Bts Commissioning / Integration • Pha ses: • • Hw Conf igura tion with W iz a rd Tr a nsmission c onf igur a tion w ith Hub Ma nage r • Bts Comm issioning with BTS ma na ge r • Te sts • Loop test s during BT S commissioning • T RX power measurem ent • Calls and Handovers • Alarm tests • Checkings • Com issioning and Inte gra tion pa rt of Site Folde r is f ille d during this pr oc e dure .
• TESTS • TRX loop tests • Tests TRXs RF and BB parts • Make during commissioning • If connection to BSC test is run automatically • If no connection to BSC run manual tests • If test fails check RX and TX cabling • Change TSDA if test is failing and cabling is correct
• TESTS • Abis loop tests • Tests connection between BSC and TRX • Made during integration • If connection to BSC test is run automatically • If no connection to BSC test is not possible • If test fails check crosconnections between BB2A and TSDA • Change BB2A or TSDA if test is failing and crosconnections are ok
• TESTS • TRX power test • Tests transmitter output power and SWR of whole antenna line • Test is done after commissioning and before integration • Connect power meter between DVDA and internal feeder • Power should be 41 dBm ± 1.5 dBm if configuration is 2:1, two TRX:s to same antenna with WCDA • Power should be 44.5 dBm ± 1.5 dBm if configuration is one TRX:s to one antenna without WCDA • SWR should be always less than 1.3
• TESTS • Making TRX power test • After commissioning with BTS manager disconnect transmission cables from FXC card • Connect power meter • Give use current command from BTS SW menu • Wait until BCF is in supervisory state and TRXs are in configuring state
• TESTS • Alarm test • During this test is tested that alarms generated by BTS and Site Support are reported properly to NMS • Site Support AC mains break down alarm • Switch OFF AC to Site Support cabinet • Check AC mains break down alarm is seen on BTS manager and call to NMS and verify that alarm is also seen there • Switch AC ON and check alarm is cleared
• Bts Cabinet door switch alarm
• Check BTS cabinet door open is seen in NMS when cabinet door is open
• FINISHING • CHEKINGS • Before leaving site chek: • BTS master clock dac word is between 1500 -2500, if not measure 13 MHz clock. Dac word is checked with BTS manager. 13 MHz clock is measured from connector on BOIA unit • All cabinets, units and cables installed properly • All cable connectors in BTS cabinet are thighten and cable labels are installed • All Unit thumb screws are thighten • All fans including cabinet fans in door are working • No alarms on NMS • All faults and missing items are reported • Site Folder is filled