BILL

Soil investigation work from Kalpakkam to Kanchipuram 230KV Transmission Line

s. Description Unit

No
1 Mobilisation and demobilization charges Per
For men & Equipment to the site Rig

2 Erection of Platform in water to enable


boring work to the required depth
Including all materials and labour for Per
erecting and dismantling to the platform Bore
After the last consisting of 3 bores in water
Boring 100mm/150mm dia standard soil
investigation bore hole upto refusal strata
foundation.

3 Which ever comes earlier, Conducting


Standard penetration test at 1.0m or part
there of upto 10m below EGC and at 2.0m
interval from 10.0m to 20m.

a,EGL to 10.0m (SPT interval 1.0m or Part


there of )

b,From 10m to 28.50m depth