ITPC IGW Project Issues Status

No.

Item
Four MGws Hardware relocation/installation done in all sites (Mammon, Zayona, Basrah, and Ninawa) .
Connection cables for E1's between OMS and DDF Fiber cables between OMS and MGW

Status
- Done

1
2 3 4

- Done for all sites - Done for all sites only for ninawa central done for 3 stms only

All MGW's (4 MGW) powered on , only we have some boards faulty in Mousil MGW . ROJ 208 365/10 R4A (MXB4 PIU) QTY: 1 ROJ 208 135/20 R3A (ISER GigE FX SX ) QTY : 1 ROJ 208 372/3 R8A (MSP3 STM1) QTY: 2 Connection between MGW's ISER's and PDN done but in test case , we are waiting cables and SFP's to reach us from tareq so we can connect the cable permanently

- We have the boards now and we will continue on Tuesday

- Ninawa to be done after Eid - Mammon we will be on site tomorrow and we will work on any pending issue (fiber connection and OMS configuration). - Zayona Done. - Basrah we need cobbler to finish the connection between MGWs and PDN. - Done for (ninawah central , basra and Zayona) for mamoon we will continue tomorrow , but we need confirm from maen . - Mail send to Navid to order them (Kaswara will follow up) - Not available on local market - Secured from local market & it is working - Done 845 national 8487 International - Request was send to customer by Zaid on Tue 8/23/2011 -I called zaid (ITPC Employee) and we arranged an urgent meeting today with Miss Zaynab.i went to ITPC and talked with Miss Zaynab,she will give us the update tomorrow at 12 oclock. - Two cables out of 6 were found. - Remaining 4 cables we will check them tomorrow..

6 7 8 9

Start with OMS work for all sites Missing 3 SFP connectors for OMS (SFP required: SE code : SU66AA / STM1 1.1 100BASESE-LX10) Quantity: 3 Check LCT serial cable for OMS (Should come with OMS HW Status of requested IGW signaling point codes (National SPC & International SPC)

10

ITPC IGW DT2 template to be filled by customer ASAP in order to start our preparations for DT2 configuration.

11

Check required Cables below:

cable between GESB-B to EXB is missing (not show stopper for the integration) 3 cables between GARP to EXB is missing (not show stopper for the integration) 2 cables for APG ETH2 to the EXB (not show stopper for the integration)

12

Synchronization reference clock for the IGW nodes to avoid problems with the carriers

-Samer will send letter to ITPC to provide sync clock.