SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - August 2004)

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Glass & Glazing Receiving and Storage Inspection SAIC-M-1057 18-May-05 CIVIL-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A Receiving Inspection

Glass & glazing including accessories shall be received based on the


A1 Applicable P.O.
specifications and description as written in the Purchase Order.

Elastomeric Joint Sealant materials shall be certified by the manufacturer


SAES-M-100
A2 as to their type, class, grade and uses.
Sec. D
(1997 UBC, Sec. 24006.2)

Glass shall be flat, textured or wired, transparent or tinted and of suitable


SAES-M-100
A3 quality for general glazing applications.
Sec. D
(1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2)

Tolerances on length and width shall be + 6.4mm; Maximum tolerances


SAES-M-100
A4 on thickness shall be -12% to +27%.
Sec. D
(1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2)

Chemically strengthened glass shall have the same dimensional


SAES-M-100
A5 tolerances as standard glass.
Sec. D
(1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2)

Tolerances on flatness for tempered or heat treated glass is + 25% of the SAES-M-100
A6
thickness. (1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2) Sec. D

Tolerances on localized warp for tempered or heat treated glass shall be


from 1.6mm over 300mm length for rectangular glass and up to 2.4mm's SAES-M-100
A7
for strip glass. Sec. D
(1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2)

For Architectural flat glass clad polycarbonates made with annealed


glass, the edges can be cut, sawed, ground, mitered, seamed or
SAES-M-100
A8 beveled; All other types of glass clad polycarbonates shall not be
Sec. D
reworked on site.
(1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2)

Tolerances on haze and imperfections in glass clad polycarbonates shall


SAES-M-100
A9 be limited to 2.5% of the total area.
Sec. D
(1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2)

All cutting to overall dimensions, drilling, notching, grinding, sand blasting


or etching shall have been performed prior to strengthening or tempering SAES-M-100
A10
the outer sheets of glass; These operations shall not occur in the field. Sec. D
(1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2)

Surfaces of the installed gasket material shall be reasonably smooth and


SAES-M-100
A11 free of excessive talc or bloom. (1997 UBC, Sec. 2401.4 & UBC
Sec. D
Standards 24.1 & 24.2)

Page 1 of 2
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Glass & Glazing Receiving and Storage Inspection SAIC-M-1057 18-May-05 Civil
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Resilient Poly Vinyl Chloride profile gasket extrusions shall be made of


SAES-M-100
A12 weatherable rigid material.
Sec. D
(1997 UBC, Sec. 2401.4 & UBC Standards 24.1 & 24.2)

B Storage Inspection

Glass and polycarbonate packaging shall be the manufacturer's standard


SAES-M-100
B1 packaging unless specified otherwise by Saudi Aramco.
Sec. D
(1997 UBC, Sec. 2406.2)

REMARKS:

REFERENCE DOCUMENTS:
1- SAES-M-100 -- Saudi Aramco Building Code, 29 January 2003
2- 1997 UBC -- Uniform Building Code, 1 January 1997

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 2 of 2