC) for a drainage
work
5. Helping the staff to complete the transmittal table of contents.
6. Do an office management jobs
7. Maulidur Rasul leave (24 25th of January 2013)
Week 7
(28th January 1st February 2013)
1. Thaipusam leave (28th of January 2013)
2. Change the format Bills of Quantities for Water Reticulation
Week 8
(4th February 8th February 2013)
1. Folding the painting according to technique given
2. Folding the drawing were carried out for the whole week
22
Week 9
(11th February 15th February 2013)
1.
2.
3.
4.
Week 10
(18th February 22nd February 2013)
1.
2.
3.
4.
Week 11
(25th February 1st March 2013)
1.
2.
3.
4.
23
Week 12
(4th March 8th March 2013)
1. Changing the format for several matters in Elemental payment
2.
3.
4.
5.
Breakdown.
Change the format of Bills of Quantities for Water Reticulation.
Send a Quatiton email to supplier.
Inserting the rate referrences.
Typing and completing the list of drawing.
Week 13
(11th March 15th March 2013)
1.
2.
3.
4.
Week 14
(18th March 22nd March 2013)
1. Checking the E.R.I and variation order list for infra 1.
2. Do the correction for past time work .
3. Taking off for a landscape plan by summing up the number of trees.
24
4. Visit the construction site with one of the quantity surveyors (Site
Valuations).
5. Make a submission for Road and Furniture.
Week 15
(25th March 29th March 2013)
1.
2.
3.
4.
5.
Week 16
(1st April 5th April 2013)
1.
2.
3.
4.
5.
Week 17
(8th April 12th April 2013)
25
1.
2.
3.
4.
Week 18
(15th April 19th April 2013)
1. Taking off for Senai Airport project.
2. Taking off of pile cap, internal ceiling finishes, etc..
3. Completing the Variation Order work.
Week 19
(22nd April 26th April 2013)
1. Completing the Variation Order work.
2. Typing and completing the list of drawing for Senai Airport project.
Week 20
(29th April 2th May 2013)
1. Taking off for Senai Airport project
2. Taking off the Guard House element for Senai Airport project.
3. Given an example of letter from supervisor.
26