Professional Documents
Culture Documents
Chart
Chart
GENERATOR
11 KV power scheme to be finalised.Approval from Inspectorate of electrical is required. Commissioning of both the switch-board must be completed before the steam blowing i.e. 16th of Aug. Commissioning of Genset will be started after steam blowing & turbine rolling i.e. 23th Aug
CHP
PLC system checking & simulation under progress. No load trial to be taken by 10th July & load trial to be taken 7 days prior to steam blowing i.e. 09th of Aug
30 TPH BOILER
at present work in 30TPH boiler is not going on as contractor has not engaged manpower for above job because the contractor is concentrating on the 36TPH afbc boiler, however work on 30TPH can progress parallaly, we are also going to conduct hydro-test for the pressure parts on 10th July, which will additionally open up all the work fronts in the 30TPH boiler .once sufficient manpower is deployed by contractor, the above jobs may be completed within 03 months & boiler can be commissioned.
TURBINE
Commissioning of turbine will take place after commissioning of DM plant, CHP, boiler. Completion of steam line & steam blowing.
Note: The status of the power plant and the details of plan of action for the commissioning of the plant is elaborated in the respective annexure below.