SUBJECT: METHOD STATEMENT FOR CHILLED WATER LINE HOT
TAPPING WORK 20th Feb 2010
Rev. 0
1.0 Carry out site survey to identify the pipe to be Hot Tapping Area.
2.0 Submit clearance form with necessary sketches or photo to Central Manager for approval.
3.0 To obtain work permit, hot work permit and storage area for material.
4.0 To remove any optical object for the Hot Tapping area and diversion area.
7.0 Customer is to ensure that the flow rate limitation during hot tapping, maximum 7 ft/s
(for liquid or Steam line).
14.0 Pressure test 1.5 time of the operating pressure and hold for 30 minutes.
17.0 To install Hot Tapping Equipment onto the gate valve or ball valve.
19.0 Start Coring depending of the size, until completion. (Estimated 2 hours)
20.0 Dismantle the Hot Tapping Equipment and proceed to the next Hot Tapping Area.
►Pipe Freezing ►Hot Tapping ► Line Stopping ► Leak Detection ► Leak Repair ► Corrosion Protection ► Hot & Cold Insulation
► Tie-in Projects ► Thickness Measurement ► Consultancy Services ►Field Equipment Rental ► Leak Repair Products
TM
HOT TAPPING WORK
-- End --