1 2 3 4 5 6

Inputs
Forecast demand 8 14 15 14 15 17
Workforce level 8 14 15 14 15 17
Undertime 0 0 0 0 0 0
Overtime 0 0 0 0 0 0

Derived
Utilized time 8 14 15 14 15 17
Hires 0 6 1 0 1 2
Layoffs 4 0 0 1 0 0

Calculated
Utilized time cost 16000 28000 30000 28000 30000 34000
Undertime cost 0 0 0 0 0 0
Overtime cost 0 0 0 0 0 0
Hiring cost 0 6000 1000 0 1000 2000
Layoff cost 2000 0 0 500 0 0
Total Cost 18000 34000 31000 28500 31000 36000

Overtime = 3000
Time cost = 2000
Undertime = 1000
Layoff = 500
Hiring = 1000
Uitgaand van 21 werkdagen in de maand
3 ploegen dienst
Januari= 12 werknemers
7 8 9 10 11 12 Total

16 21 21 21 21 23 206
16 21 21 21 21 23 206
0 0 0 0 0 0 0
0 0 0 0 0 0 0

16 21 21 21 21 23 206
0 5 0 0 0 2 17
1 0 0 0 0 0 6

32000 42000 42000 42000 42000 46000 412000


0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 5000 0 0 0 2000 17000
500 0 0 0 0 0 3000
32500 47000 42000 42000 42000 48000 432000
1 2 3 4 5 6
Inputs
Forecast demand 8 14 15 14 15 17
Workforce level 20 20 20 20 20 20
Undertime 12 6 5 6 5 3
Overtime 0 0 0 0 0 0

Derived
Utilized time 8 14 15 14 15 17
Hires 8 0 0 0 0 0
Layoffs 0 0 0 0 0 0

Calculated
Utilized time cost 16000 28000 30000 28000 30000 34000

Undertime cost 12000 6000 5000 6000 5000 3000

Overtime cost 0 0 0 0 0 0
Hiring cost 4000 0 0 0 0 0
Layoff cost 0 0 0 0 0 0
Total Cost 32000 34000 35000 34000 35000 37000

Overtime = 3000
Time cost = 2000
Undertime = 1000
Layoff = 500
Hiring = 1000
Uitgaand van 21 werkdagen in de maand
3 ploegen dienst
Januari= 12 werknemers
7 8 9 10 11 12 Total

16 21 21 21 21 23 206
20 20 20 20 20 20 240
4 0 0 0 0 0 41
0 1 1 1 1 3 7

16 20 20 20 20 20 199
0 0 0 0 0 0 8
0 0 0 0 0 0 0

32000 40000 40000 40000 40000 40000 398000

4000 0 0 0 0 0 41000

0 3000 3000 3000 3000 9000 21000


0 0 0 0 0 0 4000
0 0 0 0 0 0 0
36000 43000 43000 43000 43000 49000 464000
1 2 3 4 5 6 7
Inputs
Forecast demand 8 14 15 14 15 17 16
Workforce level 12 15 15 15 15 17 17
Undertime 4 1 0 1 0 0 1
Overtime 0 0 0 0 0 0 0

Derived
Utilized time 8 14 15 14 15 16 21
Hires 0 3 0 0 0 2 0
Layoffs 0 0 0 0 0 0 0

Calculated
Utilized time cost 16000 28000 30000 28000 30000 32000 42000
Undertime cost 4000 1000 0 1000 0 0 1000
Overtime cost 0 0 0 0 0 0 0
Hiring cost 0 3000 0 0 0 2000 0
Layoff cost 0 0 0 0 0 0 0
Total Cost 20000 32000 30000 29000 30000 34000 43000

Overtime = 3000
Time cost = 2000
Undertime = 1000
Layoff = 500
Hiring = 1000
Uitgaand van 21 werkdagen in de maand
3 ploegen dienst
Januari= 12 werknemers
8 9 10 11 12 Total

21 21 21 21 23 206
21 21 21 21 23 213
0 0 0 0 0 7
0 0 0 0 0 0

21 21 21 21 23 210
4 0 0 0 2 11
0 0 0 0 0 0

42000 42000 42000 42000 46000 420000


0 0 0 0 0 7000
0 0 0 0 0 0
4000 0 0 0 2000 11000
0 0 0 0 0 0
46000 42000 42000 42000 48000 438000