WITHUS TECHNOLOGY PTE LTD

10 Anson Road #05-19B International Plaza Singapore 079903


Tel : + 65 6221 2212 Fax : + 65 6221 3367

Daily Report Form


Date: 30 May 2008
Project Title: STM TPY 4b
Scheduled completion date: 23 July 2008

Project Staff in-charge: Mr Toh (APM)

Manpower: Working Hours: Work delayed (Specify below)


MFI 4 men 9am – 6pm Nil
Tactsser Engr 18 men 9am – 9pm Nil
Withus 4 men 8am – 7pm Nil

Description of work done


1. Installation of coldroom panels.
2. Touching up structure paint colour
3. Silicone caulking works above coldroom panels
4. Epoxy painting along gridline 1 partition

Percentage Work Completed


a. Structural works
i) hollow sections 100%
ii)I-Beam 100%
iii)unistruct 100%
b. Flooring (pvc tiles) 95%
c. Coldroom panels delivery 100%
d. Coldroom panels 90% - Installation in progress

Site issue
Nil

Delivery schedule (If any)


Nil

Work forecast for Saturday (31/05/08)


1. Coldroom panels installations
2. Coldroom panel silicone caulking works
WITHUS TECHNOLOGY PTE LTD
10 Anson Road #05-19B International Plaza Singapore 079903
Tel : + 65 6221 2212 Fax : + 65 6221 3367
Progress Photographs

Painting works for partition along gridline 1 in progress